Skip to content
GharKundli

ANJANEYA BLISS

by YASH INFRAVENTURES · Mouza-Lendhra, NagpurAlso near Laxmi Nagar, Bajaj Nagar, Shankar Nagar

Possession date of ANJANEYA BLISS: 30 October 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1190002501837, and currently active. Its completion date is now October 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ANJANEYA BLISS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ANJANEYA BLISS has moved

  1. 30 June 2029

    Completion date given when the project was registered

  2. 30 October 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ANJANEYA BLISS’s extension records on MahaRERA (PR1190002501837), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ANJANEYA BLISS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1190002501837
Status
Registered and active
Builder
YASH INFRAVENTURES
Location
Mouza-Lendhra, Nagpur · 440010
Project type
Residential / Group Housing
Registered on
23 Dec 2025
Completion date at registration
June 2029
Latest completion date
October 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
24
Sold or booked
15%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of ANJANEYA BLISS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ANJANEYA BLISS100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • ANJANEYA BLISS: covers 14 floors

Latest CC order on MahaRERA: dated 25/11/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ANJANEYA BLISS every month.

ANJANEYA BLISS: buildings, flats and land, as filed on MahaRERA

  • Buildings: ANJANEYA BLISS (14 floors, 24 units)
  • Car parking: 23 covered
  • Land: 1,045 sq m (about 0.3 acres) · sanctioned built-up 3,203 sq m
  • Boundaries filed include: Flats of Postal Audit Society
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Yash Infraventures has 3 projects on MahaRERA since 2024, this one included. Of the 3 GharKundli has checked: 3 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of ANJANEYA BLISS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ANJANEYA BLISS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ANJANEYA BLISS

What is the possession date of ANJANEYA BLISS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ANJANEYA BLISS in Mouza-Lendhra, Nagpur is 30 October 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ANJANEYA BLISS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ANJANEYA BLISS's builder has filed on MahaRERA, the official one, is 30 October 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of ANJANEYA BLISS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ANJANEYA BLISS in Mouza-Lendhra, Nagpur is PR1190002501837.

Is ANJANEYA BLISS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ANJANEYA BLISS is registered as PR1190002501837 and its status is "Registered and active".

What is the construction status of ANJANEYA BLISS?

According to GharKundli's check of MahaRERA records (updated October 2026), ANJANEYA BLISS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ANJANEYA BLISS is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does ANJANEYA BLISS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is ANJANEYA BLISS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ANJANEYA BLISS is registered on MahaRERA as PR1190002501837, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ANJANEYA BLISS's possession date changes?

The latest dates are on ANJANEYA BLISS's MahaRERA page (PR1190002501837). GharKundli's Kundli Watch sends a free WhatsApp update on ANJANEYA BLISS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ANJANEYA BLISS have?

According to GharKundli's check of MahaRERA records (updated October 2026), ANJANEYA BLISS has one building filed: ANJANEYA BLISS with 14 floors and 24 units.

How much parking does ANJANEYA BLISS have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 23 covered car parking spaces for ANJANEYA BLISS.

How big is the land of ANJANEYA BLISS?

According to GharKundli's check of MahaRERA records (updated October 2026), ANJANEYA BLISS stands on 1,045 sq m of land (about 0.3 acres), with 3,203 sq m of sanctioned built-up area.

What is the track record of ANJANEYA BLISS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Yash Infraventures has 3 projects on MahaRERA since 2024, this one included. Of the 3 GharKundli has checked: 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ANJANEYA BLISS?

Google Maps has reviews of ANJANEYA BLISS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ANJANEYA BLISS?

ANJANEYA BLISS by YASH INFRAVENTURES is in Mouza-Lendhra, Nagpur (pincode 440010), near Laxmi Nagar, Bajaj Nagar, Shankar Nagar, Maharashtra, and is registered on MahaRERA as PR1190002501837, per GharKundli's check of MahaRERA records. Its boundaries filed there include Flats of Postal Audit Society.

How many homes are in ANJANEYA BLISS?

According to GharKundli's check of MahaRERA records (updated October 2026), ANJANEYA BLISS has 24 homes in 1 tower registered on MahaRERA, and 15% of them are sold or booked.

When was ANJANEYA BLISS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ANJANEYA BLISS was registered on MahaRERA on 23 December 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on ANJANEYA BLISS?

No court cases are listed for ANJANEYA BLISS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of ANJANEYA BLISS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is YASH INFRAVENTURES, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2029 in Nagpur →

Other projects in Nagpur (Urban)

All 75 projects in Shankar Nagar (440010) →

Other projects by YASH INFRAVENTURES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.