by SHREE BALAJI ASSOCIATES · Mulund West, Mumbai 400080Also near Bhandup West, Mulund East, Off Dmart

What’s in the report? →

Possession date of Meghdoot (MahaRERA P51800004699): 31 December 2026, moved from 30 June 2021 (66 months later). No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800004699, and currently active.

Source: MahaRERA website — records for P51800004699, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Meghdoot?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Meghdoot has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51800010232)

    Reason the builder gave MahaRERA:
    “We have Real Estate project registered with MahaRERA authority with name “MEGHDOOT” vide Certificate No. P51800004699. Due date for the completion of the project as estimated at the time of the registration was 31st December 2020. Thereafte…” Read the full reason“We have Real Estate project registered with MahaRERA authority with name “MEGHDOOT” vide Certificate No. P51800004699. Due date for the completion of the project as estimated at the time of the registration was 31st December 2020. Thereafter due to Notification/Order No 13 and 14 dated 2nd April 2020 and 18th May 2020 respectively issued by MahaRERA an extension of six months received and date of completion became 30th June 2021. Construction Status of the Project: There were two wings A & B registered at the time of registration with MahaRERA. Out of the two wings, Construction of all the…”
  3. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800016925)

    Reason the builder gave MahaRERA: “We are in a process of completion of finishing work and obtaining of the approval for OC. In this light we request you to kindly grant the extension.”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800019542)

    Reason the builder gave MahaRERA:
    “RCC Work of the building is completed in full. 90% of the Finishing Work is also completed as mentioned as per latest Architect Certificate enclosed. We need extension for project completion date up-to 31-Dec-2024 for obtaining of Occupatio…” Read the full reason“RCC Work of the building is completed in full. 90% of the Finishing Work is also completed as mentioned as per latest Architect Certificate enclosed. We need extension for project completion date up-to 31-Dec-2024 for obtaining of Occupation Certificate (OC) of the building. Further in response to the queries raised at scrutiny level, we hereby state as under: - 1) Form 1 Up-to 30-03-2024, Form 2 Up-to 31-12-2023, Form 2A Up-to 31-03-2024 and Form 3 Up-to 31-12-2023 are duly complied and uploaded in the relevant document upload tab, 2) Recent Disclosure of Sold/Booked Inventories Up-to 15-0…”
  5. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51800028042)

    Reason the builder gave MahaRERA:
    “We have enclosed the Annexures of the individual consents with the Format B Application. More than 95% of the construction work is completed as evidenced by the latest Architect Certificate for the quarter ended 31-12-2025 uploaded on the R…” Read the full reason“We have enclosed the Annexures of the individual consents with the Format B Application. More than 95% of the construction work is completed as evidenced by the latest Architect Certificate for the quarter ended 31-12-2025 uploaded on the RERA portal. For completion of pending work of Car Lift, One Passenger Lift, Tower Parking work and for obtaining of Occupation Certificate (OC) and other related compliances we seek extension of project completion date up-to 31-Dec-2026. More than 51% consents of the allottees other than existing Members / Tenants as per Format- B as per circular No. 28A…”

Source: Meghdoot’s extension records on MahaRERA (P51800004699), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Meghdoot

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800004699
Status
Registered and active
Builder
SHREE BALAJI ASSOCIATES
Location
Mulund West, Mumbai · 400080
Project type
Others
Registered on
9 Aug 2017
Completion date at registration
June 2021
Latest completion date
December 2026
Delay so far
66 months
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Meghdoot, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MEGHDOOT - A100%100%98%98%
MEGHDOOT - B100%95%95%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Meghdoot every 1–2 months.

Meghdoot: buildings, flats and land, as filed on MahaRERA

  • Buildings: MEGHDOOT - A (20 floors) · MEGHDOOT - B (22 floors)
  • Land: 1,668 sq m (about 0.4 acres) · sanctioned built-up 2,525 sq m · recreational space 237 sq m
  • Boundaries filed include: DR AMBEDKAR ROAD, PURSHOTTAM KHERAJ ROAD
  • Land, as filed: CTS NO 1311,1311/1 TO 15
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Meghdoot →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Meghdoot: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Meghdoot

What is the possession date of Meghdoot?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Meghdoot in Mulund West, Mumbai is 31 December 2026 — 66 months later than 30 June 2021, the date given at registration.

The date has already moved 66 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Meghdoot?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Meghdoot's builder has filed on MahaRERA, the official one, is 31 December 2026, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Meghdoot extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Meghdoot's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2022, giving the reason "We have Real Estate project registered with MahaRERA authority with name “MEGHDOOT” vide Certificate No. P51800004699. Due date for the completion of the project as estimated at the time of the registration was 31st December 2020. Thereafter due to Notification/Order No 13 and 14 dated 2nd April 2020 and 18th May 2020 respectively issued by MahaRERA an extension of six months received and date of completion became 30th June 2021. Construction Status of the Project: There were two wings A & B registered at the time of registration with MahaRERA. Out of the two wings, Construction of all the…"; to 31 December 2023, giving the reason "We are in a process of completion of finishing work and obtaining of the approval for OC. In this light we request you to kindly grant the extension."; to 31 December 2024, giving the reason "RCC Work of the building is completed in full. 90% of the Finishing Work is also completed as mentioned as per latest Architect Certificate enclosed. We need extension for project completion date up-to 31-Dec-2024 for obtaining of Occupation Certificate (OC) of the building. Further in response to the queries raised at scrutiny level, we hereby state as under: - 1) Form 1 Up-to 30-03-2024, Form 2 Up-to 31-12-2023, Form 2A Up-to 31-03-2024 and Form 3 Up-to 31-12-2023 are duly complied and uploaded in the relevant document upload tab, 2) Recent Disclosure of Sold/Booked Inventories Up-to 15-0…"; to 31 December 2026, giving the reason "We have enclosed the Annexures of the individual consents with the Format B Application. More than 95% of the construction work is completed as evidenced by the latest Architect Certificate for the quarter ended 31-12-2025 uploaded on the RERA portal. For completion of pending work of Car Lift, One Passenger Lift, Tower Parking work and for obtaining of Occupation Certificate (OC) and other related compliances we seek extension of project completion date up-to 31-Dec-2026. More than 51% consents of the allottees other than existing Members / Tenants as per Format- B as per circular No. 28A…".

What is the RERA number of Meghdoot?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Meghdoot in Mulund West, Mumbai is P51800004699.

Is Meghdoot registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Meghdoot is registered as P51800004699 and its status is "Registered and active".

What is the current construction status of Meghdoot? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Meghdoot's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 95% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Meghdoot have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Meghdoot safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Meghdoot is registered on MahaRERA as P51800004699, its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Meghdoot?

Meghdoot is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Meghdoot?

For a flat in Meghdoot (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Meghdoot received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Meghdoot is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Meghdoot uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Meghdoot was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Meghdoot's possession date changes?

The latest dates are on Meghdoot's MahaRERA page (P51800004699). GharKundli's Kundli Watch sends a free WhatsApp update on Meghdoot every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Meghdoot have?

According to GharKundli's check of MahaRERA records (updated October 2026), Meghdoot has 2 buildings filed: MEGHDOOT - A with 20 floors; MEGHDOOT - B with 22 floors.

How big is the land of Meghdoot?

According to GharKundli's check of MahaRERA records (updated October 2026), Meghdoot stands on 1,668 sq m of land (about 0.4 acres), with 2,525 sq m of sanctioned built-up area and 237 sq m of recreational open space.

What are the reviews of Meghdoot?

Google Maps has reviews of Meghdoot written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Meghdoot?

Meghdoot by SHREE BALAJI ASSOCIATES is in Mulund West, Mumbai, pincode 400080 (near Bhandup West, Mulund East, Off Dmart), Maharashtra, and is registered on MahaRERA as P51800004699, per GharKundli's check of MahaRERA records. Its boundaries filed there include DR AMBEDKAR ROAD, PURSHOTTAM KHERAJ ROAD. Its land is filed as CTS NO 1311,1311/1 TO 15. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).

When was Meghdoot registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Meghdoot was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Does Meghdoot have any legal issues or court cases?

No court cases are listed for Meghdoot on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Meghdoot?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE BALAJI ASSOCIATES, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Mulund West (400080)

All 303 projects in Mulund West (400080) →

Other projects by SHREE BALAJI ASSOCIATES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.