Skicon Skicity Phase 1
by Skicon Infrastructure Co · Bhandup West, Mumbai 400078Also near Kanjur, Powai IIT, Bhandup EastRegistered on MahaRERA as “Skicity Phase 1”
What’s in the report? →Possession date of Skicon Skicity Phase 1 (MahaRERA P51800007336): 30 April 2027, moved from 30 December 2023 (36 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800007336, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800007336, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Skicon Skicity Phase 1?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Skicon Skicity Phase 1 has moved
30 December 2023
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT51800018509)
Reason the builder gave MahaRERA: “Due to delay in some approvals and procedures including handover of road setback area , the project got delayed.”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Skicon Skicity Phase 1’s extension records on MahaRERA (P51800007336), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Skicon Skicity Phase 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007336
- Status
- Registered and active
- Builder
- Skicon Infrastructure Co
- Location
- Bhandup West, Mumbai · 400078
- Project type
- Others
- Registered on
- 17 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- April 2027
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Skicon Skicity Phase 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Skicity | 100% | 100% | 100% | 95% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Skicon Skicity Phase 1 every 1–2 months.
Skicon Skicity Phase 1: buildings, flats and land, as filed on MahaRERA
- Buildings: Skicity (25 floors)
- Land: 2,876 sq m (about 0.7 acres) · sanctioned built-up 7,149 sq m · recreational space 698 sq m
- Boundaries filed include: Lake Road, Bahirji Naik Marg
- Land, as filed: Part of CTS nos 210/38A, 210/38B, 210/39 to 88 of Village Bhandup
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Skicon Infrastructure has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA.
Read Google reviews of Skicon Skicity Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Skicon Skicity Phase 1: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Skicon Skicity Phase 1
What is the possession date of Skicon Skicity Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Skicon Skicity Phase 1 in Bhandup West, Mumbai is 30 April 2027 — 36 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Skicon Skicity Phase 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Skicon Skicity Phase 1's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Skicon Skicity Phase 1 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Skicon Skicity Phase 1's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Due to delay in some approvals and procedures including handover of road setback area , the project got delayed.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Skicon Skicity Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Skicon Skicity Phase 1 in Bhandup West, Mumbai is P51800007336.
Is Skicon Skicity Phase 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Skicon Skicity Phase 1 is registered as P51800007336 and its status is "Registered and active".
What is the current construction status of Skicon Skicity Phase 1? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Skicon Skicity Phase 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Skicity is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Skicon Skicity Phase 1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Skicon Skicity Phase 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Skicon Skicity Phase 1 is registered on MahaRERA as P51800007336, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Skicon Skicity Phase 1?
Skicon Skicity Phase 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Skicon Skicity Phase 1?
For a flat in Skicon Skicity Phase 1 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Skicon Skicity Phase 1 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Skicon Skicity Phase 1 is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Skicon Skicity Phase 1 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Skicon Skicity Phase 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Skicon Skicity Phase 1's possession date changes?
The latest dates are on Skicon Skicity Phase 1's MahaRERA page (P51800007336). GharKundli's Kundli Watch sends a free WhatsApp update on Skicon Skicity Phase 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Skicon Skicity Phase 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Skicon Skicity Phase 1 has one building filed: Skicity with 25 floors.
How big is the land of Skicon Skicity Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Skicon Skicity Phase 1 stands on 2,876 sq m of land (about 0.7 acres), with 7,149 sq m of sanctioned built-up area and 698 sq m of recreational open space.
What is the track record of Skicon Skicity Phase 1's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Skicon Infrastructure has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 18 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Skicon Skicity Phase 1?
Google Maps has reviews of Skicon Skicity Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Skicon Skicity Phase 1?
Skicon Skicity Phase 1 by Skicon Infrastructure Co is in Bhandup West, Mumbai, pincode 400078 (near Kanjur, Powai IIT, Bhandup East), Maharashtra, and is registered on MahaRERA as P51800007336, per GharKundli's check of MahaRERA records. Its boundaries filed there include Lake Road, Bahirji Naik Marg. Its land is filed as Part of CTS nos 210/38A, 210/38B, 210/39 to 88 of Village Bhandup. GharKundli lists all 176 MahaRERA projects in Bhandup West (400078).
When was Skicon Skicity Phase 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Skicon Skicity Phase 1 was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Does Skicon Skicity Phase 1 have any legal issues or court cases?
No court cases are listed for Skicon Skicity Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Skicon Skicity Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Skicon Infrastructure Co, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Skicon Skicity Phase 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Bhandup West (400078)
- Horizon
- Pandora by Shraddha
- Godrej Nurture - Tower 3
- Godrej Nurture - Tower 2
- Sugee Vaayu
- Bhoomi Green Hill
- Valentina CHS
- Runwal Forests Tower 9 - 11
Other projects by Skicon Infrastructure Co
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.