SAHAKAR AVENUE

by SAHAKAR CORPORATION · Malad West, Mumbai

Registered on MahaRERA under P51800003995. Status: Completed. Its completion date has moved from December 2020 to October 2026, 70 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

MahaRERA registration
P51800003995
Status
Completed
Builder
SAHAKAR CORPORATION
Location
Malad West, Mumbai · 400064
Project type
Others
Registered on
7 Aug 2017
Completion date at registration
December 2020
Latest completion date
October 2026
Delay so far
70 months
Homes
98
Sold or booked
51%
Towers
2
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

GharKundli’s full report on SAHAKAR AVENUE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Kundli Watch

SAHAKAR AVENUE: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about SAHAKAR AVENUE

Is SAHAKAR AVENUE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAHAKAR AVENUE is registered as P51800003995 and its status is "Completed".

Where is SAHAKAR AVENUE?

SAHAKAR AVENUE by SAHAKAR CORPORATION is in Malad West, Mumbai (pincode 400064), Maharashtra, and is registered on MahaRERA as P51800003995, per GharKundli's check of MahaRERA records.

When is possession of SAHAKAR AVENUE due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAHAKAR AVENUE in Malad West, Mumbai is 30 October 2026 — 70 months later than 31 December 2020, the date given at registration.

Does SAHAKAR AVENUE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of SAHAKAR AVENUE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAHAKAR CORPORATION.

Other projects in pincode 400064

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.