SAHAKAR AVENUE
by SAHAKAR CORPORATION · Malad West, Mumbai
Registered on MahaRERA under P51800003995. Status: Completed. Its completion date has moved from December 2020 to October 2026, 70 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
- MahaRERA registration
- P51800003995
- Status
- Completed
- Builder
- SAHAKAR CORPORATION
- Location
- Malad West, Mumbai · 400064
- Project type
- Others
- Registered on
- 7 Aug 2017
- Completion date at registration
- December 2020
- Latest completion date
- October 2026
- Delay so far
- 70 months
- Homes
- 98
- Sold or booked
- 51%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
GharKundli’s full report on SAHAKAR AVENUE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Kundli Watch
SAHAKAR AVENUE: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about SAHAKAR AVENUE
Is SAHAKAR AVENUE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAHAKAR AVENUE is registered as P51800003995 and its status is "Completed".
Where is SAHAKAR AVENUE?
SAHAKAR AVENUE by SAHAKAR CORPORATION is in Malad West, Mumbai (pincode 400064), Maharashtra, and is registered on MahaRERA as P51800003995, per GharKundli's check of MahaRERA records.
When is possession of SAHAKAR AVENUE due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAHAKAR AVENUE in Malad West, Mumbai is 30 October 2026 — 70 months later than 31 December 2020, the date given at registration.
Does SAHAKAR AVENUE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of SAHAKAR AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAHAKAR CORPORATION.
Other projects in pincode 400064
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.