Possession date of Sun-Vision Heritage-Swati: 30 October 2020, moved from 31 December 2018 (22 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800005962. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (October 2020) has passed.

What do you want to know about Sun-Vision Heritage-Swati?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sun-Vision Heritage-Swati has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51800005671)

    Reason the builder gave MahaRERA: “delay in implementation of new DCPR and transition policies”
  3. 30 October 2020

    Revised completion date on MahaRERA

Source: Sun-Vision Heritage-Swati’s extension records on MahaRERA (P51800005962), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sun-Vision Heritage-Swati

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800005962
Status
Lapsed (registration period ended)
Builder
S.S.Primespace Pvt. Ltd.
Location
Vile Parle East, Mumbai · 400057
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
December 2018
Latest completion date
October 2020
Delay so far
22 months
Homes
20
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of Sun-Vision Heritage-Swati, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sun-Vision Heritage100%60%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sun-Vision Heritage-Swati every month.

Sun-Vision Heritage-Swati: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Sun-Vision Heritage-Swati →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sun-Vision Heritage-Swati: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sun-Vision Heritage-Swati

What is the possession date of Sun-Vision Heritage-Swati?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sun-Vision Heritage-Swati in Vile Parle East, Mumbai is 30 October 2020 — 22 months later than 31 December 2018, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Sun-Vision Heritage-Swati?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sun-Vision Heritage-Swati's builder has filed on MahaRERA, the official one, is 30 October 2020, already 22 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sun-Vision Heritage-Swati extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Vision Heritage-Swati's builder applied to MahaRERA to extend the completion date once: to 30 April 2020, giving the reason "delay in implementation of new DCPR and transition policies".

What is the RERA number of Sun-Vision Heritage-Swati?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sun-Vision Heritage-Swati in Vile Parle East, Mumbai is P51800005962.

Is Sun-Vision Heritage-Swati registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Vision Heritage-Swati is registered as P51800005962 and its status is "Lapsed (registration period ended)".

What is the construction status of Sun-Vision Heritage-Swati?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Vision Heritage-Swati's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Sun-Vision Heritage is 60% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Sun-Vision Heritage-Swati have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sun-Vision Heritage-Swati safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Vision Heritage-Swati is registered on MahaRERA as P51800005962, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 22 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sun-Vision Heritage-Swati's possession date changes?

The latest dates are on Sun-Vision Heritage-Swati's MahaRERA page (P51800005962). GharKundli's Kundli Watch sends a free WhatsApp update on Sun-Vision Heritage-Swati every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sun-Vision Heritage-Swati have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Vision Heritage-Swati has one building filed: Sun-Vision Heritage with 10 floors.

How big is the land of Sun-Vision Heritage-Swati?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Vision Heritage-Swati stands on 429 sq m of land (about 0.1 acres), with 719 sq m of sanctioned built-up area.

Where can I read reviews of Sun-Vision Heritage-Swati?

Google Maps has reviews of Sun-Vision Heritage-Swati written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sun-Vision Heritage-Swati?

Sun-Vision Heritage-Swati by S.S.Primespace Pvt. Ltd. is in Vile Parle East, Mumbai (pincode 400057), near Vile Parle West, Vileparle East, Borivali West, Maharashtra, and is registered on MahaRERA as P51800005962, per GharKundli's check of MahaRERA records. Its boundaries filed there include park road.

How many homes are in Sun-Vision Heritage-Swati?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Vision Heritage-Swati has 20 homes in 1 tower registered on MahaRERA.

When was Sun-Vision Heritage-Swati registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sun-Vision Heritage-Swati was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Sun-Vision Heritage-Swati?

No court cases are listed for Sun-Vision Heritage-Swati on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Sun-Vision Heritage-Swati?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is S.S.Primespace Pvt. Ltd..