HARI VASANT
by Hari Vasant Association of Allottees · Gangapur Road, NashikAlso near Chandshi
Possession date of HARI VASANT: 30 January 2027, moved from 31 December 2020 (69 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600000534, and currently active. Its completion date has moved from December 2020 to January 2027: 69 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 31 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about HARI VASANT?
How the possession date of HARI VASANT has moved
31 December 2020
Completion date given when the project was registered
30 December 2021
Extended at the builder's request (MahaRERA application EXT51600000945)
Reason the builder gave MahaRERA:
“There has been delay in construction due to some unavoidable reason, hence we hereby request you to allow the extension of a period of 12 months as we will strive to complete the project as per new timeline after extension ie 30th December,…” Read the full reason
“There has been delay in construction due to some unavoidable reason, hence we hereby request you to allow the extension of a period of 12 months as we will strive to complete the project as per new timeline after extension ie 30th December, 2021.”30 September 2026
Extended at the builder's request (MahaRERA application EXT51600028027)
Reason the builder gave MahaRERA: “Due to unavoidable causes”
30 January 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: HARI VASANT’s extension records on MahaRERA (P51600000534), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on HARI VASANT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 31 complaints, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600000534
- Status
- Registered and active
- Builder
- Hari Vasant Association of Allottees
- Location
- Gangapur Road, Nashik · 422005
- Project type
- Residential / Group Housing
- Registered on
- 18 Jul 2017
- Completion date at registration
- December 2020
- Latest completion date
- January 2027
- Delay so far
- 69 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 204
- Sold or booked
- 45%
- Towers
- 2
- Complaints on MahaRERA
- 31
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of HARI VASANT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
Commencement certificate (CC), as filed on MahaRERA
- Building A: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on HARI VASANT every month.
HARI VASANT: buildings, flats and land, as filed on MahaRERA
- Buildings: Building A (18 floors, 102 units) · Building B (19 floors, 102 units)
- Land: 8,375 sq m (about 2.1 acres) · sanctioned built-up 11,934 sq m · recreational space 838 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of HARI VASANT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
HARI VASANT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about HARI VASANT
What is the possession date of HARI VASANT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HARI VASANT in Gangapur Road, Nashik is 30 January 2027 — 69 months later than 31 December 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for HARI VASANT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date HARI VASANT's builder has filed on MahaRERA, the official one, is 30 January 2027, already 69 months later than the 31 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of HARI VASANT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI VASANT's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2021, giving the reason "There has been delay in construction due to some unavoidable reason, hence we hereby request you to allow the extension of a period of 12 months as we will strive to complete the project as per new timeline after extension ie 30th December, 2021."; to 30 September 2026, giving the reason "Due to unavoidable causes". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of HARI VASANT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HARI VASANT in Gangapur Road, Nashik is P51600000534.
Is HARI VASANT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI VASANT is registered as P51600000534 and its status is "Registered and active".
What is the construction status of HARI VASANT?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI VASANT's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does HARI VASANT have complaints on MahaRERA?
31 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is HARI VASANT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI VASANT is registered on MahaRERA as P51600000534, its completion date has moved 69 months since registration and 31 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if HARI VASANT's possession date changes?
The latest dates are on HARI VASANT's MahaRERA page (P51600000534). GharKundli's Kundli Watch sends a free WhatsApp update on HARI VASANT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does HARI VASANT have?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI VASANT has 2 buildings filed: Building A with 18 floors and 102 units; Building B with 19 floors and 102 units.
How big is the land of HARI VASANT?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI VASANT stands on 8,375 sq m of land (about 2.1 acres), with 11,934 sq m of sanctioned built-up area and 838 sq m of recreational open space.
Where can I read reviews of HARI VASANT?
Google Maps has reviews of HARI VASANT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 31 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is HARI VASANT?
HARI VASANT by Hari Vasant Association of Allottees is in Gangapur Road, Nashik (pincode 422005), near Chandshi, Maharashtra, and is registered on MahaRERA as P51600000534, per GharKundli's check of MahaRERA records.
How many homes are in HARI VASANT?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI VASANT has 204 homes in 2 towers registered on MahaRERA, and 45% of them are sold or booked.
When was HARI VASANT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HARI VASANT was registered on MahaRERA on 18 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on HARI VASANT?
No court cases are listed for HARI VASANT on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of HARI VASANT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Hari Vasant Association of Allottees.
Check it yourself on MahaRERA
- How to check the possession date of HARI VASANT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nashik →
Other projects in Gangapur Road
- TREELAND PHASE-5
- TREELAND PHASE-2
- SAI CASTLE
- SHREEMALHAR APARTMENT
- TREELAND - PHASE 4
- SAI ASHA
- C.M.R LEGACY APARTMENT
- TREELAND PHASE - 1
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.