TREELAND - PHASE 4

by ABH DEVELOPERS PRIVATE LIMITED · Gangapur Road, Nashik

Possession: TREELAND - PHASE 4 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600029154. Status: Completed.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about TREELAND - PHASE 4?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of TREELAND - PHASE 4 has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 30 March 2026

    Extended at the builder's request (MahaRERA application EXT51600028039)

    Reason the builder gave MahaRERA:
    “• Unavailability/Shortage of Labour: Movement restrictions and safety concerns led to a scarcity of skilled and unskilled labourers essential for project execution. Many workers from northern states took time to relocate and resume work. •…” Read the full reason“• Unavailability/Shortage of Labour: Movement restrictions and safety concerns led to a scarcity of skilled and unskilled labourers essential for project execution. Many workers from northern states took time to relocate and resume work. • Slow progress of certain activities: Social distancing protocols and safety measures have inevitably slowed down the pace of certain construction tasks. • Suspension of the works: Temporary halts in construction activities due to government directives and safety precautions have interrupted the project’s continuity. • Delay in the supply of material and e…”

Source: TREELAND - PHASE 4’s extension records on MahaRERA (P51600029154), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TREELAND - PHASE 4

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51600029154
Status
Completed
Builder
ABH DEVELOPERS PRIVATE LIMITED
Location
Gangapur Road, Nashik · 422025
Project type
Residential / Group Housing
Registered on
29 Apr 2021
Completion date at registration
March 2025
Latest completion date
March 2026
Delay so far
12 months
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of TREELAND - PHASE 4, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING F0%100%100%100%
WING G0%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TREELAND - PHASE 4 every month.

TREELAND - PHASE 4: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

ABH Developers (a group of 2 linked companies) has 14 projects on MahaRERA since 2020, this one included. Of the 10 GharKundli has checked: 6 finished, 3 within the promised date and 3 needed more time (typically 6 months); 2 still being built, 2 past the promised date (typically 12 months late); 2 lapsed. 4 complaints on MahaRERA across 2 projects.

Read Google reviews of TREELAND - PHASE 4 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TREELAND - PHASE 4: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TREELAND - PHASE 4

What is the possession date of TREELAND - PHASE 4?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TREELAND - PHASE 4 in Gangapur Road, Nashik is 30 March 2026 — 12 months later than 31 March 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for TREELAND - PHASE 4?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TREELAND - PHASE 4's builder has filed on MahaRERA, the official one, is 30 March 2026, already 12 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TREELAND - PHASE 4 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND - PHASE 4's builder applied to MahaRERA to extend the completion date once: to 30 March 2026, giving the reason "• Unavailability/Shortage of Labour: Movement restrictions and safety concerns led to a scarcity of skilled and unskilled labourers essential for project execution. Many workers from northern states took time to relocate and resume work. • Slow progress of certain activities: Social distancing protocols and safety measures have inevitably slowed down the pace of certain construction tasks. • Suspension of the works: Temporary halts in construction activities due to government directives and safety precautions have interrupted the project’s continuity. • Delay in the supply of material and e…".

What is the RERA number of TREELAND - PHASE 4?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TREELAND - PHASE 4 in Gangapur Road, Nashik is P51600029154.

Is TREELAND - PHASE 4 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND - PHASE 4 is registered as P51600029154 and its status is "Completed".

What is the construction status of TREELAND - PHASE 4?

According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND - PHASE 4's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does TREELAND - PHASE 4 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is TREELAND - PHASE 4 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND - PHASE 4 is registered on MahaRERA as P51600029154, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does TREELAND - PHASE 4 have other wings or phases?

Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: TREELAND PHASE - 1 (P51600025058, possession 29 Apr 2025); TREELAND PHASE-2 (P51600034705, possession 30 Apr 2027); TREELAND PHASE - 3 (P51600025197); TREELAND PHASE-5 (P51600034430, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.

How can I get updates if TREELAND - PHASE 4's possession date changes?

The latest dates are on TREELAND - PHASE 4's MahaRERA page (P51600029154). GharKundli's Kundli Watch sends a free WhatsApp update on TREELAND - PHASE 4 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TREELAND - PHASE 4 have?

According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND - PHASE 4 has 2 buildings filed: WING F with 26 floors; WING G with 26 floors.

How big is the land of TREELAND - PHASE 4?

According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND - PHASE 4 stands on 5,045 sq m of land (about 1.2 acres), with 11,447 sq m of sanctioned built-up area.

What is the track record of TREELAND - PHASE 4's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), ABH Developers (a group of 2 linked companies) has 14 projects on MahaRERA since 2020, this one included. Of the 10 GharKundli has checked: 6 finished, 3 within the promised date and 3 needed more time (typically 6 months); 2 still being built, 2 past the promised date (typically 12 months late); 2 lapsed. 4 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of TREELAND - PHASE 4?

Google Maps has reviews of TREELAND - PHASE 4 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TREELAND - PHASE 4?

TREELAND - PHASE 4 by ABH DEVELOPERS PRIVATE LIMITED is in Gangapur Road, Nashik (pincode 422025), Maharashtra, and is registered on MahaRERA as P51600029154, per GharKundli's check of MahaRERA records.

When was TREELAND - PHASE 4 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND - PHASE 4 was registered on MahaRERA on 29 April 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on TREELAND - PHASE 4?

No court cases are listed for TREELAND - PHASE 4 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of TREELAND - PHASE 4?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ABH DEVELOPERS PRIVATE LIMITED, which has 6 other projects registered on MahaRERA.

Other projects in Gangapur Road

Other projects by ABH DEVELOPERS PRIVATE LIMITED

All Nashik projects with no pincode on MahaRERA →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.