TREELAND PHASE-2
by ABH DEVELOPERS PRIVATE LIMITED · Gangapur Road, NashikAlso near Serene Meadows
Possession date of TREELAND PHASE-2: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600034705, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about TREELAND PHASE-2?
How the possession date of TREELAND PHASE-2 has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA31122519192)
Reason the builder gave MahaRERA:
“• Unavailability/Shortage of Labour: Movement restrictions and safety concerns led to a scarcity of skilled and unskilled labourers essential for project execution. Many workers from northern states took time to relocate and resume work. •…” Read the full reason
“• Unavailability/Shortage of Labour: Movement restrictions and safety concerns led to a scarcity of skilled and unskilled labourers essential for project execution. Many workers from northern states took time to relocate and resume work. • Slow progress of certain activities: Social distancing protocols and safety measures have inevitably slowed down the pace of certain construction tasks. • Suspension of the works: Temporary halts in construction activities due to government directives and safety precautions have interrupted the project’s continuity. • Delay in the supply of material and e…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: TREELAND PHASE-2’s extension records on MahaRERA (P51600034705), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on TREELAND PHASE-2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- TREELAND PHASE - 1P51600025058 · possession 29 Apr 2025
- TREELAND PHASE - 3P51600025197
- TREELAND - PHASE 4P51600029154 · possession 30 Mar 2026
- TREELAND PHASE-5P51600034430 · possession 30 Apr 2027
- MahaRERA registration
- P51600034705
- Status
- Registered and active
- Builder
- ABH DEVELOPERS PRIVATE LIMITED
- Location
- Gangapur Road, Nashik · 422025
- Project type
- Residential / Group Housing
- Registered on
- 20 Apr 2022
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 84
- Sold or booked
- 60%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of TREELAND PHASE-2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING D | 0% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- WING D: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on TREELAND PHASE-2 every month.
TREELAND PHASE-2: buildings, flats and land, as filed on MahaRERA
- Buildings: WING D (26 floors, 84 units)
- Car parking: 1 covered, 24 open
- Land: 5,842 sq m (about 1.4 acres) · sanctioned built-up 14,873 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
ABH Developers (a group of 2 linked companies) has 14 projects on MahaRERA since 2020, this one included. Of the 10 GharKundli has checked: 6 finished, 3 within the promised date and 3 needed more time (typically 6 months); 2 still being built, 2 past the promised date (typically 12 months late); 2 lapsed. 4 complaints on MahaRERA across 2 projects.
Read Google reviews of TREELAND PHASE-2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
TREELAND PHASE-2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about TREELAND PHASE-2
What is the possession date of TREELAND PHASE-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TREELAND PHASE-2 in Gangapur Road, Nashik is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for TREELAND PHASE-2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date TREELAND PHASE-2's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of TREELAND PHASE-2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND PHASE-2's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "• Unavailability/Shortage of Labour: Movement restrictions and safety concerns led to a scarcity of skilled and unskilled labourers essential for project execution. Many workers from northern states took time to relocate and resume work. • Slow progress of certain activities: Social distancing protocols and safety measures have inevitably slowed down the pace of certain construction tasks. • Suspension of the works: Temporary halts in construction activities due to government directives and safety precautions have interrupted the project’s continuity. • Delay in the supply of material and e…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of TREELAND PHASE-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TREELAND PHASE-2 in Gangapur Road, Nashik is P51600034705.
Is TREELAND PHASE-2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND PHASE-2 is registered as P51600034705 and its status is "Registered and active".
What is the construction status of TREELAND PHASE-2?
According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND PHASE-2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on WING D is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does TREELAND PHASE-2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is TREELAND PHASE-2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND PHASE-2 is registered on MahaRERA as P51600034705, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does TREELAND PHASE-2 have other wings or phases?
Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: TREELAND PHASE - 1 (P51600025058, possession 29 Apr 2025); TREELAND PHASE - 3 (P51600025197); TREELAND - PHASE 4 (P51600029154, possession 30 Mar 2026); TREELAND PHASE-5 (P51600034430, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.
How can I get updates if TREELAND PHASE-2's possession date changes?
The latest dates are on TREELAND PHASE-2's MahaRERA page (P51600034705). GharKundli's Kundli Watch sends a free WhatsApp update on TREELAND PHASE-2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does TREELAND PHASE-2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND PHASE-2 has one building filed: WING D with 26 floors and 84 units.
How much parking does TREELAND PHASE-2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 24 open car parking spaces for TREELAND PHASE-2.
How big is the land of TREELAND PHASE-2?
According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND PHASE-2 stands on 5,842 sq m of land (about 1.4 acres), with 14,873 sq m of sanctioned built-up area.
What is the track record of TREELAND PHASE-2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), ABH Developers (a group of 2 linked companies) has 14 projects on MahaRERA since 2020, this one included. Of the 10 GharKundli has checked: 6 finished, 3 within the promised date and 3 needed more time (typically 6 months); 2 still being built, 2 past the promised date (typically 12 months late); 2 lapsed. 4 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of TREELAND PHASE-2?
Google Maps has reviews of TREELAND PHASE-2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is TREELAND PHASE-2?
TREELAND PHASE-2 by ABH DEVELOPERS PRIVATE LIMITED is in Gangapur Road, Nashik (pincode 422025), near Serene Meadows, Maharashtra, and is registered on MahaRERA as P51600034705, per GharKundli's check of MahaRERA records.
How many homes are in TREELAND PHASE-2?
According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND PHASE-2 has 84 homes in 1 tower registered on MahaRERA, and 60% of them are sold or booked.
When was TREELAND PHASE-2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), TREELAND PHASE-2 was registered on MahaRERA on 20 April 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on TREELAND PHASE-2?
No court cases are listed for TREELAND PHASE-2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of TREELAND PHASE-2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ABH DEVELOPERS PRIVATE LIMITED, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of TREELAND PHASE-2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Gangapur Road
Other projects by ABH DEVELOPERS PRIVATE LIMITED
All Nashik projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.