SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO

by SUN INFRASTRUCTURES PVT LTD · Sawarkar Nagar, NashikAlso near Gangapur Road, Chandshi

Possession date of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO: 30 April 2027, moved from 31 March 2021 (69 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600003685, and currently active. Its completion date has moved from March 2021 to April 2027: 69 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 6 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO has moved

  1. 31 March 2021

    Completion date given when the project was registered

  2. 31 March 2022

    Extended at the builder's request (MahaRERA application EXT51600010028)

    Reason the builder gave MahaRERA:
    “Due to continuous onslaught of the 1st & 2nd wave of Covid-19 Pandemic, the supply chain of Construction material is badly affected. In addition, the 3rd wave of Covid-19 is apprehended very soon as per global anticipation. This has frighte…” Read the full reason“Due to continuous onslaught of the 1st & 2nd wave of Covid-19 Pandemic, the supply chain of Construction material is badly affected. In addition, the 3rd wave of Covid-19 is apprehended very soon as per global anticipation. This has frightened the labor force resulting in lockdown, non-availability of construction labor who have already migrated to their native place & have not returned as yet. Non-availability of transport, conveyance & logistics are other hurdles in completion of our subject projects by stipulated dates. These difficulties have already been put forth by SRO Members, befor…”
  3. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT51600012635)

    Reason the builder gave MahaRERA:
    “Dear Sir/ Ma'am, We hereby apply for extension u/s 7 (3) of the registered project bearing vide no. P51600003685. As prescribed under circular no. 0717019 dated 8 Feb 2019. the consent of 51% allottees is enclosed herewith. Kindly request t…” Read the full reason“Dear Sir/ Ma'am, We hereby apply for extension u/s 7 (3) of the registered project bearing vide no. P51600003685. As prescribed under circular no. 0717019 dated 8 Feb 2019. the consent of 51% allottees is enclosed herewith. Kindly request to grant extension for this project. Thanking you, Yours faithfully, For Sun Infrastructures Pvt. Ltd.”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51600024266)

    Reason the builder gave MahaRERA:
    “To, MahaRera, Subject - Extension to the proejct bearing Registration No. P51600003685. Respected Sir, We, hereby apply for extension u/s 7(3) of the registered project bearing vide No. P51600003685, As prescribed under circular No. 0717019…” Read the full reason“To, MahaRera, Subject - Extension to the proejct bearing Registration No. P51600003685. Respected Sir, We, hereby apply for extension u/s 7(3) of the registered project bearing vide No. P51600003685, As prescribed under circular No. 0717019, dt. 8/02/2019, the consent of the 51% allottes is enclosed herewith. The project is not completed within time specified in registration due to banking issues, financial crunch and low booking response in the project as projected, We need addional time to complete the pending development work in the project Thanking you, Yours faithfully For Sun Infrastr…”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO’s extension records on MahaRERA (P51600003685), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 6 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600003685
Status
Registered and active
Builder
SUN INFRASTRUCTURES PVT LTD
Location
Sawarkar Nagar, Nashik · 422013
Project type
Residential / Group Housing
Registered on
6 Aug 2017
Completion date at registration
March 2021
Latest completion date
April 2027
Delay so far
69 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
144
Towers
2
Complaints on MahaRERA
6
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
19

Construction progress of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AMARANTH 1 to 7 and 9 to 12 Floors100%27%5%0%
AMARANTH 8th Floor100%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO every month.

SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO: buildings, flats and land, as filed on MahaRERA

  • Buildings: AMARANTH 1 to 7 and 9 to 12 Floors (15 floors) · AMARANTH 8th Floor (1 floors)
  • Land: 6,467 sq m (about 1.6 acres) · sanctioned built-up 15,943 sq m · recreational space 718 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

SUN Infrastructures (a group of 2 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 still being built, 3 past the promised date (typically 30 months late); 1 lapsed. 10 complaints on MahaRERA across 2 projects.

Read Google reviews of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO

What is the possession date of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO in Sawarkar Nagar, Nashik is 30 April 2027 — 69 months later than 31 March 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO's builder has filed on MahaRERA, the official one, is 30 April 2027, already 69 months later than the 31 March 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO's builder applied to MahaRERA to extend the completion date 3 times: to 31 March 2022, giving the reason "Due to continuous onslaught of the 1st & 2nd wave of Covid-19 Pandemic, the supply chain of Construction material is badly affected. In addition, the 3rd wave of Covid-19 is apprehended very soon as per global anticipation. This has frightened the labor force resulting in lockdown, non-availability of construction labor who have already migrated to their native place & have not returned as yet. Non-availability of transport, conveyance & logistics are other hurdles in completion of our subject projects by stipulated dates. These difficulties have already been put forth by SRO Members, befor…"; to 31 March 2024, giving the reason "Dear Sir/ Ma'am, We hereby apply for extension u/s 7 (3) of the registered project bearing vide no. P51600003685. As prescribed under circular no. 0717019 dated 8 Feb 2019. the consent of 51% allottees is enclosed herewith. Kindly request to grant extension for this project. Thanking you, Yours faithfully, For Sun Infrastructures Pvt. Ltd."; to 31 December 2026, giving the reason "To, MahaRera, Subject - Extension to the proejct bearing Registration No. P51600003685. Respected Sir, We, hereby apply for extension u/s 7(3) of the registered project bearing vide No. P51600003685, As prescribed under circular No. 0717019, dt. 8/02/2019, the consent of the 51% allottes is enclosed herewith. The project is not completed within time specified in registration due to banking issues, financial crunch and low booking response in the project as projected, We need addional time to complete the pending development work in the project Thanking you, Yours faithfully For Sun Infrastr…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO in Sawarkar Nagar, Nashik is P51600003685.

Is SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO is registered as P51600003685 and its status is "Registered and active".

What is the construction status of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

According to GharKundli's check of MahaRERA records (updated October 2026), SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 27% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO have complaints on MahaRERA?

6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO is registered on MahaRERA as P51600003685, its completion date has moved 69 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO's possession date changes?

The latest dates are on SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO's MahaRERA page (P51600003685). GharKundli's Kundli Watch sends a free WhatsApp update on SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO have?

According to GharKundli's check of MahaRERA records (updated October 2026), SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO has 2 buildings filed: AMARANTH 1 to 7 and 9 to 12 Floors with 15 floors; AMARANTH 8th Floor with 1 floors.

How big is the land of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

According to GharKundli's check of MahaRERA records (updated October 2026), SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO stands on 6,467 sq m of land (about 1.6 acres), with 15,943 sq m of sanctioned built-up area and 718 sq m of recreational open space.

What is the track record of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), SUN Infrastructures (a group of 2 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 still being built, 3 past the promised date (typically 30 months late); 1 lapsed. 10 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

Google Maps has reviews of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO by SUN INFRASTRUCTURES PVT LTD is in Sawarkar Nagar, Nashik (pincode 422013), near Gangapur Road, Chandshi, Maharashtra, and is registered on MahaRERA as P51600003685, per GharKundli's check of MahaRERA records.

How many homes are in SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

According to GharKundli's check of MahaRERA records (updated October 2026), SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO has 144 homes in 2 towers registered on MahaRERA.

When was SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

No court cases are listed for SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUN INFRASTRUCTURES PVT LTD, which has 19 other projects registered on MahaRERA.

All projects with possession due in 2027 in Nashik →

Other projects in pincode 422013

All 120 projects in Sawarkar Nagar (422013) →

Other projects by SUN INFRASTRUCTURES PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.