Ruparel Westsky

by RUPAREL SHREEJI CONSTRUCTION PVT LTD (Classic) · Kandivali, MumbaiAlso near Bandra, Iraniwadi, Malad West

Possession date of Ruparel Westsky: 31 December 2027, moved from 30 June 2023 (54 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800007630, and currently active. 51 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Ruparel Westsky?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Ruparel Westsky has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 29 June 2024

    Extended at the builder's request (MahaRERA application EXT51800010780)

    Reason the builder gave MahaRERA: “due increase in FSI as per DCR 2034, sale construction area has been increased”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800010896)

    Reason the builder gave MahaRERA: “Due to Increase in FSI, Construction area has increase and therefore request you to grant us extension for completion of project.”
  4. 31 December 2027

    Extended at the builder's request (MahaRERA application EA23012619568)

    Reason the builder gave MahaRERA:
    ““Ruparel Westsky” is a single residential tower comprising Basement (services) + Ground + 59 floors, being developed under a redevelopment scheme in accordance with Regulation 33(10) of DCPR 2034. The project is registered with MahaRERA, wi…” Read the full reason““Ruparel Westsky” is a single residential tower comprising Basement (services) + Ground + 59 floors, being developed under a redevelopment scheme in accordance with Regulation 33(10) of DCPR 2034. The project is registered with MahaRERA, with the latest registration certificate issued on 5th October 2021 and valid up to 31st December 2025. Due to circumstances beyond the control of the promoter, the project has suffered delays, necessitating an application for extension of registration under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The primary cause of delay i…”

Source: Ruparel Westsky’s extension records on MahaRERA (P51800007630), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ruparel Westsky

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 51 complaints, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800007630
Status
Registered and active
Builder
RUPAREL SHREEJI CONSTRUCTION PVT LTD
Location
Kandivali, Mumbai · 400067
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
June 2023
Latest completion date
December 2027
Delay so far
54 months
Homes
328
Sold or booked
65%
Towers
1
Complaints on MahaRERA
51
Court cases listed
0
Appeals at the tribunal
6
Title report on file
Not found

Construction progress of Ruparel Westsky, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Parkview95%51%51%0%

Commencement certificate (CC), as filed on MahaRERA

  • Parkview: covers This C.C. is further extended from 32nd to 37th and inform RCC frame work from 38th to 53rd upper floors.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ruparel Westsky every month.

Ruparel Westsky: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK616 – 772328
Shops517 – 1,3348

The builder’s record and reviews

Ruparel Infra & Realty (a group of 12 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 13 still being built, 7 past the promised date (typically 28 months late); 10 lapsed. 856 complaints on MahaRERA across 19 projects.

Read Google reviews of Ruparel Westsky →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ruparel Westsky: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Ruparel Westsky

What is the possession date of Ruparel Westsky?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ruparel Westsky in Kandivali, Mumbai is 31 December 2027 — 54 months later than 30 June 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Ruparel Westsky?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ruparel Westsky's builder has filed on MahaRERA, the official one, is 31 December 2027, already 54 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ruparel Westsky extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Westsky's builder applied to MahaRERA to extend the completion date 3 times: to 29 June 2024, giving the reason "due increase in FSI as per DCR 2034, sale construction area has been increased"; to 31 December 2025, giving the reason "Due to Increase in FSI, Construction area has increase and therefore request you to grant us extension for completion of project."; to 31 December 2027, giving the reason "“Ruparel Westsky” is a single residential tower comprising Basement (services) + Ground + 59 floors, being developed under a redevelopment scheme in accordance with Regulation 33(10) of DCPR 2034. The project is registered with MahaRERA, with the latest registration certificate issued on 5th October 2021 and valid up to 31st December 2025. Due to circumstances beyond the control of the promoter, the project has suffered delays, necessitating an application for extension of registration under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The primary cause of delay i…".

What is the RERA number of Ruparel Westsky?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ruparel Westsky in Kandivali, Mumbai is P51800007630.

Is Ruparel Westsky registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Westsky is registered as P51800007630 and its status is "Registered and active".

What is the construction status of Ruparel Westsky?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Westsky's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Parkview is 51% done and internal work 51%. GharKundli's full report compares construction progress with the deadline.

Does Ruparel Westsky have complaints on MahaRERA?

51 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Ruparel Westsky safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Westsky is registered on MahaRERA as P51800007630, its completion date has moved 54 months since registration and 51 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Ruparel Westsky's possession date changes?

The latest dates are on Ruparel Westsky's MahaRERA page (P51800007630). GharKundli's Kundli Watch sends a free WhatsApp update on Ruparel Westsky every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ruparel Westsky have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Westsky has one building filed: Parkview with 61 floors and 336 units.

What are the flat sizes (carpet area) in Ruparel Westsky?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ruparel Westsky: 2 BHK: 616 to 772 sq ft carpet (328 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Ruparel Westsky?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Westsky stands on 3,143 sq m of land (about 0.8 acres), with 4,825 sq m of sanctioned built-up area.

What is the track record of Ruparel Westsky's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Infra & Realty (a group of 12 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 13 still being built, 7 past the promised date (typically 28 months late); 10 lapsed. 856 complaints on MahaRERA across 19 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Ruparel Westsky?

Google Maps has reviews of Ruparel Westsky written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 51 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Ruparel Westsky?

Ruparel Westsky by RUPAREL SHREEJI CONSTRUCTION PVT LTD (Classic) is in Kandivali, Mumbai (pincode 400067), near Bandra, Iraniwadi, Malad West, Maharashtra, and is registered on MahaRERA as P51800007630, per GharKundli's check of MahaRERA records.

How many homes are in Ruparel Westsky?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Westsky has 328 homes in 1 tower registered on MahaRERA, and 65% of them are sold or booked.

When was Ruparel Westsky registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Westsky was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Ruparel Westsky?

No court cases are listed for Ruparel Westsky on MahaRERA, and 6 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Ruparel Westsky?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RUPAREL SHREEJI CONSTRUCTION PVT LTD, the company Classic files this project under.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400067

All 318 projects in Kandivali West (400067) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.