by GLASSWOOD REALTY PRIVATE LIMITED · Kandivali, Mumbai 400067Also near Malad West, Orlem, Valnai

What’s in the report? →

Possession date of Delphine CHSL (MahaRERA P51800005847): 30 October 2028, moved from 30 September 2020 (93 months later). It has 41 homes (1 BHK, 2 BHK and 3 BHK, 137–751 sq ft carpet), 50% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800005847, and currently active. Its completion date has moved from September 2020 to October 2028: 93 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800005847, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Delphine CHSL?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Delphine CHSL has moved

  1. 30 September 2020

    Completion date given when the project was registered

  2. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT51800008683)

    Reason the builder gave MahaRERA:
    “Please note that we have obtained the IOD for the project on 15th September 2015 and the CC was granted to us by the MCGM on 17th May 2016 upto 5 Stilt Slab level. We had completed the stilt slab level work and had further applied for furth…” Read the full reason“Please note that we have obtained the IOD for the project on 15th September 2015 and the CC was granted to us by the MCGM on 17th May 2016 upto 5 Stilt Slab level. We had completed the stilt slab level work and had further applied for further CC and the MCGM sanctioned further CC on 23rd February 2017 for upto 9th floor. Thereafter when we approached the MCGM for further permissions, we were told that as the 30 feet DP road leading to our plot is encroached upon by unauthorized slum dwellers to the extent that, road width of 30 feet is not available on site and as the project is of 16 floor…”
  3. 30 June 2028

    Extended at the builder's request (MahaRERA application EA20052621038)

    Reason the builder gave MahaRERA:
    “Dear Sir/Ma’am, We, Glasswood Realty Private Limited, hereby declare the following with respect to the project “DELPHINE CHSL” bearing registration number P51800005847 registered under MahaRERA 1. Status of Work Completed: We are pleased to…” Read the full reason“Dear Sir/Ma’am, We, Glasswood Realty Private Limited, hereby declare the following with respect to the project “DELPHINE CHSL” bearing registration number P51800005847 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the all the buildings. Currently, we are undertaking the Pending finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance…”
  4. 30 October 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Delphine CHSL’s extension records on MahaRERA (P51800005847), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Delphine CHSL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800005847
Status
Registered and active
Builder
GLASSWOOD REALTY PRIVATE LIMITED
Location
Kandivali, Mumbai · 400067
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
September 2020
Latest completion date
October 2028
Delay so far
93 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
41
Sold or booked
50%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Delphine CHSL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DELPHINE100%100%45%0%

Commencement certificate (CC), as filed on MahaRERA

  • DELPHINE: covers 10 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Delphine CHSL every 1–2 months.

Delphine CHSL: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK310 – 41618
2 BHK61515
Multi Purpose Room137 – 1836
3 BHK7512

The builder’s record and reviews

Glasswood Realty has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 still being built, 1 past the promised date (typically 63 months late); 2 lapsed. 2 complaints on MahaRERA across 1 project.

Read Google reviews of Delphine CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Delphine CHSL: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Delphine CHSL

What is the possession date of Delphine CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Delphine CHSL in Kandivali, Mumbai is 30 October 2028 — 93 months later than 30 September 2020, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 93 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Delphine CHSL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Delphine CHSL's builder has filed on MahaRERA, the official one, is 30 October 2028, already 93 months later than the 30 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Delphine CHSL extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Delphine CHSL's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2022, giving the reason "Please note that we have obtained the IOD for the project on 15th September 2015 and the CC was granted to us by the MCGM on 17th May 2016 upto 5 Stilt Slab level. We had completed the stilt slab level work and had further applied for further CC and the MCGM sanctioned further CC on 23rd February 2017 for upto 9th floor. Thereafter when we approached the MCGM for further permissions, we were told that as the 30 feet DP road leading to our plot is encroached upon by unauthorized slum dwellers to the extent that, road width of 30 feet is not available on site and as the project is of 16 floor…"; to 30 June 2028, giving the reason "Dear Sir/Ma’am, We, Glasswood Realty Private Limited, hereby declare the following with respect to the project “DELPHINE CHSL” bearing registration number P51800005847 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the all the buildings. Currently, we are undertaking the Pending finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Delphine CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Delphine CHSL in Kandivali, Mumbai is P51800005847.

Is Delphine CHSL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Delphine CHSL is registered as P51800005847 and its status is "Registered and active".

What is the current construction status of Delphine CHSL? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Delphine CHSL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on DELPHINE is 100% done and internal work 45%. GharKundli's full report compares construction progress with the deadline.

Does Delphine CHSL have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Delphine CHSL safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Delphine CHSL is registered on MahaRERA as P51800005847, its completion date has moved 93 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Delphine CHSL?

Delphine CHSL is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Delphine CHSL are 137 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Delphine CHSL?

For a flat in Delphine CHSL (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Delphine CHSL received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Delphine CHSL is still under construction, with 30 October 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Delphine CHSL a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Delphine CHSL is a redevelopment: 33 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Delphine CHSL uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Delphine CHSL was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Delphine CHSL's possession date changes?

The latest dates are on Delphine CHSL's MahaRERA page (P51800005847). GharKundli's Kundli Watch sends a free WhatsApp update on Delphine CHSL every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Delphine CHSL have?

According to GharKundli's check of MahaRERA records (updated October 2026), Delphine CHSL has one building filed: DELPHINE with 10 floors and 41 units.

What are the flat sizes (carpet area) in Delphine CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Delphine CHSL: 1 BHK: 310 to 416 sq ft carpet (18 homes); 2 BHK: 615 sq ft carpet (15 homes); Multi Purpose Room: 137 to 183 sq ft carpet (6 homes); 3 BHK: 751 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Delphine CHSL have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 21 covered and 19 open car parking spaces for Delphine CHSL.

How big is the land of Delphine CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), Delphine CHSL stands on 1,331 sq m of land (about 0.3 acres), with 1,944 sq m of sanctioned built-up area.

What is the track record of Delphine CHSL's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Glasswood Realty has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 still being built, 1 past the promised date (typically 63 months late); 2 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Delphine CHSL?

Google Maps has reviews of Delphine CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Delphine CHSL?

Delphine CHSL by GLASSWOOD REALTY PRIVATE LIMITED is in Kandivali, Mumbai, pincode 400067 (near Malad West, Orlem, Valnai), Maharashtra, and is registered on MahaRERA as P51800005847, per GharKundli's check of MahaRERA records. Its land is filed as 1265 1265 1/4 AND 1266 1266 1/9. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).

How many flats are in Delphine CHSL, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Delphine CHSL has 41 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.

When was Delphine CHSL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Delphine CHSL was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Does Delphine CHSL have any legal issues or court cases?

No court cases are listed for Delphine CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Delphine CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GLASSWOOD REALTY PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Kandivali West (400067)

All 318 projects in Kandivali West (400067) →

Other projects by GLASSWOOD REALTY PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.