EKA PHASE III - F BUILDING
by Amit Builders · Pathardi, NashikAlso near Ambad A.S, Shirdi
Possession: EKA PHASE III - F BUILDING is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600008507. Status: Completed. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about EKA PHASE III - F BUILDING?
How the possession date of EKA PHASE III - F BUILDING has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51600003735)
Reason the builder gave MahaRERA: “Acute economic crisis in the real estate market.”
30 June 2022
Extended at the builder's request (MahaRERA application EXT51600010140)
Reason the builder gave MahaRERA:
“COVID - 19 pandemic and other factors such as lockdown, delay in materials supply, shortage of labour, and other factors affecting the market condition and construction activities the promoter is unable to complete the project in this time…” Read the full reason
“COVID - 19 pandemic and other factors such as lockdown, delay in materials supply, shortage of labour, and other factors affecting the market condition and construction activities the promoter is unable to complete the project in this time period. Therefore, request you to kindly provide an extension for 1 year. The resolution of allottees with 65% of consent is attached for your perusal.”30 June 2023
Extended at the builder's request (MahaRERA application EXT51600015389)
Reason the builder gave MahaRERA:
“The construction of the said project is complete and we have applied to the Municipal Corporation of Nashik for issuance of the completion certificate. The corporation has also done a site visit. Consent of the allottees for the extension i…” Read the full reason
“The construction of the said project is complete and we have applied to the Municipal Corporation of Nashik for issuance of the completion certificate. The corporation has also done a site visit. Consent of the allottees for the extension is attached. Request to kindly grant the extension for the project.”
Source: EKA PHASE III - F BUILDING’s extension records on MahaRERA (P51600008507), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on EKA PHASE III - F BUILDING
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 4 court cases, and how it ended
- Construction pace against the June 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600008507
- Status
- Completed
- Builder
- Amit Builders
- Location
- Pathardi, Nashik · 422010
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- June 2023
- Delay so far
- 42 months
- Homes
- 96
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 4
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of EKA PHASE III - F BUILDING, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building F | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on EKA PHASE III - F BUILDING every month.
EKA PHASE III - F BUILDING: buildings, flats and land, as filed on MahaRERA
- Buildings: Building F (14 floors)
- Land: 1,342 sq m (about 0.3 acres) · sanctioned built-up 6,511 sq m · recreational space 10,263 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of EKA PHASE III - F BUILDING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
EKA PHASE III - F BUILDING: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about EKA PHASE III - F BUILDING
What is the possession date of EKA PHASE III - F BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for EKA PHASE III - F BUILDING in Pathardi, Nashik is 30 June 2023 — 42 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for EKA PHASE III - F BUILDING?
Builders and listing sites often quote an earlier "target" date for handover. The completion date EKA PHASE III - F BUILDING's builder has filed on MahaRERA, the official one, is 30 June 2023, already 42 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of EKA PHASE III - F BUILDING extended?
According to GharKundli's check of MahaRERA records (updated November 2026), EKA PHASE III - F BUILDING's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "Acute economic crisis in the real estate market."; to 30 June 2022, giving the reason "COVID - 19 pandemic and other factors such as lockdown, delay in materials supply, shortage of labour, and other factors affecting the market condition and construction activities the promoter is unable to complete the project in this time period. Therefore, request you to kindly provide an extension for 1 year. The resolution of allottees with 65% of consent is attached for your perusal."; to 30 June 2023, giving the reason "The construction of the said project is complete and we have applied to the Municipal Corporation of Nashik for issuance of the completion certificate. The corporation has also done a site visit. Consent of the allottees for the extension is attached. Request to kindly grant the extension for the project.".
What is the RERA number of EKA PHASE III - F BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of EKA PHASE III - F BUILDING in Pathardi, Nashik is P51600008507.
Is EKA PHASE III - F BUILDING registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), EKA PHASE III - F BUILDING is registered as P51600008507 and its status is "Completed".
What is the construction status of EKA PHASE III - F BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), EKA PHASE III - F BUILDING's status on MahaRERA is "Completed". As filed by the builder, slab work on Building F is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does EKA PHASE III - F BUILDING have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is EKA PHASE III - F BUILDING safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), EKA PHASE III - F BUILDING is registered on MahaRERA as P51600008507, its MahaRERA status is "Completed", its completion date has moved 42 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if EKA PHASE III - F BUILDING's possession date changes?
The latest dates are on EKA PHASE III - F BUILDING's MahaRERA page (P51600008507). GharKundli's Kundli Watch sends a free WhatsApp update on EKA PHASE III - F BUILDING every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does EKA PHASE III - F BUILDING have?
According to GharKundli's check of MahaRERA records (updated November 2026), EKA PHASE III - F BUILDING has one building filed: Building F with 14 floors.
How big is the land of EKA PHASE III - F BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), EKA PHASE III - F BUILDING stands on 1,342 sq m of land (about 0.3 acres), with 6,511 sq m of sanctioned built-up area and 10,263 sq m of recreational open space.
Where can I read reviews of EKA PHASE III - F BUILDING?
Google Maps has reviews of EKA PHASE III - F BUILDING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is EKA PHASE III - F BUILDING?
EKA PHASE III - F BUILDING by Amit Builders is in Pathardi, Nashik (pincode 422010), near Ambad A.S, Shirdi, Maharashtra, and is registered on MahaRERA as P51600008507, per GharKundli's check of MahaRERA records.
How many homes are in EKA PHASE III - F BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), EKA PHASE III - F BUILDING has 96 homes in 1 tower registered on MahaRERA.
When was EKA PHASE III - F BUILDING registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), EKA PHASE III - F BUILDING was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on EKA PHASE III - F BUILDING?
4 court cases are listed for EKA PHASE III - F BUILDING on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of EKA PHASE III - F BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Amit Builders, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of EKA PHASE III - F BUILDING
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 422010
- Sunrise Tower
- SAI CASTLE
- SHIVLEELA APARTMENT
- Shree Ganesh Heights
- Anuveena Heights
- Ananta Heights
- RAGHUNADAN HEIGHTS
- Avadh Residency
Other projects by Amit Builders
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.