by M PATANKAR BUILD CONS PRIVATE LIMITED · Tata Colony Junction, MumbaiAlso near Mulund East, Mulund West, Vile Parle East

Possession date of Mulund Ravi Kailash: 30 April 2022, moved from 31 October 2019 (30 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800009931. Status: Lapsed (registration period ended). 14 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (April 2022) has passed.

What do you want to know about Mulund Ravi Kailash?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Mulund Ravi Kailash has moved

  1. 31 October 2019

    Completion date given when the project was registered

  2. 30 October 2020

    Extended at the builder's request (MahaRERA application EXT51800002072)

    Reason the builder gave MahaRERA:
    “The work has got delayed because of the implication of GST rules, which made the billing and accounts procedure slower because of the lack of proper understanding, thus affecting the work flow. Addition to this, demonetisation have slowed t…” Read the full reason“The work has got delayed because of the implication of GST rules, which made the billing and accounts procedure slower because of the lack of proper understanding, thus affecting the work flow. Addition to this, demonetisation have slowed the payment resulting in the delay of work. Further, there was also a shortage of the material and labour in the project vicinity area. Thus, we request you to kindly grant us the extension for a period of 9 months. Also, we hereby declare that, the work won’t be delayed thereafter and we ensure to provide the possession within the revised date of completi…”
  3. 31 October 2021

    Extended at the builder's request (MahaRERA application EXT51800008549)

    Reason the builder gave MahaRERA:
    “The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of l…” Read the full reason“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We had already obtained part OC for the project and completed 85% of the construction work and are hopeful that once we receive project extension of only six months, we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects.”
  4. 30 April 2022

    Revised completion date on MahaRERA

Source: Mulund Ravi Kailash’s extension records on MahaRERA (P51800009931), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mulund Ravi Kailash

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 14 complaints, and how it ended
  • Construction pace against the April 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009931
Status
Lapsed (registration period ended)
Builder
M PATANKAR BUILD CONS PRIVATE LIMITED
Location
Tata Colony Junction, Mumbai · 400081
Project type
Others
Registered on
22 Aug 2017
Completion date at registration
October 2019
Latest completion date
April 2022
Delay so far
30 months
Homes
51
Towers
1
Complaints on MahaRERA
14
Court cases listed
0
Appeals at the tribunal
6
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Mulund Ravi Kailash, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Mulund Ravi Kailash100%100%85%75%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mulund Ravi Kailash every month.

Mulund Ravi Kailash: buildings, flats and land, as filed on MahaRERA

  • Buildings: Mulund Ravi Kailash (18 floors)
  • Land: 937 sq m (about 0.2 acres) · sanctioned built-up 1,517 sq m
  • Boundaries filed include: Navghar Road, Tata Colony Road, Vikram Society, Ravi Raj Society
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Mulund Ravi Kailash →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mulund Ravi Kailash: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Mulund Ravi Kailash

What is the possession date of Mulund Ravi Kailash?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mulund Ravi Kailash in Tata Colony Junction, Mumbai is 30 April 2022 — 30 months later than 31 October 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Mulund Ravi Kailash?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mulund Ravi Kailash's builder has filed on MahaRERA, the official one, is 30 April 2022, already 30 months later than the 31 October 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Mulund Ravi Kailash extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Mulund Ravi Kailash's builder applied to MahaRERA to extend the completion date 2 times: to 30 October 2020, giving the reason "The work has got delayed because of the implication of GST rules, which made the billing and accounts procedure slower because of the lack of proper understanding, thus affecting the work flow. Addition to this, demonetisation have slowed the payment resulting in the delay of work. Further, there was also a shortage of the material and labour in the project vicinity area. Thus, we request you to kindly grant us the extension for a period of 9 months. Also, we hereby declare that, the work won’t be delayed thereafter and we ensure to provide the possession within the revised date of completi…"; to 31 October 2021, giving the reason "The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We had already obtained part OC for the project and completed 85% of the construction work and are hopeful that once we receive project extension of only six months, we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects.".

What is the RERA number of Mulund Ravi Kailash?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mulund Ravi Kailash in Tata Colony Junction, Mumbai is P51800009931.

Is Mulund Ravi Kailash registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mulund Ravi Kailash is registered as P51800009931 and its status is "Lapsed (registration period ended)".

What is the construction status of Mulund Ravi Kailash?

According to GharKundli's check of MahaRERA records (updated November 2026), Mulund Ravi Kailash's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Mulund Ravi Kailash is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does Mulund Ravi Kailash have complaints on MahaRERA?

14 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Mulund Ravi Kailash safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Mulund Ravi Kailash is registered on MahaRERA as P51800009931, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and 14 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Mulund Ravi Kailash's possession date changes?

The latest dates are on Mulund Ravi Kailash's MahaRERA page (P51800009931). GharKundli's Kundli Watch sends a free WhatsApp update on Mulund Ravi Kailash every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mulund Ravi Kailash have?

According to GharKundli's check of MahaRERA records (updated November 2026), Mulund Ravi Kailash has one building filed: Mulund Ravi Kailash with 18 floors.

How big is the land of Mulund Ravi Kailash?

According to GharKundli's check of MahaRERA records (updated November 2026), Mulund Ravi Kailash stands on 937 sq m of land (about 0.2 acres), with 1,517 sq m of sanctioned built-up area.

Where can I read reviews of Mulund Ravi Kailash?

Google Maps has reviews of Mulund Ravi Kailash written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 14 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Mulund Ravi Kailash?

Mulund Ravi Kailash by M PATANKAR BUILD CONS PRIVATE LIMITED is in Tata Colony Junction, Mumbai (pincode 400081), near Mulund East, Mulund West, Vile Parle East, Maharashtra, and is registered on MahaRERA as P51800009931, per GharKundli's check of MahaRERA records. Its boundaries filed there include Navghar Road, Tata Colony Road, Vikram Society, Ravi Raj Society.

How many homes are in Mulund Ravi Kailash?

According to GharKundli's check of MahaRERA records (updated November 2026), Mulund Ravi Kailash has 51 homes in 1 tower registered on MahaRERA.

When was Mulund Ravi Kailash registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mulund Ravi Kailash was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Mulund Ravi Kailash?

No court cases are listed for Mulund Ravi Kailash on MahaRERA, and 6 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Mulund Ravi Kailash?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M PATANKAR BUILD CONS PRIVATE LIMITED, which has 1 other project registered on MahaRERA.

Other projects in Kurla

All 124 projects in Mulund East (400081) →

Other projects by M PATANKAR BUILD CONS PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.