Skip to content
GharKundli

NANDAN CARNIVAL B BUILDING

by NANDAN BUILDCON PVT LTD · Adgaon, NashikAlso near Panchvati

Possession date of NANDAN CARNIVAL B BUILDING: 31 July 2028, moved from 31 March 2019 (108 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600012244, and currently active. Its completion date has moved from March 2019 to July 2028: 108 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about NANDAN CARNIVAL B BUILDING?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NANDAN CARNIVAL B BUILDING has moved

  1. 31 March 2019

    Completion date given when the project was registered

  2. 30 March 2020

    Extended at the builder's request (MahaRERA application EXT51600001887)

    Reason the builder gave MahaRERA: “CONSTRUCTION ACTIVITY NOT COMPLETED DUE TO POOR SALE. HOWEVER 30% CONSTRUCTION IS COMPLETED BY OUR OWN FUND AND PART SALE OF FLAT.”
  3. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT51600025559)

    Reason the builder gave MahaRERA:
    “Due to no response from customers which resulted into insufficient, cash flow and there fore we had to stop the project construction. Now with the help of SWAMIH fund (A fund by Govt to revive the stopped projects), We are restarting the pr…” Read the full reason“Due to no response from customers which resulted into insufficient, cash flow and there fore we had to stop the project construction. Now with the help of SWAMIH fund (A fund by Govt to revive the stopped projects), We are restarting the project.”
  4. 31 March 2028

    Extended at the builder's request (MahaRERA application EA13032620211)

    Reason the builder gave MahaRERA:
    “We have restarted the work at the project site in the month of August 2025 after completing due diligence, obtaining necessary approvals, and receiving disbursement from the SWAMIH Fund. The SWAMIH Fund has sanctioned and disbursed the requ…” Read the full reason“We have restarted the work at the project site in the month of August 2025 after completing due diligence, obtaining necessary approvals, and receiving disbursement from the SWAMIH Fund. The SWAMIH Fund has sanctioned and disbursed the required funds to enable us to complete the entire construction of the project within the next 24 months. The progress of construction is reflected in our quarterly progress reports submitted from time to time. Further, sales in the project have commenced from the month of December 2025. However, we are pleased to inform you that with the assistance of the SW…”
  5. 31 July 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: NANDAN CARNIVAL B BUILDING’s extension records on MahaRERA (P51600012244), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NANDAN CARNIVAL B BUILDING

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the July 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600012244
Status
Registered and active
Builder
NANDAN BUILDCON PVT LTD
Location
Adgaon, Nashik · 422003
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
March 2019
Latest completion date
July 2028
Delay so far
108 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
104
Sold or booked
31%
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of NANDAN CARNIVAL B BUILDING, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NANDAN CARNIVAL B BUILDING100%90%60%5%

Commencement certificate (CC), as filed on MahaRERA

  • NANDAN CARNIVAL B BUILDING: covers 14 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NANDAN CARNIVAL B BUILDING every month.

NANDAN CARNIVAL B BUILDING: buildings, flats and land, as filed on MahaRERA

  • Buildings: NANDAN CARNIVAL B BUILDING (14 floors, 104 units)
  • Car parking: 89 covered, 29 open
  • Land: 2,076 sq m (about 0.5 acres) · sanctioned built-up 14,648 sq m · recreational space 2,069 sq m
  • Boundaries filed include: 60 MTR WIDE NATIONAL HIGHWAY

The builder’s record and reviews

Nandan Associates (a group of 2 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 10 months); 3 still being built, 3 past the promised date (typically 78 months late). 9 complaints on MahaRERA across 3 projects.

Read Google reviews of NANDAN CARNIVAL B BUILDING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NANDAN CARNIVAL B BUILDING: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NANDAN CARNIVAL B BUILDING

What is the possession date of NANDAN CARNIVAL B BUILDING?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NANDAN CARNIVAL B BUILDING in Adgaon, Nashik is 31 July 2028 — 108 months later than 31 March 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for NANDAN CARNIVAL B BUILDING?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NANDAN CARNIVAL B BUILDING's builder has filed on MahaRERA, the official one, is 31 July 2028, already 108 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NANDAN CARNIVAL B BUILDING extended?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDAN CARNIVAL B BUILDING's builder applied to MahaRERA to extend the completion date 3 times: to 30 March 2020, giving the reason "CONSTRUCTION ACTIVITY NOT COMPLETED DUE TO POOR SALE. HOWEVER 30% CONSTRUCTION IS COMPLETED BY OUR OWN FUND AND PART SALE OF FLAT."; to 31 March 2026, giving the reason "Due to no response from customers which resulted into insufficient, cash flow and there fore we had to stop the project construction. Now with the help of SWAMIH fund (A fund by Govt to revive the stopped projects), We are restarting the project."; to 31 March 2028, giving the reason "We have restarted the work at the project site in the month of August 2025 after completing due diligence, obtaining necessary approvals, and receiving disbursement from the SWAMIH Fund. The SWAMIH Fund has sanctioned and disbursed the required funds to enable us to complete the entire construction of the project within the next 24 months. The progress of construction is reflected in our quarterly progress reports submitted from time to time. Further, sales in the project have commenced from the month of December 2025. However, we are pleased to inform you that with the assistance of the SW…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of NANDAN CARNIVAL B BUILDING?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NANDAN CARNIVAL B BUILDING in Adgaon, Nashik is P51600012244.

Is NANDAN CARNIVAL B BUILDING registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDAN CARNIVAL B BUILDING is registered as P51600012244 and its status is "Registered and active".

What is the construction status of NANDAN CARNIVAL B BUILDING?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDAN CARNIVAL B BUILDING's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NANDAN CARNIVAL B BUILDING is 90% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does NANDAN CARNIVAL B BUILDING have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is NANDAN CARNIVAL B BUILDING safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDAN CARNIVAL B BUILDING is registered on MahaRERA as P51600012244, its completion date has moved 108 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NANDAN CARNIVAL B BUILDING's possession date changes?

The latest dates are on NANDAN CARNIVAL B BUILDING's MahaRERA page (P51600012244). GharKundli's Kundli Watch sends a free WhatsApp update on NANDAN CARNIVAL B BUILDING every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NANDAN CARNIVAL B BUILDING have?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDAN CARNIVAL B BUILDING has one building filed: NANDAN CARNIVAL B BUILDING with 14 floors and 104 units.

How much parking does NANDAN CARNIVAL B BUILDING have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 89 covered and 29 open car parking spaces for NANDAN CARNIVAL B BUILDING.

How big is the land of NANDAN CARNIVAL B BUILDING?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDAN CARNIVAL B BUILDING stands on 2,076 sq m of land (about 0.5 acres), with 14,648 sq m of sanctioned built-up area and 2,069 sq m of recreational open space.

What is the track record of NANDAN CARNIVAL B BUILDING's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Nandan Associates (a group of 2 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 10 months); 3 still being built, 3 past the promised date (typically 78 months late). 9 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NANDAN CARNIVAL B BUILDING?

Google Maps has reviews of NANDAN CARNIVAL B BUILDING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NANDAN CARNIVAL B BUILDING?

NANDAN CARNIVAL B BUILDING by NANDAN BUILDCON PVT LTD is in Adgaon, Nashik (pincode 422003), near Panchvati, Maharashtra, and is registered on MahaRERA as P51600012244, per GharKundli's check of MahaRERA records. Its boundaries filed there include 60 MTR WIDE NATIONAL HIGHWAY.

How many homes are in NANDAN CARNIVAL B BUILDING?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDAN CARNIVAL B BUILDING has 104 homes in 1 tower registered on MahaRERA, and 31% of them are sold or booked.

When was NANDAN CARNIVAL B BUILDING registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NANDAN CARNIVAL B BUILDING was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on NANDAN CARNIVAL B BUILDING?

No court cases are listed for NANDAN CARNIVAL B BUILDING on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of NANDAN CARNIVAL B BUILDING?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NANDAN BUILDCON PVT LTD, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2028 in Nashik →

Other projects in pincode 422003

All 289 projects in Panchvati (422003) →

Other projects by NANDAN BUILDCON PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.