Tirupati Ramchandra Niwas
by SHREE TIRUPATI DEVELOPERS · Mulund West, Mumbai 400080Also near Mulund EastRegistered on MahaRERA as “RAMCHANDRA NIWAS”
What’s in the report? →Possession: Tirupati Ramchandra Niwas (MahaRERA P51800004025) is marked completed on MahaRERA. It has 10 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800004025. Status: Completed.
Source: MahaRERA website — records for P51800004025, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Tirupati Ramchandra Niwas?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Tirupati Ramchandra Niwas has moved
30 December 2021
Completion date given when the project was registered
30 December 2022
Extended at the builder's request (MahaRERA application EXT51800011239)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of the project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of the project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19.”30 June 2023
Extended at the builder's request (MahaRERA application EXT51800013454)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 100 % allottees for purpose of extension of RERA registration period of the said project.”31 December 2023
Extended at the builder's request (MahaRERA application EXT51800017090)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 100% allottees for purpose of extension of RERA registration period of the said project”30 June 2024
Extended at the builder's request (MahaRERA application EXT51800018759)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 66.67% allottees for purpose of extension of RERA registration period of the said project.”
Source: Tirupati Ramchandra Niwas’s extension records on MahaRERA (P51800004025), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Tirupati Ramchandra Niwas
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800004025
- Status
- Completed
- Builder
- SHREE TIRUPATI DEVELOPERS
- Location
- Mulund West, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 7 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- June 2024
- Delay so far
- 30 months
- Homes
- 10
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Tirupati Ramchandra Niwas, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RAMCHANDRA NIWAS | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tirupati Ramchandra Niwas every 1–2 months.
Tirupati Ramchandra Niwas: buildings, flats and land, as filed on MahaRERA
- Buildings: RAMCHANDRA NIWAS (23 floors)
- Land: 496 sq m (about 0.1 acres) · sanctioned built-up 616 sq m
- Land, as filed: PLOT NO.189, SURVEY NO. 1000,CTS NO. 1416
- Map: Get directions
The builder’s record and reviews
Shree Tirupati Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 16 months). 3 complaints on MahaRERA across 1 project.
Read Google reviews of Tirupati Ramchandra Niwas →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Tirupati Ramchandra Niwas: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Tirupati Ramchandra Niwas
What is the possession date of Tirupati Ramchandra Niwas?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tirupati Ramchandra Niwas in Mulund West, Mumbai is 30 June 2024 — 30 months later than 30 December 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Tirupati Ramchandra Niwas?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Tirupati Ramchandra Niwas's builder has filed on MahaRERA, the official one, is 30 June 2024, already 30 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Tirupati Ramchandra Niwas extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Ramchandra Niwas's builder applied to MahaRERA to extend the completion date 4 times: to 30 December 2022, giving the reason "In accordance with circular no 28, we hereby apply for extension of the project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19."; to 30 June 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 100 % allottees for purpose of extension of RERA registration period of the said project."; to 31 December 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 100% allottees for purpose of extension of RERA registration period of the said project"; to 30 June 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 66.67% allottees for purpose of extension of RERA registration period of the said project.".
What is the RERA number of Tirupati Ramchandra Niwas?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tirupati Ramchandra Niwas in Mulund West, Mumbai is P51800004025.
Is Tirupati Ramchandra Niwas registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Ramchandra Niwas is registered as P51800004025 and its status is "Completed".
What is the current construction status of Tirupati Ramchandra Niwas? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Ramchandra Niwas's status on MahaRERA is "Completed". As filed by the builder, slab work on RAMCHANDRA NIWAS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Tirupati Ramchandra Niwas have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Tirupati Ramchandra Niwas safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Ramchandra Niwas is registered on MahaRERA as P51800004025, its MahaRERA status is "Completed", its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Tirupati Ramchandra Niwas?
According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Ramchandra Niwas is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Tirupati Ramchandra Niwas?
For a flat in Tirupati Ramchandra Niwas (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Tirupati Ramchandra Niwas received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Ramchandra Niwas is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Tirupati Ramchandra Niwas completed?
According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Ramchandra Niwas is marked completed on MahaRERA, and the completion date filed there is 30 June 2024. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Has Tirupati Ramchandra Niwas uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Tirupati Ramchandra Niwas was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Tirupati Ramchandra Niwas's possession date changes?
The latest dates are on Tirupati Ramchandra Niwas's MahaRERA page (P51800004025). GharKundli's Kundli Watch sends a free WhatsApp update on Tirupati Ramchandra Niwas every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Tirupati Ramchandra Niwas have?
According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Ramchandra Niwas has one building filed: RAMCHANDRA NIWAS with 23 floors.
How big is the land of Tirupati Ramchandra Niwas?
According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Ramchandra Niwas stands on 496 sq m of land (about 0.1 acres), with 616 sq m of sanctioned built-up area.
What is the track record of Tirupati Ramchandra Niwas's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Tirupati Developers (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 finished, 0 within the promised date and 3 needed more time (typically 16 months). 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Tirupati Ramchandra Niwas?
Google Maps has reviews of Tirupati Ramchandra Niwas written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Tirupati Ramchandra Niwas?
Tirupati Ramchandra Niwas by SHREE TIRUPATI DEVELOPERS is in Mulund West, Mumbai, pincode 400080 (near Mulund East), Maharashtra, and is registered on MahaRERA as P51800004025, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO.189, SURVEY NO. 1000,CTS NO. 1416. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).
How many flats are in Tirupati Ramchandra Niwas?
According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Ramchandra Niwas has 10 homes in 1 tower registered on MahaRERA.
When was Tirupati Ramchandra Niwas registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tirupati Ramchandra Niwas was registered on MahaRERA on 7 August 2017. GharKundli did not find a title report on the land on file there.
Does Tirupati Ramchandra Niwas have any legal issues or court cases?
No court cases are listed for Tirupati Ramchandra Niwas on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Tirupati Ramchandra Niwas?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE TIRUPATI DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Tirupati Ramchandra Niwas
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mulund West (400080)
- Malhar Guide
- Arihant Royale
- The Sanctuary - Tower 5
- Keshavpada
- Dhanraj Tower
- Old Hemant Villa Co. Op. Housing Soc. LTD.
- Madhuvan Nivanta
- Shraddha Paradise Enclave
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.