Tandice
by MANISH MAHESH DHOLAKIA · Kandivali West, Mumbai 400067Also near Bandra, Iraniwadi, Malad West
What’s in the report? →Possession date of Tandice (MahaRERA P51800010353): 30 September 2025, moved from 31 July 2019 (74 months later), and it has already passed. It has 35 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800010353. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800010353, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (September 2025) has passed.
What do you want to know about Tandice?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Tandice has moved
31 July 2019
Completion date given when the project was registered
30 July 2020
Extended at the builder's request (MahaRERA application EXT51800003651)
Reason the builder gave MahaRERA:
“As per the details mentioned at the time of registration of the project at the Maharera Website we have mentioned 31.07.2019 as the project completion date. However, we were not able to complete the construction work since there was a lack…” Read the full reason
“As per the details mentioned at the time of registration of the project at the Maharera Website we have mentioned 31.07.2019 as the project completion date. However, we were not able to complete the construction work since there was a lack of labour followed by demonitization. Hence, we would like to seek an extension period of one year for the completion of the said project ie. till 30.07.2020.”31 January 2023
Extended at the builder's request (MahaRERA application EXT51800009348)
Reason the builder gave MahaRERA:
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of l…” Read the full reason
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We are on the verge of completing the construction work and are hopeful that once we receive project extension we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects. We also have the required number of consents from the allottees.”30 September 2025
Extended at the builder's request (MahaRERA application EXT51800021924)
Reason the builder gave MahaRERA:
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of l…” Read the full reason
“The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market and struggling to find resources to complete the project. Now we have arranged the fund and Competed the Entire RCC and Finishing Work. We have following pending Work Lift installation, BMC water connection and compound beautification work we are hopeful that once we receive project extension we shall obtain Occ…”
Source: Tandice’s extension records on MahaRERA (P51800010353), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Tandice
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the September 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800010353
- Status
- Lapsed (registration period ended)
- Builder
- MANISH MAHESH DHOLAKIA
- Location
- Kandivali West, Mumbai · 400067
- Project type
- Residential / Group Housing
- Registered on
- 24 Aug 2017
- Completion date at registration
- July 2019
- Latest completion date
- September 2025
- Delay so far
- 74 months
- Homes
- 35
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Tandice, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TANDICE | 70% | 90% | 65% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tandice every 1–2 months.
Tandice: buildings, flats and land, as filed on MahaRERA
- Buildings: TANDICE (9 floors)
- Land: 1,502 sq m (about 0.4 acres) · sanctioned built-up 2,420 sq m
- Land, as filed: 960, 960/1 TO 18
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Tandice →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Tandice: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Tandice
What is the possession date of Tandice?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tandice in Kandivali West, Mumbai is 30 September 2025 — 74 months later than 31 July 2019, the date given at registration. That date has already passed.
The date has already moved 74 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Tandice?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Tandice's builder has filed on MahaRERA, the official one, is 30 September 2025, already 74 months later than the 31 July 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Tandice extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Tandice's builder applied to MahaRERA to extend the completion date 3 times: to 30 July 2020, giving the reason "As per the details mentioned at the time of registration of the project at the Maharera Website we have mentioned 31.07.2019 as the project completion date. However, we were not able to complete the construction work since there was a lack of labour followed by demonitization. Hence, we would like to seek an extension period of one year for the completion of the said project ie. till 30.07.2020."; to 31 January 2023, giving the reason "The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market. We are on the verge of completing the construction work and are hopeful that once we receive project extension we shall obtain Occupancy Certificate from the Competent Authority and complete the project in all aspects. We also have the required number of consents from the allottees."; to 30 September 2025, giving the reason "The Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and liquidity crunch in the market and struggling to find resources to complete the project. Now we have arranged the fund and Competed the Entire RCC and Finishing Work. We have following pending Work Lift installation, BMC water connection and compound beautification work we are hopeful that once we receive project extension we shall obtain Occ…".
What is the RERA number of Tandice?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tandice in Kandivali West, Mumbai is P51800010353.
Is Tandice registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tandice is registered as P51800010353 and its status is "Lapsed (registration period ended)".
What is the current construction status of Tandice? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Tandice's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on TANDICE is 90% done and internal work 65%. GharKundli's full report compares construction progress with the deadline.
Does Tandice have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Tandice safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Tandice is registered on MahaRERA as P51800010353, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 74 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Tandice?
Tandice isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Tandice?
For a flat in Tandice (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Tandice received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Tandice isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Tandice?
According to GharKundli's check of MahaRERA records (updated October 2026), Tandice's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Tandice uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Tandice was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Tandice's possession date changes?
The latest dates are on Tandice's MahaRERA page (P51800010353). GharKundli's Kundli Watch sends a free WhatsApp update on Tandice every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Tandice have?
According to GharKundli's check of MahaRERA records (updated October 2026), Tandice has one building filed: TANDICE with 9 floors.
How big is the land of Tandice?
According to GharKundli's check of MahaRERA records (updated October 2026), Tandice stands on 1,502 sq m of land (about 0.4 acres), with 2,420 sq m of sanctioned built-up area.
What are the reviews of Tandice?
Google Maps has reviews of Tandice written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Tandice?
Tandice by MANISH MAHESH DHOLAKIA is in Kandivali West, Mumbai, pincode 400067 (near Bandra, Iraniwadi, Malad West), Maharashtra, and is registered on MahaRERA as P51800010353, per GharKundli's check of MahaRERA records. Its land is filed as 960, 960/1 TO 18. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).
How many flats are in Tandice?
According to GharKundli's check of MahaRERA records (updated October 2026), Tandice has 35 homes in 1 tower registered on MahaRERA.
When was Tandice registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tandice was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.
Does Tandice have any legal issues or court cases?
1 court case is listed for Tandice on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Tandice?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MANISH MAHESH DHOLAKIA.
Check it yourself on MahaRERA
- How to check the possession date of Tandice
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kandivali West (400067)
- Jayakar House
- Sigma Amber
- MPR Shri Paras Darshan
- Saffronwoods CHSL
- Charkop Shree Ganesh CHS LTD
- LA SERENA Tower 5, Tower 6 and Tower 7
- Avenue Wing B phase 2
- Prime Square
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.