Skip to content
GharKundli

Nilkanth Apartment

by BHARATBHAI KARSANBHAI ADROJA · Mane Nagar, Hirawadi, Panchvati, Nashik, Nashik 422003

What’s in the report? →

Possession: Nilkanth Apartment (MahaRERA P51600021654) is marked completed on MahaRERA. It has 32 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600021654. Status: Completed.

Source: MahaRERA website — records for P51600021654, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Nilkanth Apartment?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Nilkanth Apartment

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600021654
Status
Completed
Builder
BHARATBHAI KARSANBHAI ADROJA
Location
Mane Nagar, Hirawadi, Panchvati, Nashik, Nashik · 422003
Project type
Residential / Group Housing
Registered on
19 Jul 2019
Completion date at registration
December 2025
Latest completion date
December 2025
Homes
32
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Nilkanth Apartment, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NILKANTH APARTMENT100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nilkanth Apartment every 1–2 months.

Nilkanth Apartment: buildings, flats and land, as filed on MahaRERA

  • Buildings: NILKANTH APARTMENT (6 floors)
  • Land: 800 sq m (about 0.2 acres) · sanctioned built-up 1,369 sq m
  • Land, as filed: PLOT NO 9 TO 10/13 TO 14, S NO 237/2/2/9 TO 10/13 TO 14
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Nilkanth Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Nilkanth Apartment: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Nilkanth Apartment

What is the possession date of Nilkanth Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Nilkanth Apartment in Mane Nagar, Hirawadi, Panchvati, Nashik, Nashik is 30 December 2025.

Is the builder's possession date different from the MahaRERA date for Nilkanth Apartment?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Nilkanth Apartment's builder has filed on MahaRERA, the official one, is 30 December 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Nilkanth Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Nilkanth Apartment in Mane Nagar, Hirawadi, Panchvati, Nashik, Nashik is P51600021654.

Is Nilkanth Apartment registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Nilkanth Apartment is registered as P51600021654 and its status is "Completed".

What is the current construction status of Nilkanth Apartment? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Nilkanth Apartment's status on MahaRERA is "Completed". As filed by the builder, slab work on NILKANTH APARTMENT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Nilkanth Apartment have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Nilkanth Apartment safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Nilkanth Apartment is registered on MahaRERA as P51600021654, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Nilkanth Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Nilkanth Apartment is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Nilkanth Apartment?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Nilkanth Apartment: gharkundli.com/tools/property-cost-calculator

Has Nilkanth Apartment received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Nilkanth Apartment is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Nilkanth Apartment completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Nilkanth Apartment is marked completed on MahaRERA, and the completion date filed there is 30 December 2025. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Nilkanth Apartment uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Nilkanth Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Nilkanth Apartment's possession date changes?

The latest dates are on Nilkanth Apartment's MahaRERA page (P51600021654). GharKundli's Kundli Watch sends a free WhatsApp update on Nilkanth Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Nilkanth Apartment have?

According to GharKundli's check of MahaRERA records (updated November 2026), Nilkanth Apartment has one building filed: NILKANTH APARTMENT with 6 floors.

How big is the land of Nilkanth Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Nilkanth Apartment stands on 800 sq m of land (about 0.2 acres), with 1,369 sq m of sanctioned built-up area.

What are the reviews of Nilkanth Apartment?

Google Maps has reviews of Nilkanth Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Nilkanth Apartment?

Nilkanth Apartment by BHARATBHAI KARSANBHAI ADROJA is in Mane Nagar, Hirawadi, Panchvati, Nashik, Nashik, pincode 422003, Maharashtra, and is registered on MahaRERA as P51600021654, per GharKundli's check of MahaRERA records. Its land is filed as PLOT NO 9 TO 10/13 TO 14, S NO 237/2/2/9 TO 10/13 TO 14. GharKundli lists all 735 MahaRERA projects in Panchvati (422003).

How many flats are in Nilkanth Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), Nilkanth Apartment has 32 homes in 1 tower registered on MahaRERA.

When was Nilkanth Apartment registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Nilkanth Apartment was registered on MahaRERA on 19 July 2019. GharKundli did not find a title report on the land on file there.

Does Nilkanth Apartment have any legal issues or court cases?

No court cases are listed for Nilkanth Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Nilkanth Apartment?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is BHARATBHAI KARSANBHAI ADROJA.

Other projects in Panchvati (422003)

All 735 projects in Panchvati (422003) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.