Skip to content
GharKundli

Krushna Pride - 1

by NAMDEO GOVIND BORHADE · Pathardi Shivar, Nashik 422010Also near Ambad A.S, Shirdi

What’s in the report? →

Possession: Krushna Pride - 1 (MahaRERA P51600027619) is marked completed on MahaRERA. It has 51 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600027619. Status: Completed.

Source: MahaRERA website — records for P51600027619, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Krushna Pride - 1?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Krushna Pride - 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51600027619
Status
Completed
Builder
NAMDEO GOVIND BORHADE
Location
Pathardi Shivar, Nashik · 422010
Project type
Others
Registered on
23 Dec 2020
Completion date at registration
June 2024
Latest completion date
June 2024
Homes
51
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Krushna Pride - 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KRUSHNA PRIDE - 1100%6%80%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Krushna Pride - 1 every 1–2 months.

Krushna Pride - 1: buildings, flats and land, as filed on MahaRERA

  • Buildings: KRUSHNA PRIDE - 1 (5 floors)
  • Land: 870 sq m (about 0.2 acres) · sanctioned built-up 2,403 sq m
  • Land, as filed: Plot No 1 s no 203/1/2/4/1A/2/3 Pathardi
  • Map: Get directions

The builder’s record and reviews

Namdeo Govind Borhade has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Krushna Pride - 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Krushna Pride - 1: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Krushna Pride - 1

What is the possession date of Krushna Pride - 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Krushna Pride - 1 in Pathardi Shivar, Nashik is 30 June 2024.

Is the builder's possession date different from the MahaRERA date for Krushna Pride - 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Krushna Pride - 1's builder has filed on MahaRERA, the official one, is 30 June 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Krushna Pride - 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Krushna Pride - 1 in Pathardi Shivar, Nashik is P51600027619.

Is Krushna Pride - 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride - 1 is registered as P51600027619 and its status is "Completed".

What is the current construction status of Krushna Pride - 1? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride - 1's status on MahaRERA is "Completed". As filed by the builder, slab work on KRUSHNA PRIDE - 1 is 6% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Krushna Pride - 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Krushna Pride - 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride - 1 is registered on MahaRERA as P51600027619, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Krushna Pride - 1?

According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride - 1 is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Krushna Pride - 1?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Krushna Pride - 1: gharkundli.com/tools/property-cost-calculator

Has Krushna Pride - 1 received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride - 1 is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Krushna Pride - 1 completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride - 1 is marked completed on MahaRERA, and the completion date filed there is 30 June 2024. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Krushna Pride - 1 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Krushna Pride - 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Krushna Pride - 1 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: KRUSHNA PRIDE 3 (P51600054583, possession 30 Apr 2027). Check that your agreement names the registration of your own wing.

How can I get updates if Krushna Pride - 1's possession date changes?

The latest dates are on Krushna Pride - 1's MahaRERA page (P51600027619). GharKundli's Kundli Watch sends a free WhatsApp update on Krushna Pride - 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Krushna Pride - 1 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride - 1 has one building filed: KRUSHNA PRIDE - 1 with 5 floors.

How big is the land of Krushna Pride - 1?

According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride - 1 stands on 870 sq m of land (about 0.2 acres), with 2,403 sq m of sanctioned built-up area.

What is the track record of Krushna Pride - 1's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Namdeo Govind Borhade has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Krushna Pride - 1?

Google Maps has reviews of Krushna Pride - 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Krushna Pride - 1?

Krushna Pride - 1 by NAMDEO GOVIND BORHADE is in Pathardi Shivar, Nashik, pincode 422010 (near Ambad A.S, Shirdi), Maharashtra, and is registered on MahaRERA as P51600027619, per GharKundli's check of MahaRERA records. Its land is filed as Plot No 1 s no 203/1/2/4/1A/2/3 Pathardi. GharKundli lists all 462 MahaRERA projects in Ambad (422010).

How many flats are in Krushna Pride - 1?

According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride - 1 has 51 homes in 1 tower registered on MahaRERA.

When was Krushna Pride - 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Krushna Pride - 1 was registered on MahaRERA on 23 December 2020. GharKundli did not find a title report on the land on file there.

Does Krushna Pride - 1 have any legal issues or court cases?

No court cases are listed for Krushna Pride - 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Krushna Pride - 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NAMDEO GOVIND BORHADE, which has 1 other project registered on MahaRERA.

Other projects in Ambad (422010)

All 462 projects in Ambad (422010) →

Other projects by NAMDEO GOVIND BORHADE

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.