ROOPRAJAT ENCLAVE

by SIDDHIVINAYAK DEVELOPERS · Borivali East, MumbaiAlso near Borivali West, Rajendra Nagar, Daulat Nagar

Possession date of ROOPRAJAT ENCLAVE: 30 April 2027, moved from 30 December 2021 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800004097, and currently active. Its completion date has moved from December 2021 to April 2027: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 19 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ROOPRAJAT ENCLAVE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ROOPRAJAT ENCLAVE has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51800010907)

    Reason the builder gave MahaRERA:
    “Due to a dispute between partners and the bank account was frizzed we are unable to complete the project in the timeline. We are now requesting the Maharera Authority to grant us the extension till 30th June 2024. All the necessary requirem…” Read the full reason“Due to a dispute between partners and the bank account was frizzed we are unable to complete the project in the timeline. We are now requesting the Maharera Authority to grant us the extension till 30th June 2024. All the necessary requirement has been fulfilled and we have taken consent from allottes as well.”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800024270)

    Reason the builder gave MahaRERA: “DUE TO SOME FINANCIAL CONSTRAINTS AND DELAYED PAYMENTS FROM CLIENTS WE COULD NOT COMPLETE PROJECT ON TIME . KINDLY GRANT US EXTENTION TILL 30-06-2025”
  4. 31 December 2026

    Extended at the builder's request (MahaRERA application EA30072502254)

    Reason the builder gave MahaRERA: “DUE TO SOME FINANCIAL CONSTRAINTS AND DELAYED PAYMENTS FROM CLIENTS WE COULD NOT COMPLETE PROJECT ON TIME”
  5. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ROOPRAJAT ENCLAVE’s extension records on MahaRERA (P51800004097), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ROOPRAJAT ENCLAVE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 19 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800004097
Status
Registered and active
Builder
SIDDHIVINAYAK DEVELOPERS
Location
Borivali East, Mumbai · 400066
Project type
Others
Registered on
8 Aug 2017
Completion date at registration
December 2021
Latest completion date
April 2027
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
70
Sold or booked
98%
Towers
2
Complaints on MahaRERA
19
Court cases listed
0
Appeals at the tribunal
5
Title report on file
Not found
Builder's other MahaRERA projects
46

Construction progress of ROOPRAJAT ENCLAVE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHIVSHAKTI - REHAB100%100%100%100%
ROOPRAJAT ENCLAVE - SALE0%48%25%0%

Commencement certificate (CC), as filed on MahaRERA

  • ROOPRAJAT ENCLAVE - SALE: covers Up to plinth level

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ROOPRAJAT ENCLAVE every month.

ROOPRAJAT ENCLAVE: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Unspecified—198
1 BHK47535
2 BHK70034
Shops2269
Office Space4,8941
1 Room Kitchen4751
  • Buildings: SHIVSHAKTI - REHAB (8 floors) · ROOPRAJAT ENCLAVE - SALE (25 floors, 80 units)
  • Land: 2,031 sq m (about 0.5 acres) · sanctioned built-up 6,093 sq m · recreational space 304 sq m
  • Boundaries filed include: 7 CARTER ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of ROOPRAJAT ENCLAVE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ROOPRAJAT ENCLAVE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ROOPRAJAT ENCLAVE

What is the possession date of ROOPRAJAT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ROOPRAJAT ENCLAVE in Borivali East, Mumbai is 30 April 2027 — 60 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ROOPRAJAT ENCLAVE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ROOPRAJAT ENCLAVE's builder has filed on MahaRERA, the official one, is 30 April 2027, already 60 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ROOPRAJAT ENCLAVE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ROOPRAJAT ENCLAVE's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2024, giving the reason "Due to a dispute between partners and the bank account was frizzed we are unable to complete the project in the timeline. We are now requesting the Maharera Authority to grant us the extension till 30th June 2024. All the necessary requirement has been fulfilled and we have taken consent from allottes as well."; to 30 June 2025, giving the reason "DUE TO SOME FINANCIAL CONSTRAINTS AND DELAYED PAYMENTS FROM CLIENTS WE COULD NOT COMPLETE PROJECT ON TIME . KINDLY GRANT US EXTENTION TILL 30-06-2025"; to 31 December 2026, giving the reason "DUE TO SOME FINANCIAL CONSTRAINTS AND DELAYED PAYMENTS FROM CLIENTS WE COULD NOT COMPLETE PROJECT ON TIME". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of ROOPRAJAT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ROOPRAJAT ENCLAVE in Borivali East, Mumbai is P51800004097.

Is ROOPRAJAT ENCLAVE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ROOPRAJAT ENCLAVE is registered as P51800004097 and its status is "Registered and active".

What is the construction status of ROOPRAJAT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), ROOPRAJAT ENCLAVE's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 48% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does ROOPRAJAT ENCLAVE have complaints on MahaRERA?

19 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ROOPRAJAT ENCLAVE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ROOPRAJAT ENCLAVE is registered on MahaRERA as P51800004097, its completion date has moved 60 months since registration and 19 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ROOPRAJAT ENCLAVE's possession date changes?

The latest dates are on ROOPRAJAT ENCLAVE's MahaRERA page (P51800004097). GharKundli's Kundli Watch sends a free WhatsApp update on ROOPRAJAT ENCLAVE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ROOPRAJAT ENCLAVE have?

According to GharKundli's check of MahaRERA records (updated October 2026), ROOPRAJAT ENCLAVE has 2 buildings filed: SHIVSHAKTI - REHAB with 8 floors; ROOPRAJAT ENCLAVE - SALE with 25 floors and 80 units.

What are the flat sizes (carpet area) in ROOPRAJAT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ROOPRAJAT ENCLAVE: 1 BHK: 475 sq ft carpet (35 homes); 2 BHK: 700 sq ft carpet (34 homes); 1 Room Kitchen: 475 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of ROOPRAJAT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), ROOPRAJAT ENCLAVE stands on 2,031 sq m of land (about 0.5 acres), with 6,093 sq m of sanctioned built-up area and 304 sq m of recreational open space.

Where can I read reviews of ROOPRAJAT ENCLAVE?

Google Maps has reviews of ROOPRAJAT ENCLAVE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 19 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ROOPRAJAT ENCLAVE?

ROOPRAJAT ENCLAVE by SIDDHIVINAYAK DEVELOPERS is in Borivali East, Mumbai (pincode 400066), near Borivali West, Rajendra Nagar, Daulat Nagar, Maharashtra, and is registered on MahaRERA as P51800004097, per GharKundli's check of MahaRERA records. Its boundaries filed there include 7 CARTER ROAD.

How many homes are in ROOPRAJAT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), ROOPRAJAT ENCLAVE has 70 homes in 2 towers registered on MahaRERA, and 98% of them are sold or booked.

When was ROOPRAJAT ENCLAVE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ROOPRAJAT ENCLAVE was registered on MahaRERA on 8 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on ROOPRAJAT ENCLAVE?

No court cases are listed for ROOPRAJAT ENCLAVE on MahaRERA, and 5 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of ROOPRAJAT ENCLAVE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SIDDHIVINAYAK DEVELOPERS, which has 46 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400066

All 228 projects in Borivali East (400066) →

Other projects by SIDDHIVINAYAK DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.