ROYAL MEADOWS C 1 , C 2

by SIDDHIVINAYAK DEVELOPERS · Shahad, Thane

Possession date of ROYAL MEADOWS C 1 , C 2: 31 December 2025, moved from 1 September 2020 (63 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700008736. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about ROYAL MEADOWS C 1 , C 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ROYAL MEADOWS C 1 , C 2 has moved

  1. 1 September 2020

    Completion date given when the project was registered

  2. 31 August 2021

    Extended at the builder's request (MahaRERA application EXT51700003878)

    Reason the builder gave MahaRERA:
    “We have completed major construction work of our project “Royal Meadows C1,C2” bearing RERA Registration No. P51700008736 , but our project being located in mofussil area, we are facing many difficulties in procuring quality of material and…” Read the full reason“We have completed major construction work of our project “Royal Meadows C1,C2” bearing RERA Registration No. P51700008736 , but our project being located in mofussil area, we are facing many difficulties in procuring quality of material and manpower. Due to which our scheduled work is delayed. For the sake of completing it on the actual proposed date i.e. 01/09/2020 we cannot compromise in the quality of service. Hence we request you to grant us the revised date of completion as 31/08/2021 for our Project “Royal Meadows C1,C2” - being Registration No.P51700008736.”
  3. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT51700012486)

    Reason the builder gave MahaRERA:
    “The project is under construction & we have completed more than 90% work of the project. However due to imposition of lockdown and consequently migration of labour and contractors and scarcity of material, we are facing difficulty in arrang…” Read the full reason“The project is under construction & we have completed more than 90% work of the project. However due to imposition of lockdown and consequently migration of labour and contractors and scarcity of material, we are facing difficulty in arranging the manpower and Material to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to the above said reasons only the completion of the project has been delayed. Hence we request your honour to kindly grant us the revised date of completion as 31/12…”
  4. 31 March 2023

    Extended at the builder's request (MahaRERA application EXT51700013645)

    Reason the builder gave MahaRERA:
    “The project is under construction & we have completed more than 95% work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to comple…” Read the full reason“The project is under construction & we have completed more than 95% work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID – 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 31/03/2023 for our Project – “Royal Meadows C1, C2” bearing Registration No. P51700008736.”
  5. 31 December 2025

    Extended at the builder's request (MahaRERA application EA12072502063)

    Reason the builder gave MahaRERA:
    “The delay in obtaining the final Occupancy Certificate (OC) is primarily due to the pending completion of the clubhouse, which forms an essential amenity within the project. While the main residential buildings have been completed and are f…” Read the full reason“The delay in obtaining the final Occupancy Certificate (OC) is primarily due to the pending completion of the clubhouse, which forms an essential amenity within the project. While the main residential buildings have been completed and are fit for occupation, we have already received the Occupancy Certificate for building on 24/05/2023, and a Part Occupancy Certificate for additional completed components all common amenities, including the clubhouse was subsequently granted on 24/06/2025. In view of the above and to ensure continued compliance with RERA requirements, we have applied for an e…”

Source: ROYAL MEADOWS C 1 , C 2’s extension records on MahaRERA (P51700008736), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ROYAL MEADOWS C 1 , C 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700008736
Status
Lapsed (registration period ended)
Builder
SIDDHIVINAYAK DEVELOPERS
Location
Shahad, Thane · 421301
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
September 2020
Latest completion date
December 2025
Delay so far
63 months
Homes
188
Sold or booked
95%
Towers
2
Complaints on MahaRERA
3
Court cases listed
0
Appeals at the tribunal
2
Title report on file
Not found
Builder's other MahaRERA projects
46

Construction progress of ROYAL MEADOWS C 1 , C 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
C 1 - RIDDHI100%100%100%80%
C - 2 SIDDHI100%100%100%80%

Commencement certificate (CC), as filed on MahaRERA

  • C 1 - RIDDHI: covers 17 floors
  • C - 2 SIDDHI: covers 17 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ROYAL MEADOWS C 1 , C 2 every month.

ROYAL MEADOWS C 1 , C 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: C 1 - RIDDHI (18 floors, 94 units) · C - 2 SIDDHI (18 floors, 94 units)
  • Car parking: 76 covered
  • Land: 5,589 sq m (about 1.4 acres) · sanctioned built-up 4,553 sq m · recreational space 828 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of ROYAL MEADOWS C 1 , C 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ROYAL MEADOWS C 1 , C 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ROYAL MEADOWS C 1 , C 2

What is the possession date of ROYAL MEADOWS C 1 , C 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ROYAL MEADOWS C 1 , C 2 in Shahad, Thane is 31 December 2025 — 63 months later than 1 September 2020, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for ROYAL MEADOWS C 1 , C 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ROYAL MEADOWS C 1 , C 2's builder has filed on MahaRERA, the official one, is 31 December 2025, already 63 months later than the 1 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ROYAL MEADOWS C 1 , C 2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL MEADOWS C 1 , C 2's builder applied to MahaRERA to extend the completion date 4 times: to 31 August 2021, giving the reason "We have completed major construction work of our project “Royal Meadows C1,C2” bearing RERA Registration No. P51700008736 , but our project being located in mofussil area, we are facing many difficulties in procuring quality of material and manpower. Due to which our scheduled work is delayed. For the sake of completing it on the actual proposed date i.e. 01/09/2020 we cannot compromise in the quality of service. Hence we request you to grant us the revised date of completion as 31/08/2021 for our Project “Royal Meadows C1,C2” - being Registration No.P51700008736."; to 31 December 2022, giving the reason "The project is under construction & we have completed more than 90% work of the project. However due to imposition of lockdown and consequently migration of labour and contractors and scarcity of material, we are facing difficulty in arranging the manpower and Material to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to the above said reasons only the completion of the project has been delayed. Hence we request your honour to kindly grant us the revised date of completion as 31/12…"; to 31 March 2023, giving the reason "The project is under construction & we have completed more than 95% work on the project. However due to imposition of lockdown and consequently migration of labour and contractors we are facing difficulty in arranging the manpower to complete the project on time. Though while registering the project under RERA we were sure to complete the project on time i.e. on our proposed date, but due to this pandemic COVID – 19 it is getting delayed. Hence we request you to grant us the revised date of completion as 31/03/2023 for our Project – “Royal Meadows C1, C2” bearing Registration No. P51700008736."; to 31 December 2025, giving the reason "The delay in obtaining the final Occupancy Certificate (OC) is primarily due to the pending completion of the clubhouse, which forms an essential amenity within the project. While the main residential buildings have been completed and are fit for occupation, we have already received the Occupancy Certificate for building on 24/05/2023, and a Part Occupancy Certificate for additional completed components all common amenities, including the clubhouse was subsequently granted on 24/06/2025. In view of the above and to ensure continued compliance with RERA requirements, we have applied for an e…".

What is the RERA number of ROYAL MEADOWS C 1 , C 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ROYAL MEADOWS C 1 , C 2 in Shahad, Thane is P51700008736.

Is ROYAL MEADOWS C 1 , C 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL MEADOWS C 1 , C 2 is registered as P51700008736 and its status is "Lapsed (registration period ended)".

What is the construction status of ROYAL MEADOWS C 1 , C 2?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL MEADOWS C 1 , C 2's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does ROYAL MEADOWS C 1 , C 2 have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ROYAL MEADOWS C 1 , C 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL MEADOWS C 1 , C 2 is registered on MahaRERA as P51700008736, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 63 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ROYAL MEADOWS C 1 , C 2's possession date changes?

The latest dates are on ROYAL MEADOWS C 1 , C 2's MahaRERA page (P51700008736). GharKundli's Kundli Watch sends a free WhatsApp update on ROYAL MEADOWS C 1 , C 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ROYAL MEADOWS C 1 , C 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL MEADOWS C 1 , C 2 has 2 buildings filed: C 1 - RIDDHI with 18 floors and 94 units; C - 2 SIDDHI with 18 floors and 94 units.

How much parking does ROYAL MEADOWS C 1 , C 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 76 covered car parking spaces for ROYAL MEADOWS C 1 , C 2.

How big is the land of ROYAL MEADOWS C 1 , C 2?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL MEADOWS C 1 , C 2 stands on 5,589 sq m of land (about 1.4 acres), with 4,553 sq m of sanctioned built-up area and 828 sq m of recreational open space.

Where can I read reviews of ROYAL MEADOWS C 1 , C 2?

Google Maps has reviews of ROYAL MEADOWS C 1 , C 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ROYAL MEADOWS C 1 , C 2?

ROYAL MEADOWS C 1 , C 2 by SIDDHIVINAYAK DEVELOPERS is in Shahad, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700008736, per GharKundli's check of MahaRERA records.

How many homes are in ROYAL MEADOWS C 1 , C 2?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL MEADOWS C 1 , C 2 has 188 homes in 2 towers registered on MahaRERA, and 95% of them are sold or booked.

When was ROYAL MEADOWS C 1 , C 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ROYAL MEADOWS C 1 , C 2 was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on ROYAL MEADOWS C 1 , C 2?

No court cases are listed for ROYAL MEADOWS C 1 , C 2 on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of ROYAL MEADOWS C 1 , C 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SIDDHIVINAYAK DEVELOPERS, which has 46 other projects registered on MahaRERA.