Tharwani Solitaire Phase IV
by ANIL HARDASMAL THARWANI · Shahad, Thane 421301
What’s in the report? →Possession date of Tharwani Solitaire Phase IV (MahaRERA P51700030172): 29 November 2026, moved from 31 July 2024 (24 months later). It has 208 homes, 41% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700030172, and currently active. Its completion date has moved from July 2024 to November 2026: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700030172, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Tharwani Solitaire Phase IV?
2 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Tharwani Solitaire Phase IV has moved
31 July 2024
Completion date given when the project was registered
30 July 2025
Extended at the builder's request (MahaRERA application EXT51700019730)
Reason the builder gave MahaRERA: “DELAY IN OBTAINING ENVIRONMENT CLEARANCES AND OTHER CLEARANCES RESULTING INTO ULTIMATE DELAY IN PROJECT EXECUTION”
29 July 2026
Extended at the builder's request (MahaRERA application EA16072502088)
Reason the builder gave MahaRERA:
“Due to undue delay in obtaining environmental clearances and other clearances for Wing I and Wing J i.e Spine! and Vivianite resulting into an overall delay in project execution and implementation. Further, we have received Occupancy certif…” Read the full reason
“Due to undue delay in obtaining environmental clearances and other clearances for Wing I and Wing J i.e Spine! and Vivianite resulting into an overall delay in project execution and implementation. Further, we have received Occupancy certificate for Wing H i.e. Topaz on 03° July, 2025 which we are enclosing for your reference.”29 November 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Tharwani Solitaire Phase IV’s extension records on MahaRERA (P51700030172), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Tharwani Solitaire Phase IV
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 court cases, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- THARWANI SOLITAIRE PHASE IP51700005630 · possession 30 Apr 2018
- THARWANI SOLITAIRE PHASE IIP51700004565 · possession 29 Oct 2020
- THARWANI SOLITAIRE PHASE IIIP51700005135 · possession 29 Sep 2022
- MahaRERA registration
- P51700030172
- Status
- Registered and active
- Builder
- ANIL HARDASMAL THARWANI
- Location
- Shahad, Thane · 421301
- Project type
- Residential / Group Housing
- Registered on
- 5 Aug 2021
- Completion date at registration
- July 2024
- Latest completion date
- November 2026
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 208
- Sold or booked
- 41%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 10
Construction progress of Tharwani Solitaire Phase IV, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TOPAZ | 100% | 100% | 100% | 100% |
| SPINEL | 100% | 100% | 75% | 0% |
| VIVIANITE | 100% | 100% | 95% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- TOPAZ: covers 15 floors
- SPINEL: covers 15 floors
- VIVIANITE: covers 15 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tharwani Solitaire Phase IV every 1–2 months.
Tharwani Solitaire Phase IV: buildings, flats and land, as filed on MahaRERA
- Buildings: TOPAZ (19 floors, 88 units) · SPINEL (19 floors, 60 units) · VIVIANITE (19 floors, 60 units)
- Land: 24,163 sq m (about 6.0 acres) · sanctioned built-up 24,163 sq m · recreational space 11,174 sq m
- Land, as filed: 8/1,8/2,12/1 -12/7, 13/1,13/2,14/1-14/4
- Map: Get directions
The builder’s record and reviews
Anil Hardasmal Tharwani has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 17 months); 2 still being built, 1 past the promised date (typically 17 months late); 2 lapsed. 10 complaints on MahaRERA across 3 projects.
Read Google reviews of Tharwani Solitaire Phase IV →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Tharwani Solitaire Phase IV: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Tharwani Solitaire Phase IV
What is the possession date of Tharwani Solitaire Phase IV?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tharwani Solitaire Phase IV in Shahad, Thane is 29 November 2026 — 24 months later than 31 July 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Tharwani Solitaire Phase IV?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Tharwani Solitaire Phase IV's builder has filed on MahaRERA, the official one, is 29 November 2026, already 24 months later than the 31 July 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Tharwani Solitaire Phase IV extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Tharwani Solitaire Phase IV's builder applied to MahaRERA to extend the completion date 2 times: to 30 July 2025, giving the reason "DELAY IN OBTAINING ENVIRONMENT CLEARANCES AND OTHER CLEARANCES RESULTING INTO ULTIMATE DELAY IN PROJECT EXECUTION"; to 29 July 2026, giving the reason "Due to undue delay in obtaining environmental clearances and other clearances for Wing I and Wing J i.e Spine! and Vivianite resulting into an overall delay in project execution and implementation. Further, we have received Occupancy certificate for Wing H i.e. Topaz on 03° July, 2025 which we are enclosing for your reference.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Tharwani Solitaire Phase IV?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tharwani Solitaire Phase IV in Shahad, Thane is P51700030172.
Is Tharwani Solitaire Phase IV registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tharwani Solitaire Phase IV is registered as P51700030172 and its status is "Registered and active".
What is the current construction status of Tharwani Solitaire Phase IV? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Tharwani Solitaire Phase IV's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Tharwani Solitaire Phase IV have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Tharwani Solitaire Phase IV safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Tharwani Solitaire Phase IV is registered on MahaRERA as P51700030172, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Tharwani Solitaire Phase IV?
Tharwani Solitaire Phase IV is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Tharwani Solitaire Phase IV?
For a flat in Tharwani Solitaire Phase IV (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Tharwani Solitaire Phase IV received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Tharwani Solitaire Phase IV is still under construction, with 29 November 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Tharwani Solitaire Phase IV uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Tharwani Solitaire Phase IV was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Tharwani Solitaire Phase IV have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: THARWANI SOLITAIRE PHASE I (P51700005630, possession 30 Apr 2018); THARWANI SOLITAIRE PHASE II (P51700004565, possession 29 Oct 2020); THARWANI SOLITAIRE PHASE III (P51700005135, possession 29 Sep 2022). Check that your agreement names the registration of your own wing.
How can I get updates if Tharwani Solitaire Phase IV's possession date changes?
The latest dates are on Tharwani Solitaire Phase IV's MahaRERA page (P51700030172). GharKundli's Kundli Watch sends a free WhatsApp update on Tharwani Solitaire Phase IV every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Tharwani Solitaire Phase IV have?
According to GharKundli's check of MahaRERA records (updated October 2026), Tharwani Solitaire Phase IV has 3 buildings filed: TOPAZ with 19 floors and 88 units; SPINEL with 19 floors and 60 units; VIVIANITE with 19 floors and 60 units.
How big is the land of Tharwani Solitaire Phase IV?
According to GharKundli's check of MahaRERA records (updated October 2026), Tharwani Solitaire Phase IV stands on 24,163 sq m of land (about 6.0 acres), with 24,163 sq m of sanctioned built-up area and 11,174 sq m of recreational open space.
What is the track record of Tharwani Solitaire Phase IV's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Anil Hardasmal Tharwani has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 17 months); 2 still being built, 1 past the promised date (typically 17 months late); 2 lapsed. 10 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Tharwani Solitaire Phase IV?
Google Maps has reviews of Tharwani Solitaire Phase IV written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Tharwani Solitaire Phase IV?
Tharwani Solitaire Phase IV by ANIL HARDASMAL THARWANI is in Shahad, Thane, pincode 421301, Maharashtra, and is registered on MahaRERA as P51700030172, per GharKundli's check of MahaRERA records. Its land is filed as 8/1,8/2,12/1 -12/7, 13/1,13/2,14/1-14/4. GharKundli lists all 582 MahaRERA projects in Kalyan (421301).
How many flats are in Tharwani Solitaire Phase IV, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Tharwani Solitaire Phase IV has 208 homes in 3 towers registered on MahaRERA, and 41% of them are sold or booked.
When was Tharwani Solitaire Phase IV registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tharwani Solitaire Phase IV was registered on MahaRERA on 5 August 2021. GharKundli did not find a title report on the land on file there.
Does Tharwani Solitaire Phase IV have any legal issues or court cases?
2 court cases are listed for Tharwani Solitaire Phase IV on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Tharwani Solitaire Phase IV?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ANIL HARDASMAL THARWANI, which has 10 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Tharwani Solitaire Phase IV
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Kalyan (421301)
All 582 projects in Kalyan (421301) →Other projects by ANIL HARDASMAL THARWANI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.