THARWANI SOLITAIRE PHASE III

by ANIL HARDASMAL THARWANI · Mharal Khurd, Thane

Possession date of THARWANI SOLITAIRE PHASE III: 29 September 2022, moved from 30 March 2021 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700005135. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (September 2022) has passed.

What do you want to know about THARWANI SOLITAIRE PHASE III?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of THARWANI SOLITAIRE PHASE III has moved

  1. 30 March 2021

    Completion date given when the project was registered

  2. 29 March 2022

    Extended at the builder's request (MahaRERA application EXT51700009293)

    Reason the builder gave MahaRERA:
    “In the Covid -19 ( Corona Virus) Pandemic Situation there has been consequent Nation wide lock down also there has been reverse migration of labourers to their native places which consequently resulted in short supply of laborers and also b…” Read the full reason“In the Covid -19 ( Corona Virus) Pandemic Situation there has been consequent Nation wide lock down also there has been reverse migration of labourers to their native places which consequently resulted in short supply of laborers and also break in supply chain of construction material hence the construction activity of the said project has been severally impacted Kindly consider this as the reason for delay which is not in our hand. Also, there was lack of sand supply for Tharwani Solitaire project for a period of more than 6 months for the period of March 2020 to August 2020.Further, we go…”
  3. 29 September 2022

    Revised completion date on MahaRERA

Source: THARWANI SOLITAIRE PHASE III’s extension records on MahaRERA (P51700005135), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on THARWANI SOLITAIRE PHASE III

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 2 court cases, and how it ended
  • Construction pace against the September 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700005135
Status
Lapsed (registration period ended)
Builder
ANIL HARDASMAL THARWANI
Location
Mharal Khurd, Thane · 421301
Project type
Others
Registered on
9 Aug 2017
Completion date at registration
March 2021
Latest completion date
September 2022
Delay so far
18 months
Homes
130
Towers
4
Complaints on MahaRERA
1
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
10

Construction progress of THARWANI SOLITAIRE PHASE III, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
HIDDENITE100%100%100%100%
OPAL100%100%100%80%
QUARTZ0%0%0%0%
RUBY0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on THARWANI SOLITAIRE PHASE III every month.

THARWANI SOLITAIRE PHASE III: buildings, flats and land, as filed on MahaRERA

  • Buildings: HIDDENITE (8 floors) · OPAL (9 floors) · QUARTZ (8 floors) · RUBY (8 floors)
  • Land: 14,250 sq m (about 3.5 acres) · sanctioned built-up 7,172 sq m · recreational space 11,113 sq m

The builder’s record and reviews

Anil Hardasmal Tharwani has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 17 months); 2 still being built, 1 past the promised date (typically 17 months late); 2 lapsed. 10 complaints on MahaRERA across 3 projects.

Read Google reviews of THARWANI SOLITAIRE PHASE III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

THARWANI SOLITAIRE PHASE III: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about THARWANI SOLITAIRE PHASE III

What is the possession date of THARWANI SOLITAIRE PHASE III?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for THARWANI SOLITAIRE PHASE III in Mharal Khurd, Thane is 29 September 2022 — 18 months later than 30 March 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for THARWANI SOLITAIRE PHASE III?

Builders and listing sites often quote an earlier "target" date for handover. The completion date THARWANI SOLITAIRE PHASE III's builder has filed on MahaRERA, the official one, is 29 September 2022, already 18 months later than the 30 March 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of THARWANI SOLITAIRE PHASE III extended?

According to GharKundli's check of MahaRERA records (updated November 2026), THARWANI SOLITAIRE PHASE III's builder applied to MahaRERA to extend the completion date once: to 29 March 2022, giving the reason "In the Covid -19 ( Corona Virus) Pandemic Situation there has been consequent Nation wide lock down also there has been reverse migration of labourers to their native places which consequently resulted in short supply of laborers and also break in supply chain of construction material hence the construction activity of the said project has been severally impacted Kindly consider this as the reason for delay which is not in our hand. Also, there was lack of sand supply for Tharwani Solitaire project for a period of more than 6 months for the period of March 2020 to August 2020.Further, we go…".

What is the RERA number of THARWANI SOLITAIRE PHASE III?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of THARWANI SOLITAIRE PHASE III in Mharal Khurd, Thane is P51700005135.

Is THARWANI SOLITAIRE PHASE III registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), THARWANI SOLITAIRE PHASE III is registered as P51700005135 and its status is "Lapsed (registration period ended)".

What is the construction status of THARWANI SOLITAIRE PHASE III?

According to GharKundli's check of MahaRERA records (updated November 2026), THARWANI SOLITAIRE PHASE III's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does THARWANI SOLITAIRE PHASE III have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is THARWANI SOLITAIRE PHASE III safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), THARWANI SOLITAIRE PHASE III is registered on MahaRERA as P51700005135, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does THARWANI SOLITAIRE PHASE III have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: THARWANI SOLITAIRE PHASE I (P51700005630, possession 30 Apr 2018); THARWANI SOLITAIRE PHASE II (P51700004565, possession 29 Oct 2020); THARWANI SOLITAIRE PHASE IV (P51700030172, possession 29 Nov 2026). Check that your agreement names the registration of your own wing.

How can I get updates if THARWANI SOLITAIRE PHASE III's possession date changes?

The latest dates are on THARWANI SOLITAIRE PHASE III's MahaRERA page (P51700005135). GharKundli's Kundli Watch sends a free WhatsApp update on THARWANI SOLITAIRE PHASE III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does THARWANI SOLITAIRE PHASE III have?

According to GharKundli's check of MahaRERA records (updated November 2026), THARWANI SOLITAIRE PHASE III has 4 buildings filed: HIDDENITE with 8 floors; OPAL with 9 floors; QUARTZ with 8 floors; RUBY with 8 floors.

How big is the land of THARWANI SOLITAIRE PHASE III?

According to GharKundli's check of MahaRERA records (updated November 2026), THARWANI SOLITAIRE PHASE III stands on 14,250 sq m of land (about 3.5 acres), with 7,172 sq m of sanctioned built-up area and 11,113 sq m of recreational open space.

What is the track record of THARWANI SOLITAIRE PHASE III's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Anil Hardasmal Tharwani has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 17 months); 2 still being built, 1 past the promised date (typically 17 months late); 2 lapsed. 10 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of THARWANI SOLITAIRE PHASE III?

Google Maps has reviews of THARWANI SOLITAIRE PHASE III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is THARWANI SOLITAIRE PHASE III?

THARWANI SOLITAIRE PHASE III by ANIL HARDASMAL THARWANI is in Mharal Khurd, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700005135, per GharKundli's check of MahaRERA records.

How many homes are in THARWANI SOLITAIRE PHASE III?

According to GharKundli's check of MahaRERA records (updated November 2026), THARWANI SOLITAIRE PHASE III has 130 homes in 4 towers registered on MahaRERA.

When was THARWANI SOLITAIRE PHASE III registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), THARWANI SOLITAIRE PHASE III was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on THARWANI SOLITAIRE PHASE III?

2 court cases are listed for THARWANI SOLITAIRE PHASE III on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of THARWANI SOLITAIRE PHASE III?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ANIL HARDASMAL THARWANI, which has 10 other projects registered on MahaRERA.