SAI NIRVANA
by Shanklesha Constructions · Shahad, Thane
Possession: SAI NIRVANA is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700003913. Status: Completed. MahaRERA has issued a regulatory order on this project. 8 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SAI NIRVANA?
How the possession date of SAI NIRVANA has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51700003829)
Reason the builder gave MahaRERA:
“The Project commenced under MMRDA Rental Housing Scheme whereby developers were offered additional FSI in return for providing tenements of 160 sq. ft. carpet area to MMRDA free of cost. The FSI of the free sale area is released in proporti…” Read the full reason
“The Project commenced under MMRDA Rental Housing Scheme whereby developers were offered additional FSI in return for providing tenements of 160 sq. ft. carpet area to MMRDA free of cost. The FSI of the free sale area is released in proportion to the construction of the rental housing units. In November 2016, demonetisation policy was announced which impacted the project. Material supply became irregular and unreliable. Labors rushed to their home town in panic resulting in almost complete halt of work at site. Due to the overall economic situation customers were avoiding making large purcha…”31 March 2024
Extended at the builder's request (MahaRERA application EXT51700015210)
Reason the builder gave MahaRERA:
“1) We have obtained the RERA registration number on 06/08/2017. 2) We are law abiding firm. We have voluntarily applied for RERA and got the RERA number. 3) The project is completed. 4) In COVID-19 pandemic, we handed over the building to t…” Read the full reason
“1) We have obtained the RERA registration number on 06/08/2017. 2) We are law abiding firm. We have voluntarily applied for RERA and got the RERA number. 3) The project is completed. 4) In COVID-19 pandemic, we handed over the building to the government for treatment of patients suffering from COVID-19. 5) We have not sold/booked the units to any customers. 6) We have already applied for an occupation certificate from local authority and the same is awaited. 7) Since the occupancy certificate from local authority is awaited, we are forced to take an extension of the project till 31/03/2024”
Source: SAI NIRVANA’s extension records on MahaRERA (P51700003913), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI NIRVANA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 8 complaints, and how it ended
- Construction pace against the March 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700003913
- Status
- Completed
- Builder
- Shanklesha Constructions
- Location
- Shahad, Thane · 421301
- Project type
- Others
- Registered on
- 6 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- March 2024
- Delay so far
- 51 months
- Homes
- 780
- Towers
- 3
- Complaints on MahaRERA
- 8
- Court cases listed
- 0
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of SAI NIRVANA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building 1 MMRDA Rental | 100% | 100% | 100% | 100% |
| BUILDING 2 | 100% | 100% | 100% | 100% |
| BUILDING 3 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI NIRVANA every month.
SAI NIRVANA: buildings, flats and land, as filed on MahaRERA
- Buildings: Building 1 MMRDA Rental (24 floors) · BUILDING 2 (37 floors) · BUILDING 3 (37 floors)
- Land: 9,722 sq m (about 2.4 acres) · sanctioned built-up 24,587 sq m · recreational space 929 sq m
- Boundaries filed include: Kalyan Murbad Road
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAI NIRVANA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI NIRVANA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI NIRVANA
What is the possession date of SAI NIRVANA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI NIRVANA in Shahad, Thane is 31 March 2024 — 51 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SAI NIRVANA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI NIRVANA's builder has filed on MahaRERA, the official one, is 31 March 2024, already 51 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAI NIRVANA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI NIRVANA's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "The Project commenced under MMRDA Rental Housing Scheme whereby developers were offered additional FSI in return for providing tenements of 160 sq. ft. carpet area to MMRDA free of cost. The FSI of the free sale area is released in proportion to the construction of the rental housing units. In November 2016, demonetisation policy was announced which impacted the project. Material supply became irregular and unreliable. Labors rushed to their home town in panic resulting in almost complete halt of work at site. Due to the overall economic situation customers were avoiding making large purcha…"; to 31 March 2024, giving the reason "1) We have obtained the RERA registration number on 06/08/2017. 2) We are law abiding firm. We have voluntarily applied for RERA and got the RERA number. 3) The project is completed. 4) In COVID-19 pandemic, we handed over the building to the government for treatment of patients suffering from COVID-19. 5) We have not sold/booked the units to any customers. 6) We have already applied for an occupation certificate from local authority and the same is awaited. 7) Since the occupancy certificate from local authority is awaited, we are forced to take an extension of the project till 31/03/2024".
What is the RERA number of SAI NIRVANA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI NIRVANA in Shahad, Thane is P51700003913.
Is SAI NIRVANA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI NIRVANA is registered as P51700003913 and its status is "Completed".
What is the construction status of SAI NIRVANA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI NIRVANA's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does SAI NIRVANA have complaints on MahaRERA?
8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAI NIRVANA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI NIRVANA is registered on MahaRERA as P51700003913, its MahaRERA status is "Completed", its completion date has moved 51 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI NIRVANA's possession date changes?
The latest dates are on SAI NIRVANA's MahaRERA page (P51700003913). GharKundli's Kundli Watch sends a free WhatsApp update on SAI NIRVANA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI NIRVANA have?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI NIRVANA has 3 buildings filed: Building 1 MMRDA Rental with 24 floors; BUILDING 2 with 37 floors; BUILDING 3 with 37 floors.
How big is the land of SAI NIRVANA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI NIRVANA stands on 9,722 sq m of land (about 2.4 acres), with 24,587 sq m of sanctioned built-up area and 929 sq m of recreational open space.
Where can I read reviews of SAI NIRVANA?
Google Maps has reviews of SAI NIRVANA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI NIRVANA?
SAI NIRVANA by Shanklesha Constructions is in Shahad, Thane (pincode 421301), Maharashtra, and is registered on MahaRERA as P51700003913, per GharKundli's check of MahaRERA records. Its boundaries filed there include Kalyan Murbad Road.
How many homes are in SAI NIRVANA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI NIRVANA has 780 homes in 3 towers registered on MahaRERA.
When was SAI NIRVANA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI NIRVANA was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI NIRVANA?
No court cases are listed for SAI NIRVANA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SAI NIRVANA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shanklesha Constructions.
Check it yourself on MahaRERA
- How to check the possession date of SAI NIRVANA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Shahad
All 582 projects in Kalyan (421301) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.