TOWER 28

by Shiv Shakti Builders And Developers · Malad East, MumbaiAlso near Malad West, Goregaon East, Goregaon West

Possession date of TOWER 28: 30 October 2026, moved from 30 June 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800009511, and currently active. Its completion date has moved from June 2022 to October 2026: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 52 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about TOWER 28?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of TOWER 28 has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51800012120)

    Reason the builder gave MahaRERA:
    “With regard to the captioned subject, we would like to state that proposed date for completion of our project Tower 28 MahaRERA registration no. P51800009511 (4 buildings A, B, D and E - all comprising of 2 basements + ground + 2 Podiums +…” Read the full reason“With regard to the captioned subject, we would like to state that proposed date for completion of our project Tower 28 MahaRERA registration no. P51800009511 (4 buildings A, B, D and E - all comprising of 2 basements + ground + 2 Podiums + 21 habitable floors) is 30th June, 2022. Due to multiple waves of Covid-19, the construction work of the project was disbursed significantly. Public offices were also closed or working on lower capacity and therefore, various approvals from the multiple departments could not be obtained timely. Due to this unfortunate and unforeseen situation, our constru…”
  3. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51800017175)

    Reason the builder gave MahaRERA:
    “We have completed entire RCC structure & finishing work of buildings A and B of the project and Occupancy certificate from the concerned authorities has also been obtained on 13th May, 2023. We have also completed the entire RCC structure w…” Read the full reason“We have completed entire RCC structure & finishing work of buildings A and B of the project and Occupancy certificate from the concerned authorities has also been obtained on 13th May, 2023. We have also completed the entire RCC structure work & finishing work of building E of the project and application for the issuance of Occupancy Certificate has been made before the authorities. Copy of the Occupancy Certificate for building A & B and application for issuance of Occupancy Certificates for building E are enclosed herewith for your ready reference. Due to some unfortunate and unforeseen s…”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800024076)

    Reason the builder gave MahaRERA: “Due to administrative delay in obtaining further commencement certificate the building D is running little bit delay.”
  5. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800025761)

    Reason the builder gave MahaRERA: “There was an Incident on site on 05th September, 2024 in which 3 labour was died due to this stop work notice has been issued for whole site from SRA Department as well as from Labour Department.”
  6. 30 June 2026

    Extended at the builder's request (MahaRERA application EA07012619344)

    Reason the builder gave MahaRERA:
    “We have tried our level best to complete the finishing work by June and it was almost done too. Then we have applied for occupancy certificate of this wing. Since this wing was the last wing of the said Phase so the OC related compliance we…” Read the full reason“We have tried our level best to complete the finishing work by June and it was almost done too. Then we have applied for occupancy certificate of this wing. Since this wing was the last wing of the said Phase so the OC related compliance were little more and we had to procure multiple NOC’s for the whole project before we got the final OC of D wing. Before filing the extension application, we had to update the data on the new RERA portal for the whole project that too for the last 7-8 years and the portal was new to understand so it took more time than the normal course. We have even obtain…”
  7. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: TOWER 28’s extension records on MahaRERA (P51800009511), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TOWER 28

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 52 complaints, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009511
Status
Registered and active
Builder
Shiv Shakti Builders And Developers
Location
Malad East, Mumbai · 400097
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
June 2022
Latest completion date
October 2026
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
321
Sold or booked
98%
Towers
7
Complaints on MahaRERA
52
Court cases listed
0
Appeals at the tribunal
11
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of TOWER 28, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A Wing100%100%100%100%
B Wing100%100%100%100%
D Wing100%85%70%0%
E Wing100%100%100%100%
G WING REFERRED IN 2ND PHASE0%0%0%0%
F WING REFERRED IN II PHASE0%0%0%0%
C Wing REFERRED IN II PHASE0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • A Wing: covers 21 floors
  • B Wing: covers 21 floors
  • D Wing: covers 21 floors
  • E Wing: covers 21 floors
  • G WING REFERRED IN 2ND PHASE: covers 0 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TOWER 28 every month.

TOWER 28: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Unspecified—594
2 BHK436 – 619185
1 BHK443 – 619136
  • Buildings: A Wing (25 floors, 80 units) · B Wing (25 floors, 80 units) · D Wing (25 floors, 81 units) · E Wing (25 floors, 80 units)
  • Car parking: 202 covered
  • Land: 11,210 sq m (about 2.8 acres) · sanctioned built-up 24,567 sq m · recreational space 819 sq m
  • Boundaries filed include: Haji Bapu Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Shiv Shakti Builders And Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 21 months late). 56 complaints on MahaRERA across 2 projects.

Read Google reviews of TOWER 28 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TOWER 28: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TOWER 28

What is the possession date of TOWER 28?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TOWER 28 in Malad East, Mumbai is 30 October 2026 — 48 months later than 30 June 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for TOWER 28?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TOWER 28's builder has filed on MahaRERA, the official one, is 30 October 2026, already 48 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TOWER 28 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), TOWER 28's builder applied to MahaRERA to extend the completion date 5 times: to 30 June 2023, giving the reason "With regard to the captioned subject, we would like to state that proposed date for completion of our project Tower 28 MahaRERA registration no. P51800009511 (4 buildings A, B, D and E - all comprising of 2 basements + ground + 2 Podiums + 21 habitable floors) is 30th June, 2022. Due to multiple waves of Covid-19, the construction work of the project was disbursed significantly. Public offices were also closed or working on lower capacity and therefore, various approvals from the multiple departments could not be obtained timely. Due to this unfortunate and unforeseen situation, our constru…"; to 30 June 2024, giving the reason "We have completed entire RCC structure & finishing work of buildings A and B of the project and Occupancy certificate from the concerned authorities has also been obtained on 13th May, 2023. We have also completed the entire RCC structure work & finishing work of building E of the project and application for the issuance of Occupancy Certificate has been made before the authorities. Copy of the Occupancy Certificate for building A & B and application for issuance of Occupancy Certificates for building E are enclosed herewith for your ready reference. Due to some unfortunate and unforeseen s…"; to 31 December 2024, giving the reason "Due to administrative delay in obtaining further commencement certificate the building D is running little bit delay."; to 30 June 2025, giving the reason "There was an Incident on site on 05th September, 2024 in which 3 labour was died due to this stop work notice has been issued for whole site from SRA Department as well as from Labour Department."; to 30 June 2026, giving the reason "We have tried our level best to complete the finishing work by June and it was almost done too. Then we have applied for occupancy certificate of this wing. Since this wing was the last wing of the said Phase so the OC related compliance were little more and we had to procure multiple NOC’s for the whole project before we got the final OC of D wing. Before filing the extension application, we had to update the data on the new RERA portal for the whole project that too for the last 7-8 years and the portal was new to understand so it took more time than the normal course. We have even obtain…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of TOWER 28?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TOWER 28 in Malad East, Mumbai is P51800009511.

Is TOWER 28 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TOWER 28 is registered as P51800009511 and its status is "Registered and active".

What is the construction status of TOWER 28?

According to GharKundli's check of MahaRERA records (updated October 2026), TOWER 28's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 7 towers. GharKundli's full report compares construction progress with the deadline.

Does TOWER 28 have complaints on MahaRERA?

52 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is TOWER 28 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), TOWER 28 is registered on MahaRERA as P51800009511, its completion date has moved 48 months since registration and 52 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if TOWER 28's possession date changes?

The latest dates are on TOWER 28's MahaRERA page (P51800009511). GharKundli's Kundli Watch sends a free WhatsApp update on TOWER 28 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TOWER 28 have?

According to GharKundli's check of MahaRERA records (updated October 2026), TOWER 28 has 4 buildings filed: A Wing with 25 floors and 80 units; B Wing with 25 floors and 80 units; D Wing with 25 floors and 81 units; E Wing with 25 floors and 80 units.

What are the flat sizes (carpet area) in TOWER 28?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for TOWER 28: 2 BHK: 436 to 619 sq ft carpet (185 homes); 1 BHK: 443 to 619 sq ft carpet (136 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does TOWER 28 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 202 covered car parking spaces for TOWER 28.

How big is the land of TOWER 28?

According to GharKundli's check of MahaRERA records (updated October 2026), TOWER 28 stands on 11,210 sq m of land (about 2.8 acres), with 24,567 sq m of sanctioned built-up area and 819 sq m of recreational open space.

What is the track record of TOWER 28's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Shakti Builders And Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 21 months late). 56 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of TOWER 28?

Google Maps has reviews of TOWER 28 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 52 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TOWER 28?

TOWER 28 by Shiv Shakti Builders And Developers is in Malad East, Mumbai (pincode 400097), near Malad West, Goregaon East, Goregaon West, Maharashtra, and is registered on MahaRERA as P51800009511, per GharKundli's check of MahaRERA records. Its boundaries filed there include Haji Bapu Road.

How many homes are in TOWER 28?

According to GharKundli's check of MahaRERA records (updated October 2026), TOWER 28 has 321 homes in 7 towers registered on MahaRERA, and 98% of them are sold or booked.

When was TOWER 28 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TOWER 28 was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on TOWER 28?

No court cases are listed for TOWER 28 on MahaRERA, and 11 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of TOWER 28?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shiv Shakti Builders And Developers, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400097

All 195 projects in Malad East (400097) →

Other projects by Shiv Shakti Builders And Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.