Tower 28 - C and F
by Shiv Shakti Builders And Developers · Malad East, MumbaiAlso near Malad West Dely, Motilal Nagar
Possession date of Tower 28 - C and F: 30 April 2028, moved from 30 June 2025 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800028777, and currently active. Its completion date has moved from June 2025 to April 2028: 30 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Tower 28 - C and F?
How the possession date of Tower 28 - C and F has moved
30 June 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EXT51800011799)
Reason the builder gave MahaRERA:
“We would like to state that proposed date for completion of our project Tower 28 - C and F (comprising of 2 basements + ground + 2 Podiums + 42 habitable floors) initially was 31st December, 2024 which later vide MahaRERA order no.: 21/2021…” Read the full reason
“We would like to state that proposed date for completion of our project Tower 28 - C and F (comprising of 2 basements + ground + 2 Podiums + 42 habitable floors) initially was 31st December, 2024 which later vide MahaRERA order no.: 21/2021 dated 06th August, 2021 extended for 6 months by invoking force majeure for Covid-19 Pandemic second wave for a period of extension of project w.e.f. 15th April, 2021 to 14th September, 2021 resulting into the new proposed date of completion to be 30th June, 2025. The project was registered under MahaRERA vide registration no. P51800028777 dated 30th Mar…”31 December 2027
Extended at the builder's request (MahaRERA application EXT51800019800)
Reason the builder gave MahaRERA: “Due the complex structure of the buildings in project being high rise project and the current construction status, it appears that the completion of the project will take more time than what was expected initially.”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Tower 28 - C and F’s extension records on MahaRERA (P51800028777), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Tower 28 - C and F
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800028777
- Status
- Registered and active
- Builder
- Shiv Shakti Builders And Developers
- Location
- Malad East, Mumbai · 400097
- Project type
- Residential / Group Housing
- Registered on
- 30 Mar 2021
- Completion date at registration
- June 2025
- Latest completion date
- April 2028
- Delay so far
- 30 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 383
- Sold or booked
- 46%
- Towers
- 2
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Tower 28 - C and F, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| C Wing | 100% | 0% | 0% | 0% |
| F Wing | 100% | 95% | 79% | 25% |
Commencement certificate (CC), as filed on MahaRERA
- C Wing: covers 37 floors
- F Wing: covers 37 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Tower 28 - C and F every month.
Tower 28 - C and F: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 602 – 691 | 315 |
| 3 BHK | 846 – 897 | 58 |
| Duplex | 1,022 – 1,310 | 10 |
- Buildings: C Wing (46 floors, 171 units) · F Wing (46 floors, 212 units)
- Land: 11,211 sq m (about 2.8 acres) · sanctioned built-up 15,433 sq m
- Boundaries filed include: Haji Bapu Road, Railway Track
The builder’s record and reviews
Shiv Shakti Builders And Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 21 months late). 56 complaints on MahaRERA across 2 projects.
Read Google reviews of Tower 28 - C and F →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Tower 28 - C and F: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Tower 28 - C and F
What is the possession date of Tower 28 - C and F?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Tower 28 - C and F in Malad East, Mumbai is 30 April 2028 — 30 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Tower 28 - C and F?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Tower 28 - C and F's builder has filed on MahaRERA, the official one, is 30 April 2028, already 30 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Tower 28 - C and F extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Tower 28 - C and F's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2026, giving the reason "We would like to state that proposed date for completion of our project Tower 28 - C and F (comprising of 2 basements + ground + 2 Podiums + 42 habitable floors) initially was 31st December, 2024 which later vide MahaRERA order no.: 21/2021 dated 06th August, 2021 extended for 6 months by invoking force majeure for Covid-19 Pandemic second wave for a period of extension of project w.e.f. 15th April, 2021 to 14th September, 2021 resulting into the new proposed date of completion to be 30th June, 2025. The project was registered under MahaRERA vide registration no. P51800028777 dated 30th Mar…"; to 31 December 2027, giving the reason "Due the complex structure of the buildings in project being high rise project and the current construction status, it appears that the completion of the project will take more time than what was expected initially.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Tower 28 - C and F?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Tower 28 - C and F in Malad East, Mumbai is P51800028777.
Is Tower 28 - C and F registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tower 28 - C and F is registered as P51800028777 and its status is "Registered and active".
What is the construction status of Tower 28 - C and F?
According to GharKundli's check of MahaRERA records (updated October 2026), Tower 28 - C and F's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 95% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Tower 28 - C and F have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Tower 28 - C and F safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Tower 28 - C and F is registered on MahaRERA as P51800028777, its completion date has moved 30 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Tower 28 - C and F's possession date changes?
The latest dates are on Tower 28 - C and F's MahaRERA page (P51800028777). GharKundli's Kundli Watch sends a free WhatsApp update on Tower 28 - C and F every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Tower 28 - C and F have?
According to GharKundli's check of MahaRERA records (updated October 2026), Tower 28 - C and F has 2 buildings filed: C Wing with 46 floors and 171 units; F Wing with 46 floors and 212 units.
What are the flat sizes (carpet area) in Tower 28 - C and F?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Tower 28 - C and F: 2 BHK: 602 to 691 sq ft carpet (315 homes); 3 BHK: 846 to 897 sq ft carpet (58 homes); Duplex: 1022 to 1310 sq ft carpet (10 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Tower 28 - C and F?
According to GharKundli's check of MahaRERA records (updated October 2026), Tower 28 - C and F stands on 11,211 sq m of land (about 2.8 acres), with 15,433 sq m of sanctioned built-up area.
What is the track record of Tower 28 - C and F's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shiv Shakti Builders And Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 21 months late). 56 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Tower 28 - C and F?
Google Maps has reviews of Tower 28 - C and F written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Tower 28 - C and F?
Tower 28 - C and F by Shiv Shakti Builders And Developers is in Malad East, Mumbai (pincode 400097), near Malad West Dely, Motilal Nagar, Maharashtra, and is registered on MahaRERA as P51800028777, per GharKundli's check of MahaRERA records. Its boundaries filed there include Haji Bapu Road, Railway Track.
How many homes are in Tower 28 - C and F?
According to GharKundli's check of MahaRERA records (updated October 2026), Tower 28 - C and F has 383 homes in 2 towers registered on MahaRERA, and 46% of them are sold or booked.
When was Tower 28 - C and F registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Tower 28 - C and F was registered on MahaRERA on 30 March 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Tower 28 - C and F?
No court cases are listed for Tower 28 - C and F on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Tower 28 - C and F?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shiv Shakti Builders And Developers, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Tower 28 - C and F
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400097
- Upper East 97
- Vardhan Royale
- Aarambh Phase III by group Satellite
- Nivetia Heights
- Pearl Solitaire
- L&T Realty Ahana Tower A
- L&T Realty Ahana Tower B
- NAMO WHISPERING BLISS
Other projects by Shiv Shakti Builders And Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.