AKSHAY PARADISE

by DINESH S CHANDNANI · Tilak Nagar, MumbaiAlso near Chembur, Ghatkopar East, Ghatkopar West

Possession date of AKSHAY PARADISE: 31 December 2025, moved from 1 June 2021 (54 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800004753. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about AKSHAY PARADISE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AKSHAY PARADISE has moved

  1. 1 June 2021

    Completion date given when the project was registered

  2. 1 June 2022

    Extended at the builder's request (MahaRERA application EXT51800009933)

    Reason the builder gave MahaRERA:
    “This is with reference to above referred subject, requesting to you kindly grant us extension of the project for the period of one (01) year ending 18th June 2022, since the Project has suffered badly due to pandemic, which has caused unava…” Read the full reason“This is with reference to above referred subject, requesting to you kindly grant us extension of the project for the period of one (01) year ending 18th June 2022, since the Project has suffered badly due to pandemic, which has caused unavailability of labours, and also delay in further approval due to continuous lock down.”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800013619)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 58.11% allottees for purpose of extension of RERA registration period of the said project.”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800027227)

    Reason the builder gave MahaRERA:
    “I, Dinesh S Chandnani, the promoter of the project AKSHAY PARADISE (Registration No. P51800004753) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the delay in the compl…” Read the full reason“I, Dinesh S Chandnani, the promoter of the project AKSHAY PARADISE (Registration No. P51800004753) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all…”

Source: AKSHAY PARADISE’s extension records on MahaRERA (P51800004753), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AKSHAY PARADISE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800004753
Status
Lapsed (registration period ended)
Builder
DINESH S CHANDNANI
Location
Tilak Nagar, Mumbai · 400089
Project type
Mixed
Registered on
9 Aug 2017
Completion date at registration
June 2021
Latest completion date
December 2025
Delay so far
54 months
Homes
102
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of AKSHAY PARADISE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AKSHAY PARADISE100%70%40%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AKSHAY PARADISE every month.

AKSHAY PARADISE: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of AKSHAY PARADISE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AKSHAY PARADISE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AKSHAY PARADISE

What is the possession date of AKSHAY PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AKSHAY PARADISE in Tilak Nagar, Mumbai is 31 December 2025 — 54 months later than 1 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for AKSHAY PARADISE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AKSHAY PARADISE's builder has filed on MahaRERA, the official one, is 31 December 2025, already 54 months later than the 1 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AKSHAY PARADISE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY PARADISE's builder applied to MahaRERA to extend the completion date 3 times: to 1 June 2022, giving the reason "This is with reference to above referred subject, requesting to you kindly grant us extension of the project for the period of one (01) year ending 18th June 2022, since the Project has suffered badly due to pandemic, which has caused unavailability of labours, and also delay in further approval due to continuous lock down."; to 31 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 58.11% allottees for purpose of extension of RERA registration period of the said project."; to 31 December 2025, giving the reason "I, Dinesh S Chandnani, the promoter of the project AKSHAY PARADISE (Registration No. P51800004753) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all…".

What is the RERA number of AKSHAY PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AKSHAY PARADISE in Tilak Nagar, Mumbai is P51800004753.

Is AKSHAY PARADISE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY PARADISE is registered as P51800004753 and its status is "Lapsed (registration period ended)".

What is the construction status of AKSHAY PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY PARADISE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on AKSHAY PARADISE is 70% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.

Does AKSHAY PARADISE have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AKSHAY PARADISE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY PARADISE is registered on MahaRERA as P51800004753, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AKSHAY PARADISE's possession date changes?

The latest dates are on AKSHAY PARADISE's MahaRERA page (P51800004753). GharKundli's Kundli Watch sends a free WhatsApp update on AKSHAY PARADISE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AKSHAY PARADISE have?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY PARADISE has one building filed: AKSHAY PARADISE with 16 floors.

How big is the land of AKSHAY PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY PARADISE stands on 1,766 sq m of land (about 0.4 acres), with 5,921 sq m of sanctioned built-up area and 183 sq m of recreational open space.

Where can I read reviews of AKSHAY PARADISE?

Google Maps has reviews of AKSHAY PARADISE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AKSHAY PARADISE?

AKSHAY PARADISE by DINESH S CHANDNANI is in Tilak Nagar, Mumbai (pincode 400089), near Chembur, Ghatkopar East, Ghatkopar West, Maharashtra, and is registered on MahaRERA as P51800004753, per GharKundli's check of MahaRERA records.

How many homes are in AKSHAY PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY PARADISE has 102 homes in 1 tower registered on MahaRERA.

When was AKSHAY PARADISE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSHAY PARADISE was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on AKSHAY PARADISE?

No court cases are listed for AKSHAY PARADISE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of AKSHAY PARADISE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DINESH S CHANDNANI.

Other projects in pincode 400089

All 75 projects in Chembur (400089) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.