Possession date of ADHRIT: 30 April 2027, moved from 30 October 2023 (38 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800009600, and currently active. Its completion date has moved from October 2023 to April 2027: 38 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 6 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ADHRIT?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ADHRIT has moved

  1. 30 October 2023

    Completion date given when the project was registered

  2. 29 October 2024

    Extended at the builder's request (MahaRERA application EXT51800017742)

    Reason the builder gave MahaRERA:
    “Due to Covid 19, entire cash flow has been affected resulting in delay in construction activities. We seek extension u/s 6 of the Act to complete the project with extended timeline. We assure you that we shall complete the construction in e…” Read the full reason“Due to Covid 19, entire cash flow has been affected resulting in delay in construction activities. We seek extension u/s 6 of the Act to complete the project with extended timeline. We assure you that we shall complete the construction in extended timeline and hence request your good selves to kindly grant us extension looking at various force majure conditions and factors beyond our control.”
  3. 31 July 2025

    Extended at the builder's request (MahaRERA application EXT51800024860)

    Reason the builder gave MahaRERA:
    “The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, cau…” Read the full reason“The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 31-07-2025. We hereby submit this application seeking an extension of the project under section 7 (3) of Maharera.”
  4. 31 March 2026

    Extended at the builder's request (MahaRERA application EA30062501865)

    Reason the builder gave MahaRERA:
    “a. Outbreak of Covid – 19 , b. Old Promoter Liability : The initial Development Agreement dated 22.04.2003 with M/s. Bahubali Developers was terminated due to non- performance. This led to disputes requiring resolution through Arbitration a…” Read the full reason“a. Outbreak of Covid – 19 , b. Old Promoter Liability : The initial Development Agreement dated 22.04.2003 with M/s. Bahubali Developers was terminated due to non- performance. This led to disputes requiring resolution through Arbitration and the legal proceedings. The said Arbitration proceedings are in the last phase of hearing before the H’ble Arbitrator appointed by the H’ble High court and the last date of Arbitration proceeding to be completed is 31.08.2024. This also gave a financial stress to the project as we had to spend all the money for the project towards Statutory Payments, Ar…”
  5. 31 December 2026

    Extended at the builder's request (MahaRERA application EA26032620388)

    Reason the builder gave MahaRERA:
    “The progress of the project was significantly impacted by a series of unforeseen challenges, primarily arising from the COVID-19 pandemic and its aftermath. Between March 2020 and February 2022, construction activities were severely disrupt…” Read the full reason“The progress of the project was significantly impacted by a series of unforeseen challenges, primarily arising from the COVID-19 pandemic and its aftermath. Between March 2020 and February 2022, construction activities were severely disrupted due to nationwide lockdowns, movement restrictions, and mandatory safety measures. These conditions led to acute shortages of skilled and unskilled labour, disruptions in the supply chain for essential materials and equipment, and prolonged periods of inactivity on site. Despite these obstacles, the developer made continuous efforts to sustain limited…”
  6. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ADHRIT’s extension records on MahaRERA (P51800009600), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ADHRIT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 6 complaints and 24 court cases, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800009600
Status
Registered and active
Builder
MUNDARA DEVELOPERS
Location
Malad, Mumbai · 400064
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
October 2023
Latest completion date
April 2027
Delay so far
38 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
468
Sold or booked
73%
Towers
5
Complaints on MahaRERA
6
Court cases listed
24
Appeals at the tribunal
3
Title report on file
Not found

Construction progress of ADHRIT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PUSHPAK 1 REHAB100%100%100%100%
PUSHPAK 2 REHAB100%100%100%100%
PUSHAPAK 3 REHAB100%100%100%100%
ADHRIT100%100%90%75%
REHAB / COMPOSITE BUILDING NO 5100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • PUSHPAK 1 REHAB: covers 8 floors
  • PUSHPAK 2 REHAB: covers 8 floors
  • PUSHAPAK 3 REHAB: covers 8 floors
  • ADHRIT: covers 51 floors
  • REHAB / COMPOSITE BUILDING NO 5: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ADHRIT every month.

ADHRIT: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 Room Kitchen225207
2 BHK8,567 – 51,606132
1 BHK30064
3 BHK10,889 – 11,68459
Other2,298 – 26,4159
Hall2,2981
  • Buildings: PUSHPAK 1 REHAB (8 floors, 64 units) · PUSHPAK 2 REHAB (8 floors, 79 units) · PUSHAPAK 3 REHAB (8 floors, 64 units) · ADHRIT (51 floors, 201 units) · REHAB / COMPOSITE BUILDING NO 5 (9 floors, 64 units)
  • Car parking: 287 covered
  • Land: 7,511 sq m (about 1.9 acres) · sanctioned built-up 25,228 sq m · recreational space 1,296 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of ADHRIT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ADHRIT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ADHRIT

What is the possession date of ADHRIT?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ADHRIT in Malad, Mumbai is 30 April 2027 — 38 months later than 30 October 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ADHRIT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ADHRIT's builder has filed on MahaRERA, the official one, is 30 April 2027, already 38 months later than the 30 October 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ADHRIT extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ADHRIT's builder applied to MahaRERA to extend the completion date 4 times: to 29 October 2024, giving the reason "Due to Covid 19, entire cash flow has been affected resulting in delay in construction activities. We seek extension u/s 6 of the Act to complete the project with extended timeline. We assure you that we shall complete the construction in extended timeline and hence request your good selves to kindly grant us extension looking at various force majure conditions and factors beyond our control."; to 31 July 2025, giving the reason "The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labor and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However we are trying to complete the project at the earliest. Kindly process our application and grant us the extension till 31-07-2025. We hereby submit this application seeking an extension of the project under section 7 (3) of Maharera."; to 31 March 2026, giving the reason "a. Outbreak of Covid – 19 , b. Old Promoter Liability : The initial Development Agreement dated 22.04.2003 with M/s. Bahubali Developers was terminated due to non- performance. This led to disputes requiring resolution through Arbitration and the legal proceedings. The said Arbitration proceedings are in the last phase of hearing before the H’ble Arbitrator appointed by the H’ble High court and the last date of Arbitration proceeding to be completed is 31.08.2024. This also gave a financial stress to the project as we had to spend all the money for the project towards Statutory Payments, Ar…"; to 31 December 2026, giving the reason "The progress of the project was significantly impacted by a series of unforeseen challenges, primarily arising from the COVID-19 pandemic and its aftermath. Between March 2020 and February 2022, construction activities were severely disrupted due to nationwide lockdowns, movement restrictions, and mandatory safety measures. These conditions led to acute shortages of skilled and unskilled labour, disruptions in the supply chain for essential materials and equipment, and prolonged periods of inactivity on site. Despite these obstacles, the developer made continuous efforts to sustain limited…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of ADHRIT?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ADHRIT in Malad, Mumbai is P51800009600.

Is ADHRIT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ADHRIT is registered as P51800009600 and its status is "Registered and active".

What is the construction status of ADHRIT?

According to GharKundli's check of MahaRERA records (updated October 2026), ADHRIT's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.

Does ADHRIT have complaints on MahaRERA?

6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ADHRIT safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ADHRIT is registered on MahaRERA as P51800009600, its completion date has moved 38 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ADHRIT's possession date changes?

The latest dates are on ADHRIT's MahaRERA page (P51800009600). GharKundli's Kundli Watch sends a free WhatsApp update on ADHRIT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ADHRIT have?

According to GharKundli's check of MahaRERA records (updated October 2026), ADHRIT has 5 buildings filed: PUSHPAK 1 REHAB with 8 floors and 64 units; PUSHPAK 2 REHAB with 8 floors and 79 units; PUSHAPAK 3 REHAB with 8 floors and 64 units; ADHRIT with 51 floors and 201 units; REHAB / COMPOSITE BUILDING NO 5 with 9 floors and 64 units.

What are the flat sizes (carpet area) in ADHRIT?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for ADHRIT: 1 Room Kitchen: 225 sq ft carpet (207 homes); 2 BHK: 8567 to 51606 sq ft carpet (132 homes); 1 BHK: 300 sq ft carpet (64 homes); 3 BHK: 10889 to 11684 sq ft carpet (59 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does ADHRIT have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 287 covered car parking spaces for ADHRIT.

How big is the land of ADHRIT?

According to GharKundli's check of MahaRERA records (updated October 2026), ADHRIT stands on 7,511 sq m of land (about 1.9 acres), with 25,228 sq m of sanctioned built-up area and 1,296 sq m of recreational open space.

Where can I read reviews of ADHRIT?

Google Maps has reviews of ADHRIT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ADHRIT?

ADHRIT by MUNDARA DEVELOPERS is in Malad, Mumbai (pincode 400064), near Kandivali West, Worli, Andheri West, Maharashtra, and is registered on MahaRERA as P51800009600, per GharKundli's check of MahaRERA records.

How many homes are in ADHRIT?

According to GharKundli's check of MahaRERA records (updated October 2026), ADHRIT has 468 homes in 5 towers registered on MahaRERA, and 73% of them are sold or booked.

When was ADHRIT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ADHRIT was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on ADHRIT?

24 court cases are listed for ADHRIT on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of ADHRIT?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MUNDARA DEVELOPERS.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400064

All 301 projects in Malad West (400064) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.