EKTA APARTMENT UPTO 17TH FLOOR
by ADITYA ENTERPRISE PROJECT EKTA · Rajendra Nagar, MumbaiAlso near Borivali West, Borivali East, Magathane
Possession date of EKTA APARTMENT UPTO 17TH FLOOR: 28 June 2026, moved from 31 March 2019 (83 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800009361. Status: Lapsed (registration period ended). Its completion date has moved from March 2019 to June 2026: 83 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (June 2026) has passed.
What do you want to know about EKTA APARTMENT UPTO 17TH FLOOR?
How the possession date of EKTA APARTMENT UPTO 17TH FLOOR has moved
31 March 2019
Completion date given when the project was registered
30 March 2020
Extended at the builder's request (MahaRERA application EXT51800001792)
Reason the builder gave MahaRERA:
“we have received Commencement Certificate from Municipal Corporation of Greater Mumbai on 07th April 2014 and further extended upto 12th upper floor on 10th October 2017, thereafter further approval was stuck due to MCGM and MHADA internal…” Read the full reason
“we have received Commencement Certificate from Municipal Corporation of Greater Mumbai on 07th April 2014 and further extended upto 12th upper floor on 10th October 2017, thereafter further approval was stuck due to MCGM and MHADA internal problems.”31 December 2021
Extended at the builder's request (MahaRERA application EXT51800009908)
Reason the builder gave MahaRERA:
“Dear Sir, We hereby apply for extension u/s 7(3) of the registered project bearing vide no. P5180009361 do hereby declare that the extended date of completion of above mentioned project was 30th September 2020. We would like to inform you t…” Read the full reason
“Dear Sir, We hereby apply for extension u/s 7(3) of the registered project bearing vide no. P5180009361 do hereby declare that the extended date of completion of above mentioned project was 30th September 2020. We would like to inform you that the project is 80% completed. We have total 72 apartments in EKTA APARTMENT UPTO 17TH FLOOR and out of that 71 apartments are sold and 1 apartments are unsold which needs to be sell but without the Extension Number we are unable to sell those inventories. Hence we are making this application for Project Extension u/s 7(3). We request you give extensio…”31 December 2023
Extended at the builder's request (MahaRERA application EXT51800015244)
Reason the builder gave MahaRERA:
“We received Commencement Certificate from the Municipal Corporation of Greater Mumbai on 07th April 2014 for the Top of Stilt slab level thereafter the CC is extended time-time as 18-06-2013 upto 5th Floor, then 08-09-2015 extended upto 10t…” Read the full reason
“We received Commencement Certificate from the Municipal Corporation of Greater Mumbai on 07th April 2014 for the Top of Stilt slab level thereafter the CC is extended time-time as 18-06-2013 upto 5th Floor, then 08-09-2015 extended upto 10th Floor and 10-10-2017 upto 12th Floor, thereafter further approval was stuck due to MCGM and MHADA internal problems. Vide a Notification of Urban Development Department, Govt. of Maharashtra u/no. TPB/4315/167/CR-51/2015/UD-II dated 23rd May 2018. Govt. of Maharashtra appointed MHADA as the planning authority for MHADA layouts, respect of this notificat…”31 December 2024
Extended at the builder's request (MahaRERA application EXT51800019040)
Reason the builder gave MahaRERA:
“We, the promoters of the ongoing MAHDA Re-development residential project known as 'Ekta Apartment,' developing the project with commercial shops on the ground floor and residential units on the upper floors, i.e., 1st to 22nd Floor. This p…” Read the full reason
“We, the promoters of the ongoing MAHDA Re-development residential project known as 'Ekta Apartment,' developing the project with commercial shops on the ground floor and residential units on the upper floors, i.e., 1st to 22nd Floor. This project is registered under MahaRERA with registration number P51800009361. We received the initial IOD from the Municipal Corporation of Greater Mumbai on 12-05-2011. The said project is a MAHDA Re-development project, and as a result, we have complied with various amendments as per MHADA’s guidelines. Subsequently, we obtained the first Commencement Cert…”28 February 2026
Extended at the builder's request (MahaRERA application EXT51800028105)
Reason the builder gave MahaRERA:
“With reference to above we would like to state that the project has been completed upto 16th floor & the delay has been caused due to delay in approvals, amendment in DCPR 2034, due to Covid & other technical reasons. However almost more th…” Read the full reason
“With reference to above we would like to state that the project has been completed upto 16th floor & the delay has been caused due to delay in approvals, amendment in DCPR 2034, due to Covid & other technical reasons. However almost more than 90% work is completed & possessions has been handed over to respective members & Purchasers. We are pleased to inform you that as per the Intimation of Disapproval (IOD) and Commencement Certificate (CC) already received, the construction work for the project is 95% complete. However, as per the provisions under the new Development Control and Promotio…”28 June 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: EKTA APARTMENT UPTO 17TH FLOOR’s extension records on MahaRERA (P51800009361), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on EKTA APARTMENT UPTO 17TH FLOOR
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800009361
- Status
- Lapsed (registration period ended)
- Builder
- ADITYA ENTERPRISE PROJECT EKTA
- Location
- Rajendra Nagar, Mumbai · 400066
- Project type
- Others
- Registered on
- 22 Aug 2017
- Completion date at registration
- March 2019
- Latest completion date
- June 2026
- Delay so far
- 83 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of EKTA APARTMENT UPTO 17TH FLOOR, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| EKTA APARTMENT UPTO 17TH FLOOR | 100% | 100% | 95% | 60% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on EKTA APARTMENT UPTO 17TH FLOOR every month.
EKTA APARTMENT UPTO 17TH FLOOR: buildings, flats and land, as filed on MahaRERA
- Buildings: EKTA APARTMENT UPTO 17TH FLOOR (18 floors)
- Land: 657 sq m (about 0.2 acres) · sanctioned built-up 3,348 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Aditya Enterprise Project Ekta has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 42 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of EKTA APARTMENT UPTO 17TH FLOOR →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
EKTA APARTMENT UPTO 17TH FLOOR: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about EKTA APARTMENT UPTO 17TH FLOOR
What is the possession date of EKTA APARTMENT UPTO 17TH FLOOR?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for EKTA APARTMENT UPTO 17TH FLOOR in Rajendra Nagar, Mumbai is 28 June 2026 — 83 months later than 31 March 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for EKTA APARTMENT UPTO 17TH FLOOR?
Builders and listing sites often quote an earlier "target" date for handover. The completion date EKTA APARTMENT UPTO 17TH FLOOR's builder has filed on MahaRERA, the official one, is 28 June 2026, already 83 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of EKTA APARTMENT UPTO 17TH FLOOR extended?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA APARTMENT UPTO 17TH FLOOR's builder applied to MahaRERA to extend the completion date 5 times: to 30 March 2020, giving the reason "we have received Commencement Certificate from Municipal Corporation of Greater Mumbai on 07th April 2014 and further extended upto 12th upper floor on 10th October 2017, thereafter further approval was stuck due to MCGM and MHADA internal problems."; to 31 December 2021, giving the reason "Dear Sir, We hereby apply for extension u/s 7(3) of the registered project bearing vide no. P5180009361 do hereby declare that the extended date of completion of above mentioned project was 30th September 2020. We would like to inform you that the project is 80% completed. We have total 72 apartments in EKTA APARTMENT UPTO 17TH FLOOR and out of that 71 apartments are sold and 1 apartments are unsold which needs to be sell but without the Extension Number we are unable to sell those inventories. Hence we are making this application for Project Extension u/s 7(3). We request you give extensio…"; to 31 December 2023, giving the reason "We received Commencement Certificate from the Municipal Corporation of Greater Mumbai on 07th April 2014 for the Top of Stilt slab level thereafter the CC is extended time-time as 18-06-2013 upto 5th Floor, then 08-09-2015 extended upto 10th Floor and 10-10-2017 upto 12th Floor, thereafter further approval was stuck due to MCGM and MHADA internal problems. Vide a Notification of Urban Development Department, Govt. of Maharashtra u/no. TPB/4315/167/CR-51/2015/UD-II dated 23rd May 2018. Govt. of Maharashtra appointed MHADA as the planning authority for MHADA layouts, respect of this notificat…"; to 31 December 2024, giving the reason "We, the promoters of the ongoing MAHDA Re-development residential project known as 'Ekta Apartment,' developing the project with commercial shops on the ground floor and residential units on the upper floors, i.e., 1st to 22nd Floor. This project is registered under MahaRERA with registration number P51800009361. We received the initial IOD from the Municipal Corporation of Greater Mumbai on 12-05-2011. The said project is a MAHDA Re-development project, and as a result, we have complied with various amendments as per MHADA’s guidelines. Subsequently, we obtained the first Commencement Cert…"; to 28 February 2026, giving the reason "With reference to above we would like to state that the project has been completed upto 16th floor & the delay has been caused due to delay in approvals, amendment in DCPR 2034, due to Covid & other technical reasons. However almost more than 90% work is completed & possessions has been handed over to respective members & Purchasers. We are pleased to inform you that as per the Intimation of Disapproval (IOD) and Commencement Certificate (CC) already received, the construction work for the project is 95% complete. However, as per the provisions under the new Development Control and Promotio…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of EKTA APARTMENT UPTO 17TH FLOOR?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of EKTA APARTMENT UPTO 17TH FLOOR in Rajendra Nagar, Mumbai is P51800009361.
Is EKTA APARTMENT UPTO 17TH FLOOR registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA APARTMENT UPTO 17TH FLOOR is registered as P51800009361 and its status is "Lapsed (registration period ended)".
What is the construction status of EKTA APARTMENT UPTO 17TH FLOOR?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA APARTMENT UPTO 17TH FLOOR's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on EKTA APARTMENT UPTO 17TH FLOOR is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does EKTA APARTMENT UPTO 17TH FLOOR have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is EKTA APARTMENT UPTO 17TH FLOOR safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA APARTMENT UPTO 17TH FLOOR is registered on MahaRERA as P51800009361, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 83 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if EKTA APARTMENT UPTO 17TH FLOOR's possession date changes?
The latest dates are on EKTA APARTMENT UPTO 17TH FLOOR's MahaRERA page (P51800009361). GharKundli's Kundli Watch sends a free WhatsApp update on EKTA APARTMENT UPTO 17TH FLOOR every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does EKTA APARTMENT UPTO 17TH FLOOR have?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA APARTMENT UPTO 17TH FLOOR has one building filed: EKTA APARTMENT UPTO 17TH FLOOR with 18 floors.
How big is the land of EKTA APARTMENT UPTO 17TH FLOOR?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA APARTMENT UPTO 17TH FLOOR stands on 657 sq m of land (about 0.2 acres), with 3,348 sq m of sanctioned built-up area.
What is the track record of EKTA APARTMENT UPTO 17TH FLOOR's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Enterprise Project Ekta has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 42 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of EKTA APARTMENT UPTO 17TH FLOOR?
Google Maps has reviews of EKTA APARTMENT UPTO 17TH FLOOR written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is EKTA APARTMENT UPTO 17TH FLOOR?
EKTA APARTMENT UPTO 17TH FLOOR by ADITYA ENTERPRISE PROJECT EKTA is in Rajendra Nagar, Mumbai (pincode 400066), near Borivali West, Borivali East, Magathane, Maharashtra, and is registered on MahaRERA as P51800009361, per GharKundli's check of MahaRERA records.
When was EKTA APARTMENT UPTO 17TH FLOOR registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), EKTA APARTMENT UPTO 17TH FLOOR was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on EKTA APARTMENT UPTO 17TH FLOOR?
No court cases are listed for EKTA APARTMENT UPTO 17TH FLOOR on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of EKTA APARTMENT UPTO 17TH FLOOR?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ADITYA ENTERPRISE PROJECT EKTA, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of EKTA APARTMENT UPTO 17TH FLOOR
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in pincode 400066
- Rustomjee Summit
- RAJENDRA NAGAR SWAGAT CHSL
- RAJENDRA NAGAR OMSAI CO-OPERATIVE HOUSING SOCIETY LIMITED
- MEGH MAHAL CHSL
- PARSHURAM HEIGHTS
- DTG ASHFORD
- H. Rishabraj AER
- Paras Darshan
Other projects by ADITYA ENTERPRISE PROJECT EKTA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.