Ekta Appartment From 18TH Floor To 22ND Floor
by ADITYA ENTERPRISE PROJECT EKTA · Dahisar East, Mumbai 400066Also near Borivali West, Borivali East, Rajendra Nagar
What’s in the report? →Possession date of Ekta Appartment From 18TH Floor To 22ND Floor (MahaRERA P51800011046): 30 April 2027, moved from 30 December 2021 (60 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800011046, and currently active. Its completion date has moved from December 2021 to April 2027: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800011046, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Ekta Appartment From 18TH Floor To 22ND Floor?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Ekta Appartment From 18TH Floor To 22ND Floor has moved
30 December 2021
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT51800025565)
Reason the builder gave MahaRERA:
“With reference to above we would like to state that the project has been completed upto 17th floor & the delay has been caused due to delay in approvals, amendment in DCPR 2034, due to Covid & other technical reasons. However almost more th…” Read the full reason
“With reference to above we would like to state that the project has been completed upto 17th floor & the delay has been caused due to delay in approvals, amendment in DCPR 2034, due to Covid & other technical reasons. However almost more than 70% work is completed & possessions has been handed over to respective members & Purchasers. We are pleased to inform you that as per the Intimation of Disapproval (IOD), the construction work for the project upto 17th floor is 95% complete. However, as per the provisions under the new Development Control and Promotion Regulations (DCPR) 2034, it is no…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Ekta Appartment From 18TH Floor To 22ND Floor’s extension records on MahaRERA (P51800011046), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ekta Appartment From 18TH Floor To 22ND Floor
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800011046
- Status
- Registered and active
- Builder
- ADITYA ENTERPRISE PROJECT EKTA
- Location
- Dahisar East, Mumbai · 400066
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- April 2027
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Ekta Appartment From 18TH Floor To 22ND Floor, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| EKTA APARTMENTS | 100% | 17% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ekta Appartment From 18TH Floor To 22ND Floor every 1–2 months.
Ekta Appartment From 18TH Floor To 22ND Floor: buildings, flats and land, as filed on MahaRERA
- Buildings: EKTA APARTMENTS (6 floors)
- Land: 657 sq m (about 0.2 acres)
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Aditya Enterprise Project Ekta has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 42 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Ekta Appartment From 18TH Floor To 22ND Floor →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ekta Appartment From 18TH Floor To 22ND Floor: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Ekta Appartment From 18TH Floor To 22ND Floor
What is the possession date of Ekta Appartment From 18TH Floor To 22ND Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ekta Appartment From 18TH Floor To 22ND Floor in Dahisar East, Mumbai is 30 April 2027 — 60 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 60 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Ekta Appartment From 18TH Floor To 22ND Floor?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ekta Appartment From 18TH Floor To 22ND Floor's builder has filed on MahaRERA, the official one, is 30 April 2027, already 60 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Ekta Appartment From 18TH Floor To 22ND Floor extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Appartment From 18TH Floor To 22ND Floor's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "With reference to above we would like to state that the project has been completed upto 17th floor & the delay has been caused due to delay in approvals, amendment in DCPR 2034, due to Covid & other technical reasons. However almost more than 70% work is completed & possessions has been handed over to respective members & Purchasers. We are pleased to inform you that as per the Intimation of Disapproval (IOD), the construction work for the project upto 17th floor is 95% complete. However, as per the provisions under the new Development Control and Promotion Regulations (DCPR) 2034, it is no…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Ekta Appartment From 18TH Floor To 22ND Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ekta Appartment From 18TH Floor To 22ND Floor in Dahisar East, Mumbai is P51800011046.
Is Ekta Appartment From 18TH Floor To 22ND Floor registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Appartment From 18TH Floor To 22ND Floor is registered as P51800011046 and its status is "Registered and active".
What is the current construction status of Ekta Appartment From 18TH Floor To 22ND Floor? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Appartment From 18TH Floor To 22ND Floor's status on MahaRERA is "Registered and active". As filed by the builder, slab work on EKTA APARTMENTS is 17% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Ekta Appartment From 18TH Floor To 22ND Floor have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Ekta Appartment From 18TH Floor To 22ND Floor safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Appartment From 18TH Floor To 22ND Floor is registered on MahaRERA as P51800011046, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Ekta Appartment From 18TH Floor To 22ND Floor?
Ekta Appartment From 18TH Floor To 22ND Floor is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Ekta Appartment From 18TH Floor To 22ND Floor?
For a flat in Ekta Appartment From 18TH Floor To 22ND Floor (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Ekta Appartment From 18TH Floor To 22ND Floor received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Appartment From 18TH Floor To 22ND Floor is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Ekta Appartment From 18TH Floor To 22ND Floor uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ekta Appartment From 18TH Floor To 22ND Floor was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Ekta Appartment From 18TH Floor To 22ND Floor's possession date changes?
The latest dates are on Ekta Appartment From 18TH Floor To 22ND Floor's MahaRERA page (P51800011046). GharKundli's Kundli Watch sends a free WhatsApp update on Ekta Appartment From 18TH Floor To 22ND Floor every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ekta Appartment From 18TH Floor To 22ND Floor have?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Appartment From 18TH Floor To 22ND Floor has one building filed: EKTA APARTMENTS with 6 floors.
How big is the land of Ekta Appartment From 18TH Floor To 22ND Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Appartment From 18TH Floor To 22ND Floor stands on 657 sq m of land (about 0.2 acres).
What is the track record of Ekta Appartment From 18TH Floor To 22ND Floor's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Enterprise Project Ekta has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 42 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Ekta Appartment From 18TH Floor To 22ND Floor?
Google Maps has reviews of Ekta Appartment From 18TH Floor To 22ND Floor written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Ekta Appartment From 18TH Floor To 22ND Floor?
Ekta Appartment From 18TH Floor To 22ND Floor by ADITYA ENTERPRISE PROJECT EKTA is in Dahisar East, Mumbai, pincode 400066 (near Borivali West, Borivali East, Rajendra Nagar), Maharashtra, and is registered on MahaRERA as P51800011046, per GharKundli's check of MahaRERA records. GharKundli lists all 228 MahaRERA projects in Borivali East (400066).
When was Ekta Appartment From 18TH Floor To 22ND Floor registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ekta Appartment From 18TH Floor To 22ND Floor was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Does Ekta Appartment From 18TH Floor To 22ND Floor have any legal issues or court cases?
No court cases are listed for Ekta Appartment From 18TH Floor To 22ND Floor on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Ekta Appartment From 18TH Floor To 22ND Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ADITYA ENTERPRISE PROJECT EKTA, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Ekta Appartment From 18TH Floor To 22ND Floor
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Borivali East (400066)
All 228 projects in Borivali East (400066) →Other projects by ADITYA ENTERPRISE PROJECT EKTA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.