Gauri Milestone
by GAURI DEVELOPERS · Dahisar East, Mumbai 400068Also near Mandapeshwar, Borivali EastRegistered on MahaRERA as “MILESTONE”
What’s in the report? →Possession date of Gauri Milestone (MahaRERA P51800031163): 30 April 2030, moved from 30 June 2025 (54 months later). It has 36 homes (1 BHK and 2 BHK, 344–678 sq ft carpet), 10% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800031163, and currently active. Its completion date has moved from June 2025 to April 2030: 54 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800031163, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Gauri Milestone?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Gauri Milestone has moved
30 June 2025
Completion date given when the project was registered
31 December 2029
Extended at the builder's request (MahaRERA application EA04042620558)
Reason the builder gave MahaRERA:
“Sub.: Submission of technical reasons for delay in completion of the Project 'Milestone'. We would like to request you that the project named as "Milestone" which is located at C. S. Road, Anand Nagar, Dahisar (East), Mumbai 400068, having…” Read the full reason
“Sub.: Submission of technical reasons for delay in completion of the Project 'Milestone'. We would like to request you that the project named as "Milestone" which is located at C. S. Road, Anand Nagar, Dahisar (East), Mumbai 400068, having its Registration No. P51800031163 was mentioned to be completed on 30/06/2025. The main delay is due to unforeseen issue regarding Shifting of High Frequency Tx/Rx station from Dahisar to alternate location at Gorai, which was beyond control of anybody. The Ministry of Civil Aviation has laid down the height restriction for our project and other projects…”30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Gauri Milestone’s extension records on MahaRERA (P51800031163), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Gauri Milestone
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800031163
- Status
- Registered and active
- Builder
- GAURI DEVELOPERS
- Location
- Dahisar East, Mumbai · 400068
- Project type
- Others
- Registered on
- 11 Oct 2021
- Completion date at registration
- June 2025
- Latest completion date
- April 2030
- Delay so far
- 54 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 36
- Sold or booked
- 10%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Gauri Milestone, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A WING | 0% | 0% | 0% | 0% |
| B WING | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- A WING: covers building comprising of Wing A – Stilt + 1st to 5th upper floors
- B WING: covers Ground(part) + Stilt(part) + 1st to 4th + (part) 5th floor
Latest CC order on MahaRERA: dated 01/11/2023.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gauri Milestone every 1–2 months.
Gauri Milestone: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 538 – 678 | 20 |
| 1 BHK | 344 – 506 | 16 |
| Shops | 172 – 581 | 6 |
| Office Space | 829 – 1,259 | 2 |
- Buildings: A WING (6 floors, 20 units) · B WING (6 floors, 24 units)
- Car parking: 141 covered
- Land: 3,064 sq m (about 0.8 acres) · sanctioned built-up 3,085 sq m
- Land, as filed: CTS NO 1431A OF VILLAGE DAHISAR
- Map: Get directions
The builder’s record and reviews
Gauri Land Developers (a group of 5 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 still being built, 4 past the promised date (typically 70 months late); 2 lapsed. 11 complaints on MahaRERA across 4 projects.
Read Google reviews of Gauri Milestone →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Gauri Milestone: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Gauri Milestone
What is the possession date of Gauri Milestone?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gauri Milestone in Dahisar East, Mumbai is 30 April 2030 — 54 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 54 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Gauri Milestone?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Gauri Milestone's builder has filed on MahaRERA, the official one, is 30 April 2030, already 54 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Gauri Milestone extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Milestone's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "Sub.: Submission of technical reasons for delay in completion of the Project 'Milestone'. We would like to request you that the project named as "Milestone" which is located at C. S. Road, Anand Nagar, Dahisar (East), Mumbai 400068, having its Registration No. P51800031163 was mentioned to be completed on 30/06/2025. The main delay is due to unforeseen issue regarding Shifting of High Frequency Tx/Rx station from Dahisar to alternate location at Gorai, which was beyond control of anybody. The Ministry of Civil Aviation has laid down the height restriction for our project and other projects…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Gauri Milestone?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gauri Milestone in Dahisar East, Mumbai is P51800031163.
Is Gauri Milestone registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Milestone is registered as P51800031163 and its status is "Registered and active".
What is the current construction status of Gauri Milestone? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Milestone's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Gauri Milestone have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Gauri Milestone safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Milestone is registered on MahaRERA as P51800031163, its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Gauri Milestone?
Gauri Milestone is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Gauri Milestone are 344 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Gauri Milestone?
For a flat in Gauri Milestone (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Gauri Milestone received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Milestone is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Gauri Milestone a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Milestone is a redevelopment: 14 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Gauri Milestone uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Gauri Milestone was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Gauri Milestone's possession date changes?
The latest dates are on Gauri Milestone's MahaRERA page (P51800031163). GharKundli's Kundli Watch sends a free WhatsApp update on Gauri Milestone every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Gauri Milestone have?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Milestone has 2 buildings filed: A WING with 6 floors and 20 units; B WING with 6 floors and 24 units.
What are the flat sizes (carpet area) in Gauri Milestone?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Gauri Milestone: 2 BHK: 538 to 678 sq ft carpet (20 homes); 1 BHK: 344 to 506 sq ft carpet (16 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Gauri Milestone have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 141 covered car parking spaces for Gauri Milestone.
How big is the land of Gauri Milestone?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Milestone stands on 3,064 sq m of land (about 0.8 acres), with 3,085 sq m of sanctioned built-up area.
What is the track record of Gauri Milestone's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Land Developers (a group of 5 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 5 still being built, 4 past the promised date (typically 70 months late); 2 lapsed. 11 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Gauri Milestone?
Google Maps has reviews of Gauri Milestone written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Gauri Milestone?
Gauri Milestone by GAURI DEVELOPERS is in Dahisar East, Mumbai, pincode 400068 (near Mandapeshwar, Borivali East), Maharashtra, and is registered on MahaRERA as P51800031163, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 1431A OF VILLAGE DAHISAR. GharKundli lists all 180 MahaRERA projects in Dahisar East (400068).
How many flats are in Gauri Milestone, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Milestone has 36 homes in 2 towers registered on MahaRERA, and 10% of them are sold or booked.
When was Gauri Milestone registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gauri Milestone was registered on MahaRERA on 11 October 2021. GharKundli did not find a title report on the land on file there.
Does Gauri Milestone have any legal issues or court cases?
No court cases are listed for Gauri Milestone on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Gauri Milestone?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GAURI DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Gauri Milestone
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai Suburban →
Other projects in Dahisar East (400068)
- Nirali Lifespace
- Rajhans
- Shree Ganesh CHSL
- Brindavan CHSL
- Raj Capital
- Royal Accord
- Ozone Residency
- Empire Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.