Chaitraban Phase-I

by S & S DEVELOPERS · Adgaon Shiwar, NashikAlso near Panchvati

Possession date of Chaitraban Phase-I: 30 April 2027, moved from 31 December 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600034181, and currently active. Its completion date has moved from December 2022 to April 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Chaitraban Phase-I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Chaitraban Phase-I has moved

  1. 31 December 2022

    Completion date given when the project was registered

  2. 30 December 2026

    Extended at the builder's request (MahaRERA application EXT51600013043)

    Reason the builder gave MahaRERA: “Change in Esimated Date of Project Completion due to revision in Sanctioned Plan”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Chaitraban Phase-I’s extension records on MahaRERA (P51600034181), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Chaitraban Phase-I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600034181
Status
Registered and active
Builder
S & S DEVELOPERS
Location
Adgaon Shiwar, Nashik · 422003
Project type
Others
Registered on
25 Mar 2022
Completion date at registration
December 2022
Latest completion date
April 2027
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
160
Sold or booked
35%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Chaitraban Phase-I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A-wing80%35%40%60%
B-Wing80%35%75%55%

Commencement certificate (CC), as filed on MahaRERA

  • A-wing: covers 13 floors
  • B-Wing: covers 12 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Chaitraban Phase-I every month.

Chaitraban Phase-I: buildings, flats and land, as filed on MahaRERA

  • Buildings: A-wing (13 floors, 111 units) · B-Wing (12 floors, 80 units)
  • Land: 2,466 sq m (about 0.6 acres) · sanctioned built-up 8,597 sq m
  • Boundaries filed include: 7 and half Metre Road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Chaitraban Phase-I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Chaitraban Phase-I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Chaitraban Phase-I

What is the possession date of Chaitraban Phase-I?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Chaitraban Phase-I in Adgaon Shiwar, Nashik is 30 April 2027 — 48 months later than 31 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Chaitraban Phase-I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Chaitraban Phase-I's builder has filed on MahaRERA, the official one, is 30 April 2027, already 48 months later than the 31 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Chaitraban Phase-I extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Chaitraban Phase-I's builder applied to MahaRERA to extend the completion date once: to 30 December 2026, giving the reason "Change in Esimated Date of Project Completion due to revision in Sanctioned Plan". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Chaitraban Phase-I?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Chaitraban Phase-I in Adgaon Shiwar, Nashik is P51600034181.

Is Chaitraban Phase-I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Chaitraban Phase-I is registered as P51600034181 and its status is "Registered and active".

What is the construction status of Chaitraban Phase-I?

According to GharKundli's check of MahaRERA records (updated November 2026), Chaitraban Phase-I's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 35% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Chaitraban Phase-I have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Chaitraban Phase-I safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Chaitraban Phase-I is registered on MahaRERA as P51600034181, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Chaitraban Phase-I's possession date changes?

The latest dates are on Chaitraban Phase-I's MahaRERA page (P51600034181). GharKundli's Kundli Watch sends a free WhatsApp update on Chaitraban Phase-I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Chaitraban Phase-I have?

According to GharKundli's check of MahaRERA records (updated November 2026), Chaitraban Phase-I has 2 buildings filed: A-wing with 13 floors and 111 units; B-Wing with 12 floors and 80 units.

How big is the land of Chaitraban Phase-I?

According to GharKundli's check of MahaRERA records (updated November 2026), Chaitraban Phase-I stands on 2,466 sq m of land (about 0.6 acres), with 8,597 sq m of sanctioned built-up area.

Where can I read reviews of Chaitraban Phase-I?

Google Maps has reviews of Chaitraban Phase-I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Chaitraban Phase-I?

Chaitraban Phase-I by S & S DEVELOPERS is in Adgaon Shiwar, Nashik (pincode 422003), near Panchvati, Maharashtra, and is registered on MahaRERA as P51600034181, per GharKundli's check of MahaRERA records. Its boundaries filed there include 7 and half Metre Road.

How many homes are in Chaitraban Phase-I?

According to GharKundli's check of MahaRERA records (updated November 2026), Chaitraban Phase-I has 160 homes in 2 towers registered on MahaRERA, and 35% of them are sold or booked.

When was Chaitraban Phase-I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Chaitraban Phase-I was registered on MahaRERA on 25 March 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Chaitraban Phase-I?

No court cases are listed for Chaitraban Phase-I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Chaitraban Phase-I?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is S & S DEVELOPERS.

All projects with possession due in 2027 in Nashik →

Other projects in pincode 422003

All 356 projects in Panchvati (422003) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.