Possession date of OLIVE GARDEN: 30 January 2027, moved from 31 March 2025 (18 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51600034504, and currently active. Its completion date has moved from March 2025 to January 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about OLIVE GARDEN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of OLIVE GARDEN has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 31 March 2026

    Extended at the builder's request (MahaRERA application EXT51600028060)

    Reason the builder gave MahaRERA:
    “Construction of project is not completed on time. We unable to complete the project till 31/03/2025. We request you to please grant us extension till 31/03/2026. We are in process of completion of project. The project is not completed withi…” Read the full reason“Construction of project is not completed on time. We unable to complete the project till 31/03/2025. We request you to please grant us extension till 31/03/2026. We are in process of completion of project. The project is not completed within time specified in registration due to financial crunch and less booking response in the project we need additional time to complete the pending development works in the project”
  3. 30 September 2026

    Extended at the builder's request (MahaRERA application EA24042620721)

    Reason the builder gave MahaRERA: “The project is not completed within time specified in registration due to financial crunch and slow booking response in the project we need additional time to complete the pending development works in the project.”
  4. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: OLIVE GARDEN’s extension records on MahaRERA (P51600034504), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on OLIVE GARDEN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600034504
Status
Registered and active
Builder
OLIVE INFRASTRUCTURE
Location
Dwarka Corner, Nashik · 422011
Project type
Others
Registered on
11 Apr 2022
Completion date at registration
March 2025
Latest completion date
January 2027
Delay so far
18 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
27
Sold or booked
63%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of OLIVE GARDEN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
OLIVE GARDEN A WING100%100%100%50%
OLIVE GARDEN B WING100%100%100%50%

Commencement certificate (CC), as filed on MahaRERA

  • OLIVE GARDEN A WING: covers 8 floors
  • OLIVE GARDEN B WING: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on OLIVE GARDEN every month.

OLIVE GARDEN: buildings, flats and land, as filed on MahaRERA

  • Buildings: OLIVE GARDEN A WING (8 floors, 20 units) · OLIVE GARDEN B WING (8 floors, 20 units)
  • Car parking: 33 covered
  • Land: 1,188 sq m (about 0.3 acres) · sanctioned built-up 3,542 sq m
  • Boundaries filed include: 15 MTS WIDTH ROAD

The builder’s record and reviews

Aqeeq Infrastructure AND Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 15 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of OLIVE GARDEN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

OLIVE GARDEN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about OLIVE GARDEN

What is the possession date of OLIVE GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for OLIVE GARDEN in Dwarka Corner, Nashik is 30 January 2027 — 18 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for OLIVE GARDEN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date OLIVE GARDEN's builder has filed on MahaRERA, the official one, is 30 January 2027, already 18 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of OLIVE GARDEN extended?

According to GharKundli's check of MahaRERA records (updated October 2026), OLIVE GARDEN's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2026, giving the reason "Construction of project is not completed on time. We unable to complete the project till 31/03/2025. We request you to please grant us extension till 31/03/2026. We are in process of completion of project. The project is not completed within time specified in registration due to financial crunch and less booking response in the project we need additional time to complete the pending development works in the project"; to 30 September 2026, giving the reason "The project is not completed within time specified in registration due to financial crunch and slow booking response in the project we need additional time to complete the pending development works in the project.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of OLIVE GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of OLIVE GARDEN in Dwarka Corner, Nashik is P51600034504.

Is OLIVE GARDEN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), OLIVE GARDEN is registered as P51600034504 and its status is "Registered and active".

What is the construction status of OLIVE GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), OLIVE GARDEN's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does OLIVE GARDEN have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is OLIVE GARDEN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), OLIVE GARDEN is registered on MahaRERA as P51600034504, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if OLIVE GARDEN's possession date changes?

The latest dates are on OLIVE GARDEN's MahaRERA page (P51600034504). GharKundli's Kundli Watch sends a free WhatsApp update on OLIVE GARDEN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does OLIVE GARDEN have?

According to GharKundli's check of MahaRERA records (updated October 2026), OLIVE GARDEN has 2 buildings filed: OLIVE GARDEN A WING with 8 floors and 20 units; OLIVE GARDEN B WING with 8 floors and 20 units.

How much parking does OLIVE GARDEN have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 33 covered car parking spaces for OLIVE GARDEN.

How big is the land of OLIVE GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), OLIVE GARDEN stands on 1,188 sq m of land (about 0.3 acres), with 3,542 sq m of sanctioned built-up area.

What is the track record of OLIVE GARDEN's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Aqeeq Infrastructure AND Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 15 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of OLIVE GARDEN?

Google Maps has reviews of OLIVE GARDEN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is OLIVE GARDEN?

OLIVE GARDEN by OLIVE INFRASTRUCTURE is in Dwarka Corner, Nashik (pincode 422011), near Ojhar A.F. Stn, Maharashtra, and is registered on MahaRERA as P51600034504, per GharKundli's check of MahaRERA records. Its boundaries filed there include 15 MTS WIDTH ROAD.

How many homes are in OLIVE GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), OLIVE GARDEN has 27 homes in 2 towers registered on MahaRERA, and 63% of them are sold or booked.

When was OLIVE GARDEN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), OLIVE GARDEN was registered on MahaRERA on 11 April 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on OLIVE GARDEN?

No court cases are listed for OLIVE GARDEN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of OLIVE GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is OLIVE INFRASTRUCTURE.

All projects with possession due in 2027 in Nashik →

Other projects in pincode 422011

All 93 projects in Dwarka Corner (422011) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.