Waterways
by Sanklecha Construction Private Limited · tapovan road, Nashik
Possession date of Waterways: 31 December 2028, moved from 30 June 2021 (90 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600008638, and currently active. MahaRERA has issued a regulatory order on this project. 6 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Waterways?
How the possession date of Waterways has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT51600010285)
Reason the builder gave MahaRERA: “Delay Due to Covid -19 pandemic and its cascading affects, we required more time to complete”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51600015058)
Reason the builder gave MahaRERA: “Various Reason already Explain in exemplary Note with Form E”
31 December 2028
Extended at the builder's request (MahaRERA application EA18122518764)
Reason the builder gave MahaRERA:
“the project loan availed by us from the State Bank of India was classified as a default, pursuant to which the Bank initiated proceedings under the SARFAESI Act, 2002, including actions under Sections 13(2) and 13(4). During the period betw…” Read the full reason
“the project loan availed by us from the State Bank of India was classified as a default, pursuant to which the Bank initiated proceedings under the SARFAESI Act, 2002, including actions under Sections 13(2) and 13(4). During the period between 2020 and 2022, the Bank also took symbolic possession of the project. These circumstances resulted in severe financial constraints and significantly impacted the progress of the project. In order to overcome these financial difficulties and ensure completion of the project, we, as developers, approached SWAMIH Investment Fund–I. The Hon’ble Finance Mi…”
Source: Waterways’s extension records on MahaRERA (P51600008638), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Waterways
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 complaints, and how it ended
- Construction pace against the December 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600008638
- Status
- Registered and active
- Builder
- Sanklecha Construction Private Limited
- Location
- tapovan road, Nashik · 422011
- Project type
- Residential / Group Housing
- Registered on
- 19 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- December 2028
- Delay so far
- 90 months
- Homes
- 192
- Sold or booked
- 60%
- Towers
- 8
- Complaints on MahaRERA
- 6
- Court cases listed
- 0
- Appeals at the tribunal
- 3
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 11
Construction progress of Waterways, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A1 | 100% | 100% | 100% | 70% |
| A2 | 100% | 100% | 100% | 50% |
| B1 | 100% | 100% | 10% | 0% |
| B2 | 100% | 50% | 0% | 0% |
| C1 | 100% | 80% | 0% | 0% |
| C2 | 100% | 0% | 0% | 0% |
| D1 | 0% | 0% | 0% | 0% |
| D2 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- A1: covers 12 floors
- A2: covers 12 floors
- B1: covers 12 floors
- B2: covers 2 floors
- C1: covers 12 floors
Latest CC order on MahaRERA: dated 06/06/2015.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Waterways every month.
Waterways: buildings, flats and land, as filed on MahaRERA
- Buildings: A1 (14 floors, 48 units) · A2 (14 floors, 48 units) · B1 (14 floors, 48 units) · B2 (14 floors) · C1 (14 floors, 48 units) · C2 (14 floors) · D1 (14 floors) · D2 (14 floors)
- Land: 18,306 sq m (about 4.5 acres) · sanctioned built-up 16,158 sq m
The builder’s record and reviews
Sanklecha Construction has 12 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 43 months); 3 still being built, 3 past the promised date (typically 78 months late). 17 complaints on MahaRERA across 4 projects.
Read Google reviews of Waterways →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Waterways: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Waterways
What is the possession date of Waterways?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Waterways in tapovan road, Nashik is 31 December 2028 — 90 months later than 30 June 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Waterways?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Waterways's builder has filed on MahaRERA, the official one, is 31 December 2028, already 90 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Waterways extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Waterways's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "Delay Due to Covid -19 pandemic and its cascading affects, we required more time to complete"; to 31 December 2025, giving the reason "Various Reason already Explain in exemplary Note with Form E"; to 31 December 2028, giving the reason "the project loan availed by us from the State Bank of India was classified as a default, pursuant to which the Bank initiated proceedings under the SARFAESI Act, 2002, including actions under Sections 13(2) and 13(4). During the period between 2020 and 2022, the Bank also took symbolic possession of the project. These circumstances resulted in severe financial constraints and significantly impacted the progress of the project. In order to overcome these financial difficulties and ensure completion of the project, we, as developers, approached SWAMIH Investment Fund–I. The Hon’ble Finance Mi…".
What is the RERA number of Waterways?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Waterways in tapovan road, Nashik is P51600008638.
Is Waterways registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Waterways is registered as P51600008638 and its status is "Registered and active".
What is the construction status of Waterways?
According to GharKundli's check of MahaRERA records (updated October 2026), Waterways's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 8 towers. GharKundli's full report compares construction progress with the deadline.
Does Waterways have complaints on MahaRERA?
6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Waterways safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Waterways is registered on MahaRERA as P51600008638, its completion date has moved 90 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Waterways's possession date changes?
The latest dates are on Waterways's MahaRERA page (P51600008638). GharKundli's Kundli Watch sends a free WhatsApp update on Waterways every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Waterways have?
According to GharKundli's check of MahaRERA records (updated October 2026), Waterways has 8 buildings filed: A1 with 14 floors and 48 units; A2 with 14 floors and 48 units; B1 with 14 floors and 48 units; B2 with 14 floors; C1 with 14 floors and 48 units; C2 with 14 floors; and 2 more.
How big is the land of Waterways?
According to GharKundli's check of MahaRERA records (updated October 2026), Waterways stands on 18,306 sq m of land (about 4.5 acres), with 16,158 sq m of sanctioned built-up area.
What is the track record of Waterways's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sanklecha Construction has 12 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 43 months); 3 still being built, 3 past the promised date (typically 78 months late). 17 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Waterways?
Google Maps has reviews of Waterways written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Waterways?
Waterways by Sanklecha Construction Private Limited is in tapovan road, Nashik (pincode 422011), Maharashtra, and is registered on MahaRERA as P51600008638, per GharKundli's check of MahaRERA records.
How many homes are in Waterways?
According to GharKundli's check of MahaRERA records (updated October 2026), Waterways has 192 homes in 8 towers registered on MahaRERA, and 60% of them are sold or booked.
When was Waterways registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Waterways was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Waterways?
No court cases are listed for Waterways on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Waterways?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sanklecha Construction Private Limited, which has 11 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Waterways
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Nashik →
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- YUNUS RESIDENCY
- SHIV KUNJ
- Quillion Residencies at Quillion Park - Phase 2
- SHREE VISHVA
- SARA SERENITY APARTMENT
Other projects by Sanklecha Construction Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.