The Metrozone Kingstone D1
by Sanklecha Construction Private Limited · Mumbai Naka, Nashik
Possession date of The Metrozone Kingstone D1: 30 April 2027, moved from 31 December 2019 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600005201, and currently active. Its completion date has moved from December 2019 to April 2027: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about The Metrozone Kingstone D1?
How the possession date of The Metrozone Kingstone D1 has moved
31 December 2019
Completion date given when the project was registered
31 March 2023
Extended at the builder's request (MahaRERA application EXT51600008607)
Reason the builder gave MahaRERA: “delay in Govt. Permission like Environment & Corporation sanction, New Laws, Covid 19 and Demonetization”
31 December 2026
Extended at the builder's request (MahaRERA application EXT51600017837)
Reason the builder gave MahaRERA: “We are in process of Increase the floors & area according to the DCPR. Now We Get revised sanction from Nashik Muncipal Corporation. So We are appliing for Extension & Correction in the area of project”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: The Metrozone Kingstone D1’s extension records on MahaRERA (P51600005201), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on The Metrozone Kingstone D1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600005201
- Status
- Registered and active
- Builder
- Sanklecha Construction Private Limited
- Location
- Mumbai Naka, Nashik · 422009
- Project type
- Residential / Group Housing
- Registered on
- 10 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- April 2027
- Delay so far
- 84 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 30
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 4
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 11
Construction progress of The Metrozone Kingstone D1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Kingstone D1 | 100% | 85% | 50% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Metrozone Kingstone D1 every month.
The Metrozone Kingstone D1: buildings, flats and land, as filed on MahaRERA
- Buildings: Kingstone D1 (16 floors)
- Land: 2,575 sq m (about 0.6 acres) · sanctioned built-up 3,823 sq m
The builder’s record and reviews
Sanklecha Construction has 12 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 43 months); 3 still being built, 3 past the promised date (typically 78 months late). 17 complaints on MahaRERA across 4 projects.
Read Google reviews of The Metrozone Kingstone D1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
The Metrozone Kingstone D1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about The Metrozone Kingstone D1
What is the possession date of The Metrozone Kingstone D1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for The Metrozone Kingstone D1 in Mumbai Naka, Nashik is 30 April 2027 — 84 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for The Metrozone Kingstone D1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date The Metrozone Kingstone D1's builder has filed on MahaRERA, the official one, is 30 April 2027, already 84 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of The Metrozone Kingstone D1 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Kingstone D1's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2023, giving the reason "delay in Govt. Permission like Environment & Corporation sanction, New Laws, Covid 19 and Demonetization"; to 31 December 2026, giving the reason "We are in process of Increase the floors & area according to the DCPR. Now We Get revised sanction from Nashik Muncipal Corporation. So We are appliing for Extension & Correction in the area of project". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of The Metrozone Kingstone D1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of The Metrozone Kingstone D1 in Mumbai Naka, Nashik is P51600005201.
Is The Metrozone Kingstone D1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Kingstone D1 is registered as P51600005201 and its status is "Registered and active".
What is the construction status of The Metrozone Kingstone D1?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Kingstone D1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Kingstone D1 is 85% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does The Metrozone Kingstone D1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is The Metrozone Kingstone D1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Kingstone D1 is registered on MahaRERA as P51600005201, its completion date has moved 84 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if The Metrozone Kingstone D1's possession date changes?
The latest dates are on The Metrozone Kingstone D1's MahaRERA page (P51600005201). GharKundli's Kundli Watch sends a free WhatsApp update on The Metrozone Kingstone D1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does The Metrozone Kingstone D1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Kingstone D1 has one building filed: Kingstone D1 with 16 floors.
How big is the land of The Metrozone Kingstone D1?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Kingstone D1 stands on 2,575 sq m of land (about 0.6 acres), with 3,823 sq m of sanctioned built-up area.
What is the track record of The Metrozone Kingstone D1's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanklecha Construction has 12 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 43 months); 3 still being built, 3 past the promised date (typically 78 months late). 17 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of The Metrozone Kingstone D1?
Google Maps has reviews of The Metrozone Kingstone D1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is The Metrozone Kingstone D1?
The Metrozone Kingstone D1 by Sanklecha Construction Private Limited is in Mumbai Naka, Nashik (pincode 422009), Maharashtra, and is registered on MahaRERA as P51600005201, per GharKundli's check of MahaRERA records.
How many homes are in The Metrozone Kingstone D1?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Kingstone D1 has 30 homes in 1 tower registered on MahaRERA.
When was The Metrozone Kingstone D1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Kingstone D1 was registered on MahaRERA on 10 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on The Metrozone Kingstone D1?
4 court cases are listed for The Metrozone Kingstone D1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of The Metrozone Kingstone D1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sanklecha Construction Private Limited, which has 11 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of The Metrozone Kingstone D1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nashik →
Other projects in Mumbai Naka
All 218 projects in CIDCO Colony (422009) →Other projects by Sanklecha Construction Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.