The Metrozone Aspen C3
by Sanklecha Construction Private Limited · Mumbai Naka, Nashik
Possession: The Metrozone Aspen C3 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600007130. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about The Metrozone Aspen C3?
How the possession date of The Metrozone Aspen C3 has moved
30 June 2018
Completion date given when the project was registered
30 September 2020
Extended at the builder's request (MahaRERA application EXT51600005607)
Reason the builder gave MahaRERA: “delay in Govt. Permission like Environment & Corporation sanction, New Laws and Demonetization”
31 October 2022
Extended at the builder's request (MahaRERA application EXT51600011500)
Reason the builder gave MahaRERA: “Project is delay due to corona pandemic situation , now we had completed project also received completion certificate from Nashik Municipal corporation”
Source: The Metrozone Aspen C3’s extension records on MahaRERA (P51600007130), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on The Metrozone Aspen C3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 court cases, and how it ended
- Construction pace against the October 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- The Metrozone Aspen C1P51600005208
- The Metrozone Aspen C2P51600009327
- MahaRERA registration
- P51600007130
- Status
- Completed
- Builder
- Sanklecha Construction Private Limited
- Location
- Mumbai Naka, Nashik · 422009
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- June 2018
- Latest completion date
- October 2022
- Delay so far
- 52 months
- Homes
- 24
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 4
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 11
Construction progress of The Metrozone Aspen C3, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Aspen C3 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Metrozone Aspen C3 every month.
The Metrozone Aspen C3: buildings, flats and land, as filed on MahaRERA
- Buildings: Aspen C3 (14 floors)
- Land: 2,153 sq m (about 0.5 acres) · sanctioned built-up 2,153 sq m
- Boundaries filed include: Internal Road and Open Space, Internal Road and Parking
The builder’s record and reviews
Sanklecha Construction has 12 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 43 months); 3 still being built, 3 past the promised date (typically 78 months late). 17 complaints on MahaRERA across 4 projects.
Read Google reviews of The Metrozone Aspen C3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
The Metrozone Aspen C3: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about The Metrozone Aspen C3
What is the possession date of The Metrozone Aspen C3?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for The Metrozone Aspen C3 in Mumbai Naka, Nashik is 31 October 2022 — 52 months later than 30 June 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for The Metrozone Aspen C3?
Builders and listing sites often quote an earlier "target" date for handover. The completion date The Metrozone Aspen C3's builder has filed on MahaRERA, the official one, is 31 October 2022, already 52 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of The Metrozone Aspen C3 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Aspen C3's builder applied to MahaRERA to extend the completion date 2 times: to 30 September 2020, giving the reason "delay in Govt. Permission like Environment & Corporation sanction, New Laws and Demonetization"; to 31 October 2022, giving the reason "Project is delay due to corona pandemic situation , now we had completed project also received completion certificate from Nashik Municipal corporation".
What is the RERA number of The Metrozone Aspen C3?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of The Metrozone Aspen C3 in Mumbai Naka, Nashik is P51600007130.
Is The Metrozone Aspen C3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Aspen C3 is registered as P51600007130 and its status is "Completed".
What is the construction status of The Metrozone Aspen C3?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Aspen C3's status on MahaRERA is "Completed". As filed by the builder, slab work on Aspen C3 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does The Metrozone Aspen C3 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is The Metrozone Aspen C3 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Aspen C3 is registered on MahaRERA as P51600007130, its MahaRERA status is "Completed", its completion date has moved 52 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does The Metrozone Aspen C3 have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: The Metrozone Aspen C1 (P51600005208); The Metrozone Aspen C2 (P51600009327). Check that your agreement names the registration of your own wing.
How can I get updates if The Metrozone Aspen C3's possession date changes?
The latest dates are on The Metrozone Aspen C3's MahaRERA page (P51600007130). GharKundli's Kundli Watch sends a free WhatsApp update on The Metrozone Aspen C3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does The Metrozone Aspen C3 have?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Aspen C3 has one building filed: Aspen C3 with 14 floors.
How big is the land of The Metrozone Aspen C3?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Aspen C3 stands on 2,153 sq m of land (about 0.5 acres), with 2,153 sq m of sanctioned built-up area.
What is the track record of The Metrozone Aspen C3's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanklecha Construction has 12 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 43 months); 3 still being built, 3 past the promised date (typically 78 months late). 17 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of The Metrozone Aspen C3?
Google Maps has reviews of The Metrozone Aspen C3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is The Metrozone Aspen C3?
The Metrozone Aspen C3 by Sanklecha Construction Private Limited is in Mumbai Naka, Nashik (pincode 422009), Maharashtra, and is registered on MahaRERA as P51600007130, per GharKundli's check of MahaRERA records. Its boundaries filed there include Internal Road and Open Space, Internal Road and Parking.
How many homes are in The Metrozone Aspen C3?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Aspen C3 has 24 homes in 1 tower registered on MahaRERA.
When was The Metrozone Aspen C3 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Aspen C3 was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on The Metrozone Aspen C3?
4 court cases are listed for The Metrozone Aspen C3 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of The Metrozone Aspen C3?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sanklecha Construction Private Limited, which has 11 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of The Metrozone Aspen C3
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mumbai Naka
All 218 projects in CIDCO Colony (422009) →Other projects by Sanklecha Construction Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.