Possession: The Metrozone Hampston B3 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600012165. Status: Completed. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
Sales frozen by MahaRERA: completion date lapsed
MahaRERA has put this project in abeyance because its completion date has lapsed. Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about The Metrozone Hampston B3?
How the possession date of The Metrozone Hampston B3 has moved
30 September 2018
Completion date given when the project was registered
29 September 2019
Extended at the builder's request (MahaRERA application EXT51600000866)
Reason the builder gave MahaRERA:
“1) The revised layout plan and revised building plan is yet to be sanctioned by Nashik Municipal Corporation. 2) Construction activity has not been completed, hence completion certificate is yet to be obtained from Nashik Municipal corporat…” Read the full reason
“1) The revised layout plan and revised building plan is yet to be sanctioned by Nashik Municipal Corporation. 2) Construction activity has not been completed, hence completion certificate is yet to be obtained from Nashik Municipal corporation. 3) Electricity and Water connection work is also under process.”31 December 2021
Extended at the builder's request (MahaRERA application EXT51600008527)
Reason the builder gave MahaRERA: “Covid 19 and Delay in approvals and Clareance from Goverment authority”
31 December 2023
Extended at the builder's request (MahaRERA application EXT51600013769)
Reason the builder gave MahaRERA: “COVID-19 , financial Difficulties and other reasons beyond the control.”
Source: The Metrozone Hampston B3’s extension records on MahaRERA (P51600012165), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on The Metrozone Hampston B3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints and 4 court cases, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- The Metrozone Hampston B1P51600007133
- The Metrozone Hampston B2P51600008309 · possession 31 Oct 2022
- MahaRERA registration
- P51600012165
- Status
- Completed
- Builder
- Sanklecha Construction Private Limited
- Location
- Near Indira Nagar, Nashik · 422009
- Project type
- Residential / Group Housing
- Registered on
- 1 Sep 2017
- Completion date at registration
- September 2018
- Latest completion date
- December 2023
- Delay so far
- 63 months
- Homes
- 48
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 4
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 11
Construction progress of The Metrozone Hampston B3, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Hampston B3 | 100% | 80% | 70% | 30% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Metrozone Hampston B3 every month.
The Metrozone Hampston B3: buildings, flats and land, as filed on MahaRERA
- Buildings: Hampston B3 (14 floors)
- Land: 2,639 sq m (about 0.7 acres) · sanctioned built-up 6,248 sq m
- Boundaries filed include: Internal Road and Open Space
The builder’s record and reviews
Sanklecha Construction has 12 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 43 months); 3 still being built, 3 past the promised date (typically 78 months late). 17 complaints on MahaRERA across 4 projects.
Read Google reviews of The Metrozone Hampston B3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
The Metrozone Hampston B3: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about The Metrozone Hampston B3
What is the possession date of The Metrozone Hampston B3?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for The Metrozone Hampston B3 in Near Indira Nagar, Nashik is 31 December 2023 — 63 months later than 30 September 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for The Metrozone Hampston B3?
Builders and listing sites often quote an earlier "target" date for handover. The completion date The Metrozone Hampston B3's builder has filed on MahaRERA, the official one, is 31 December 2023, already 63 months later than the 30 September 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of The Metrozone Hampston B3 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Hampston B3's builder applied to MahaRERA to extend the completion date 3 times: to 29 September 2019, giving the reason "1) The revised layout plan and revised building plan is yet to be sanctioned by Nashik Municipal Corporation. 2) Construction activity has not been completed, hence completion certificate is yet to be obtained from Nashik Municipal corporation. 3) Electricity and Water connection work is also under process."; to 31 December 2021, giving the reason "Covid 19 and Delay in approvals and Clareance from Goverment authority"; to 31 December 2023, giving the reason "COVID-19 , financial Difficulties and other reasons beyond the control.".
What is the RERA number of The Metrozone Hampston B3?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of The Metrozone Hampston B3 in Near Indira Nagar, Nashik is P51600012165.
Is The Metrozone Hampston B3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Hampston B3 is registered as P51600012165 and its status is "Completed". On MahaRERA's own list: Sales frozen by MahaRERA: completion date lapsed. MahaRERA has put this project in abeyance because its completion date has lapsed. Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.
What is the construction status of The Metrozone Hampston B3?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Hampston B3's status on MahaRERA is "Completed". As filed by the builder, slab work on Hampston B3 is 80% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does The Metrozone Hampston B3 have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is The Metrozone Hampston B3 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Hampston B3 is registered on MahaRERA as P51600012165, its MahaRERA status is "Completed", its completion date has moved 63 months since registration, 3 complaints are listed against it and it is on MahaRERA's list "Sales frozen by MahaRERA: completion date lapsed". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does The Metrozone Hampston B3 have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: The Metrozone Hampston B1 (P51600007133); The Metrozone Hampston B2 (P51600008309, possession 31 Oct 2022). Check that your agreement names the registration of your own wing.
How can I get updates if The Metrozone Hampston B3's possession date changes?
The latest dates are on The Metrozone Hampston B3's MahaRERA page (P51600012165). GharKundli's Kundli Watch sends a free WhatsApp update on The Metrozone Hampston B3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does The Metrozone Hampston B3 have?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Hampston B3 has one building filed: Hampston B3 with 14 floors.
How big is the land of The Metrozone Hampston B3?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Hampston B3 stands on 2,639 sq m of land (about 0.7 acres), with 6,248 sq m of sanctioned built-up area.
What is the track record of The Metrozone Hampston B3's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanklecha Construction has 12 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 0 within the promised date and 4 needed more time (typically 43 months); 3 still being built, 3 past the promised date (typically 78 months late). 17 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of The Metrozone Hampston B3?
Google Maps has reviews of The Metrozone Hampston B3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is The Metrozone Hampston B3?
The Metrozone Hampston B3 by Sanklecha Construction Private Limited is in Near Indira Nagar, Nashik (pincode 422009), Maharashtra, and is registered on MahaRERA as P51600012165, per GharKundli's check of MahaRERA records. Its boundaries filed there include Internal Road and Open Space.
How many homes are in The Metrozone Hampston B3?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Hampston B3 has 48 homes in 1 tower registered on MahaRERA.
When was The Metrozone Hampston B3 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Metrozone Hampston B3 was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on The Metrozone Hampston B3?
4 court cases are listed for The Metrozone Hampston B3 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of The Metrozone Hampston B3?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sanklecha Construction Private Limited, which has 11 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of The Metrozone Hampston B3
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Nashik
- Fortunes Emerald Park
- Laxmi Commercial Complex
- SHUBHSANKALP CO-OPERATIVE HOUSING SOCIETY LIMITED
- Quillion Residencies at Quillion Park - Phase 2
- SHIV KUNJ
- YUNUS RESIDENCY
- SHREE VISHVA
- SARA SERENITY APARTMENT
Other projects by Sanklecha Construction Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.