SHIVSIDDHI HEIGHTS
by PANKAJ SUDHAKAR GAVALI · Panchvati, Nashik
Possession date of SHIVSIDDHI HEIGHTS: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600045197, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SHIVSIDDHI HEIGHTS?
How the possession date of SHIVSIDDHI HEIGHTS has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHIVSIDDHI HEIGHTS’s extension records on MahaRERA (P51600045197), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHIVSIDDHI HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600045197
- Status
- Registered and active
- Builder
- PANKAJ SUDHAKAR GAVALI
- Location
- Panchvati, Nashik · 422003
- Project type
- Residential / Group Housing
- Registered on
- 10 May 2022
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 21
- Sold or booked
- 40%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHIVSIDDHI HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHIVSIDDHI HEIGHTS | 100% | 100% | 100% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHIVSIDDHI HEIGHTS every month.
SHIVSIDDHI HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: SHIVSIDDHI HEIGHTS (9 floors)
- Car parking: 11 covered
- Land: 548 sq m (about 0.1 acres) · sanctioned built-up 1,780 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHIVSIDDHI HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHIVSIDDHI HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHIVSIDDHI HEIGHTS
What is the possession date of SHIVSIDDHI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHIVSIDDHI HEIGHTS in Panchvati, Nashik is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHIVSIDDHI HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHIVSIDDHI HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SHIVSIDDHI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHIVSIDDHI HEIGHTS in Panchvati, Nashik is P51600045197.
Is SHIVSIDDHI HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIVSIDDHI HEIGHTS is registered as P51600045197 and its status is "Registered and active".
What is the construction status of SHIVSIDDHI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIVSIDDHI HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHIVSIDDHI HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SHIVSIDDHI HEIGHTS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SHIVSIDDHI HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIVSIDDHI HEIGHTS is registered on MahaRERA as P51600045197, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHIVSIDDHI HEIGHTS's possession date changes?
The latest dates are on SHIVSIDDHI HEIGHTS's MahaRERA page (P51600045197). GharKundli's Kundli Watch sends a free WhatsApp update on SHIVSIDDHI HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHIVSIDDHI HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIVSIDDHI HEIGHTS has one building filed: SHIVSIDDHI HEIGHTS with 9 floors.
How much parking does SHIVSIDDHI HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 11 covered car parking spaces for SHIVSIDDHI HEIGHTS.
How big is the land of SHIVSIDDHI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIVSIDDHI HEIGHTS stands on 548 sq m of land (about 0.1 acres), with 1,780 sq m of sanctioned built-up area.
Where can I read reviews of SHIVSIDDHI HEIGHTS?
Google Maps has reviews of SHIVSIDDHI HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHIVSIDDHI HEIGHTS?
SHIVSIDDHI HEIGHTS by PANKAJ SUDHAKAR GAVALI is in Panchvati, Nashik (pincode 422003), Maharashtra, and is registered on MahaRERA as P51600045197, per GharKundli's check of MahaRERA records.
How many homes are in SHIVSIDDHI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIVSIDDHI HEIGHTS has 21 homes in 1 tower registered on MahaRERA, and 40% of them are sold or booked.
When was SHIVSIDDHI HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHIVSIDDHI HEIGHTS was registered on MahaRERA on 10 May 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SHIVSIDDHI HEIGHTS?
No court cases are listed for SHIVSIDDHI HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SHIVSIDDHI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PANKAJ SUDHAKAR GAVALI.
Check it yourself on MahaRERA
- How to check the possession date of SHIVSIDDHI HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Nashik →
Other projects in pincode 422003
- ALPINE
- Vastu Shilp
- SHIVSUNDAR HEIGHTS
- PADMASHREE PARK
- Saubhagya Pride
- SAMARTH DATTAKRUPA
- Amber Co. Op. Hsg. Soc.
- AKSHAR GARDEN
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.