MANGAL MURTI APARTMENT

by PRAFULL SHANKARRAO AHIRE · Makhamalabad, NashikAlso near Panchvati

Possession date of MANGAL MURTI APARTMENT: 31 December 2023, moved from 20 March 2023 (9 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51600046686. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about MANGAL MURTI APARTMENT?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on MANGAL MURTI APARTMENT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51600046686
Status
Lapsed (registration period ended)
Builder
PRAFULL SHANKARRAO AHIRE
Location
Makhamalabad, Nashik · 422003
Project type
Residential / Group Housing
Registered on
29 Aug 2022
Completion date at registration
March 2023
Latest completion date
December 2023
Delay so far
9 months
Homes
9
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MANGAL MURTI APARTMENT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MANGAL MURTI APARTMENT100%100%90%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MANGAL MURTI APARTMENT every month.

MANGAL MURTI APARTMENT: buildings, flats and land, as filed on MahaRERA

  • Buildings: MANGAL MURTI APARTMENT (6 floors)
  • Land: 450 sq m (about 0.1 acres) · sanctioned built-up 816 sq m
  • Boundaries filed include: MAKHAMALABAD- MHASARUL ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MANGAL MURTI APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MANGAL MURTI APARTMENT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MANGAL MURTI APARTMENT

What is the possession date of MANGAL MURTI APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MANGAL MURTI APARTMENT in Makhamalabad, Nashik is 31 December 2023 — 9 months later than 20 March 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for MANGAL MURTI APARTMENT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MANGAL MURTI APARTMENT's builder has filed on MahaRERA, the official one, is 31 December 2023, already 9 months later than the 20 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of MANGAL MURTI APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MANGAL MURTI APARTMENT in Makhamalabad, Nashik is P51600046686.

Is MANGAL MURTI APARTMENT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MANGAL MURTI APARTMENT is registered as P51600046686 and its status is "Lapsed (registration period ended)".

What is the construction status of MANGAL MURTI APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), MANGAL MURTI APARTMENT's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MANGAL MURTI APARTMENT is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does MANGAL MURTI APARTMENT have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is MANGAL MURTI APARTMENT safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), MANGAL MURTI APARTMENT is registered on MahaRERA as P51600046686, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MANGAL MURTI APARTMENT's possession date changes?

The latest dates are on MANGAL MURTI APARTMENT's MahaRERA page (P51600046686). GharKundli's Kundli Watch sends a free WhatsApp update on MANGAL MURTI APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MANGAL MURTI APARTMENT have?

According to GharKundli's check of MahaRERA records (updated November 2026), MANGAL MURTI APARTMENT has one building filed: MANGAL MURTI APARTMENT with 6 floors.

How big is the land of MANGAL MURTI APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), MANGAL MURTI APARTMENT stands on 450 sq m of land (about 0.1 acres), with 816 sq m of sanctioned built-up area.

Where can I read reviews of MANGAL MURTI APARTMENT?

Google Maps has reviews of MANGAL MURTI APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MANGAL MURTI APARTMENT?

MANGAL MURTI APARTMENT by PRAFULL SHANKARRAO AHIRE is in Makhamalabad, Nashik (pincode 422003), near Panchvati, Maharashtra, and is registered on MahaRERA as P51600046686, per GharKundli's check of MahaRERA records. Its boundaries filed there include MAKHAMALABAD- MHASARUL ROAD.

How many homes are in MANGAL MURTI APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), MANGAL MURTI APARTMENT has 9 homes in 1 tower registered on MahaRERA.

When was MANGAL MURTI APARTMENT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MANGAL MURTI APARTMENT was registered on MahaRERA on 29 August 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on MANGAL MURTI APARTMENT?

No court cases are listed for MANGAL MURTI APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of MANGAL MURTI APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PRAFULL SHANKARRAO AHIRE.

Other projects in pincode 422003

All 232 projects in Panchvati (422003) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.