Priyanka Blossom Apartment C Wing
by DHATRAK CONSTRUWELL · Sawarkar Nagar, NashikAlso near Gole Colony, Gandhi Nagar (Nashik), Trimurti Chowk
Possession date of Priyanka Blossom Apartment C Wing: 30 April 2030, moved from 31 December 2027 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600048879, and currently active. Its completion date has moved from December 2027 to April 2030: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Priyanka Blossom Apartment C Wing?
How the possession date of Priyanka Blossom Apartment C Wing has moved
31 December 2027
Completion date given when the project was registered
30 December 2029
Extended at the builder's request (MahaRERA application EA20112518386)
Reason the builder gave MahaRERA: “As per annexed letter”
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Priyanka Blossom Apartment C Wing’s extension records on MahaRERA (P51600048879), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Priyanka Blossom Apartment C Wing
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600048879
- Status
- Registered and active
- Builder
- DHATRAK CONSTRUWELL
- Location
- Sawarkar Nagar, Nashik · 422013
- Project type
- Residential / Group Housing
- Registered on
- 24 Jan 2023
- Completion date at registration
- December 2027
- Latest completion date
- April 2030
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 57
- Sold or booked
- 12%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Priyanka Blossom Apartment C Wing, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Priyanka Blossom Apartment C Wing | 100% | 81% | 50% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Priyanka Blossom Apartment C Wing: covers 23 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Priyanka Blossom Apartment C Wing every month.
Priyanka Blossom Apartment C Wing: buildings, flats and land, as filed on MahaRERA
- Buildings: Priyanka Blossom Apartment C Wing (23 floors, 57 units)
- Land: 3,139 sq m (about 0.8 acres) · sanctioned built-up 8,944 sq m
The builder’s record and reviews
Dhatrak Construwell has 3 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 1 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Priyanka Blossom Apartment C Wing →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Priyanka Blossom Apartment C Wing: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Priyanka Blossom Apartment C Wing
What is the possession date of Priyanka Blossom Apartment C Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Priyanka Blossom Apartment C Wing in Sawarkar Nagar, Nashik is 30 April 2030 — 24 months later than 31 December 2027, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Priyanka Blossom Apartment C Wing?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Priyanka Blossom Apartment C Wing's builder has filed on MahaRERA, the official one, is 30 April 2030, already 24 months later than the 31 December 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Priyanka Blossom Apartment C Wing extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Priyanka Blossom Apartment C Wing's builder applied to MahaRERA to extend the completion date once: to 30 December 2029, giving the reason "As per annexed letter". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Priyanka Blossom Apartment C Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Priyanka Blossom Apartment C Wing in Sawarkar Nagar, Nashik is P51600048879.
Is Priyanka Blossom Apartment C Wing registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Priyanka Blossom Apartment C Wing is registered as P51600048879 and its status is "Registered and active".
What is the construction status of Priyanka Blossom Apartment C Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), Priyanka Blossom Apartment C Wing's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Priyanka Blossom Apartment C Wing is 81% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does Priyanka Blossom Apartment C Wing have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Priyanka Blossom Apartment C Wing safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Priyanka Blossom Apartment C Wing is registered on MahaRERA as P51600048879, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Priyanka Blossom Apartment C Wing's possession date changes?
The latest dates are on Priyanka Blossom Apartment C Wing's MahaRERA page (P51600048879). GharKundli's Kundli Watch sends a free WhatsApp update on Priyanka Blossom Apartment C Wing every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Priyanka Blossom Apartment C Wing have?
According to GharKundli's check of MahaRERA records (updated October 2026), Priyanka Blossom Apartment C Wing has one building filed: Priyanka Blossom Apartment C Wing with 23 floors and 57 units.
How big is the land of Priyanka Blossom Apartment C Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), Priyanka Blossom Apartment C Wing stands on 3,139 sq m of land (about 0.8 acres), with 8,944 sq m of sanctioned built-up area.
What is the track record of Priyanka Blossom Apartment C Wing's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Dhatrak Construwell has 3 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 1 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Priyanka Blossom Apartment C Wing?
Google Maps has reviews of Priyanka Blossom Apartment C Wing written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Priyanka Blossom Apartment C Wing?
Priyanka Blossom Apartment C Wing by DHATRAK CONSTRUWELL is in Sawarkar Nagar, Nashik (pincode 422013), near Gole Colony, Gandhi Nagar (Nashik), Trimurti Chowk, Maharashtra, and is registered on MahaRERA as P51600048879, per GharKundli's check of MahaRERA records.
How many homes are in Priyanka Blossom Apartment C Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), Priyanka Blossom Apartment C Wing has 57 homes in 1 tower registered on MahaRERA, and 12% of them are sold or booked.
When was Priyanka Blossom Apartment C Wing registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Priyanka Blossom Apartment C Wing was registered on MahaRERA on 24 January 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Priyanka Blossom Apartment C Wing?
No court cases are listed for Priyanka Blossom Apartment C Wing on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Priyanka Blossom Apartment C Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DHATRAK CONSTRUWELL, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Priyanka Blossom Apartment C Wing
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Nashik →
Other projects in pincode 422013
- SAISHRUSHTI
- RIVIERA TOWER
- IRIS HEIGHTS
- VALENCIA RIVERSIDE APARTMENT
- ROONGTA EXQUISITE APARTMENT
- Gruhyog
- Yashoda Miracle
- SKY NIRVANA
Other projects by DHATRAK CONSTRUWELL
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.