SHIVBLISS
by RUSHI BUILDER & DEVELOPER · Bhandup, Mumbai
Possession: SHIVBLISS is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800011156. Status: Completed. 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHIVBLISS?
How the possession date of SHIVBLISS has moved
31 December 2018
Completion date given when the project was registered
30 April 2020
Extended at the builder's request (MahaRERA application EXT51800003797)
Reason the builder gave MahaRERA:
“Above project is registered on 31/08/2017 with the expected completion date of 31/12/2018. During the tenure of the project many unexpected hurdles arose which extended the proceedings a bit. Hence we wish to revise the proposed date of com…” Read the full reason
“Above project is registered on 31/08/2017 with the expected completion date of 31/12/2018. During the tenure of the project many unexpected hurdles arose which extended the proceedings a bit. Hence we wish to revise the proposed date of completion to 31/12/2019. Some of the hurdles causing the extension are: 1. There was litigation intiated by one of the tenant which stopped work during the period 2017-18. 2. Due to substantial delay in getting the litigation solved, SRA and other competent authorities delayed their approvals. 3. Due to rains, forcemajeure conditions and unexpected events o…”30 April 2020
Extended at the builder's request (MahaRERA application EXT51800005379)
Reason the builder gave MahaRERA: “Explanation & Reasons as per Explanation Application attached. Also Checkout Annexures to that supporting explanations are Reasons thereof”
30 June 2021
Extended at the builder's request (MahaRERA application EXT51800008805)
Reason the builder gave MahaRERA: “As Attached”
31 December 2023
Extended at the builder's request (MahaRERA application EXT51800011776)
Reason the builder gave MahaRERA:
“The project consists of 3 wings. Wing A is complete, OC is received and possession is also given. The unfinished work is for commercial units i.e Wing B & C. Extension is sought for completion of the said commercial wings which is wing B &…” Read the full reason
“The project consists of 3 wings. Wing A is complete, OC is received and possession is also given. The unfinished work is for commercial units i.e Wing B & C. Extension is sought for completion of the said commercial wings which is wing B & C. Extension due to ongoing uncertainity of COVID, Lockdown and after effects of the same on availability of material, labour, required permissions, etc.”31 December 2025
Extended at the builder's request (MahaRERA application EXT51800018688)
Reason the builder gave MahaRERA:
“The Project has been Delayed due to reasons given laid here before 1. Slow Processing of approvals & Permissions at SRA due to ongoing litigations, Complaints. 2. Demonetisation 3.labour, Material & Contractor problem leading to delay in co…” Read the full reason
“The Project has been Delayed due to reasons given laid here before 1. Slow Processing of approvals & Permissions at SRA due to ongoing litigations, Complaints. 2. Demonetisation 3.labour, Material & Contractor problem leading to delay in completing of pending work of commerecial wing due to COVID & pandemic effect. 4 Change in Developement Control Regulation 5. Introduction of GST 6. Extended Lockdown during second wave of Covid 6. Several Litigations & Obtaining Orders from Competent authorities etc.”
Source: SHIVBLISS’s extension records on MahaRERA (P51800011156), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHIVBLISS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800011156
- Status
- Completed
- Builder
- RUSHI BUILDER & DEVELOPER
- Location
- Bhandup, Mumbai · 400078
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2025
- Delay so far
- 84 months
- Homes
- 167
- Towers
- 1
- Complaints on MahaRERA
- 5
- Court cases listed
- 0
- Appeals at the tribunal
- 3
- Title report on file
- Not found
Construction progress of SHIVBLISS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHIVBLISS | 100% | 100% | 50% | 50% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHIVBLISS every month.
SHIVBLISS: buildings, flats and land, as filed on MahaRERA
- Buildings: SHIVBLISS (22 floors)
- Land: 3,275 sq m (about 0.8 acres) · sanctioned built-up 10,416 sq m · recreational space 491 sq m
The builder’s record and reviews
SO Lucky Builders (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 65 months). 6 complaints on MahaRERA across 2 projects.
Read Google reviews of SHIVBLISS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHIVBLISS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHIVBLISS
What is the possession date of SHIVBLISS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHIVBLISS in Bhandup, Mumbai is 31 December 2025 — 84 months later than 31 December 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SHIVBLISS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHIVBLISS's builder has filed on MahaRERA, the official one, is 31 December 2025, already 84 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHIVBLISS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVBLISS's builder applied to MahaRERA to extend the completion date 5 times: to 30 April 2020, giving the reason "Above project is registered on 31/08/2017 with the expected completion date of 31/12/2018. During the tenure of the project many unexpected hurdles arose which extended the proceedings a bit. Hence we wish to revise the proposed date of completion to 31/12/2019. Some of the hurdles causing the extension are: 1. There was litigation intiated by one of the tenant which stopped work during the period 2017-18. 2. Due to substantial delay in getting the litigation solved, SRA and other competent authorities delayed their approvals. 3. Due to rains, forcemajeure conditions and unexpected events o…"; to 30 April 2020, giving the reason "Explanation & Reasons as per Explanation Application attached. Also Checkout Annexures to that supporting explanations are Reasons thereof"; to 30 June 2021, giving the reason "As Attached"; to 31 December 2023, giving the reason "The project consists of 3 wings. Wing A is complete, OC is received and possession is also given. The unfinished work is for commercial units i.e Wing B & C. Extension is sought for completion of the said commercial wings which is wing B & C. Extension due to ongoing uncertainity of COVID, Lockdown and after effects of the same on availability of material, labour, required permissions, etc."; to 31 December 2025, giving the reason "The Project has been Delayed due to reasons given laid here before 1. Slow Processing of approvals & Permissions at SRA due to ongoing litigations, Complaints. 2. Demonetisation 3.labour, Material & Contractor problem leading to delay in completing of pending work of commerecial wing due to COVID & pandemic effect. 4 Change in Developement Control Regulation 5. Introduction of GST 6. Extended Lockdown during second wave of Covid 6. Several Litigations & Obtaining Orders from Competent authorities etc.".
What is the RERA number of SHIVBLISS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHIVBLISS in Bhandup, Mumbai is P51800011156.
Is SHIVBLISS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVBLISS is registered as P51800011156 and its status is "Completed".
What is the construction status of SHIVBLISS?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVBLISS's status on MahaRERA is "Completed". As filed by the builder, slab work on SHIVBLISS is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does SHIVBLISS have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHIVBLISS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVBLISS is registered on MahaRERA as P51800011156, its MahaRERA status is "Completed", its completion date has moved 84 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHIVBLISS's possession date changes?
The latest dates are on SHIVBLISS's MahaRERA page (P51800011156). GharKundli's Kundli Watch sends a free WhatsApp update on SHIVBLISS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHIVBLISS have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVBLISS has one building filed: SHIVBLISS with 22 floors.
How big is the land of SHIVBLISS?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVBLISS stands on 3,275 sq m of land (about 0.8 acres), with 10,416 sq m of sanctioned built-up area and 491 sq m of recreational open space.
What is the track record of SHIVBLISS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), SO Lucky Builders (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 65 months). 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHIVBLISS?
Google Maps has reviews of SHIVBLISS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHIVBLISS?
SHIVBLISS by RUSHI BUILDER & DEVELOPER is in Bhandup, Mumbai (pincode 400078), Maharashtra, and is registered on MahaRERA as P51800011156, per GharKundli's check of MahaRERA records.
How many homes are in SHIVBLISS?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVBLISS has 167 homes in 1 tower registered on MahaRERA.
When was SHIVBLISS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHIVBLISS was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SHIVBLISS?
No court cases are listed for SHIVBLISS on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SHIVBLISS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RUSHI BUILDER & DEVELOPER.
Check it yourself on MahaRERA
- How to check the possession date of SHIVBLISS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400078
- Runwal Forests Tower 9 - 11
- Horizon
- Valentina CHS
- Sugee Vaayu
- Godrej Nurture - Tower 2
- Godrej Nurture - Tower 3
- BHOOMI GREEN HILL
- Pandora by Shraddha
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.