SHREE GITARJUN
by INFINIA BUILDCON · Makhmalabad, NashikAlso near Panchvati
Possession date of SHREE GITARJUN: 25 December 2026. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600051247, and currently active. Its completion date is now December 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SHREE GITARJUN?
How the possession date of SHREE GITARJUN has moved
25 August 2026
Completion date given when the project was registered
25 December 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SHREE GITARJUN’s extension records on MahaRERA (P51600051247), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHREE GITARJUN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51600051247
- Status
- Registered and active
- Builder
- INFINIA BUILDCON
- Location
- Makhmalabad, Nashik · 422003
- Project type
- Residential / Group Housing
- Registered on
- 8 Jun 2023
- Completion date at registration
- August 2026
- Latest completion date
- December 2026
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 23
- Sold or booked
- 96%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHREE GITARJUN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHREE GITARJUN | 0% | 100% | 50% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE GITARJUN every month.
SHREE GITARJUN: buildings, flats and land, as filed on MahaRERA
- Buildings: SHREE GITARJUN (6 floors)
- Car parking: 11 covered
- Land: 491 sq m (about 0.1 acres) · sanctioned built-up 1,571 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHREE GITARJUN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHREE GITARJUN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHREE GITARJUN
What is the possession date of SHREE GITARJUN?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHREE GITARJUN in Makhmalabad, Nashik is 25 December 2026, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SHREE GITARJUN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE GITARJUN's builder has filed on MahaRERA, the official one, is 25 December 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SHREE GITARJUN?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHREE GITARJUN in Makhmalabad, Nashik is P51600051247.
Is SHREE GITARJUN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE GITARJUN is registered as P51600051247 and its status is "Registered and active".
What is the construction status of SHREE GITARJUN?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE GITARJUN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHREE GITARJUN is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does SHREE GITARJUN have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SHREE GITARJUN safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE GITARJUN is registered on MahaRERA as P51600051247, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHREE GITARJUN's possession date changes?
The latest dates are on SHREE GITARJUN's MahaRERA page (P51600051247). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE GITARJUN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHREE GITARJUN have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE GITARJUN has one building filed: SHREE GITARJUN with 6 floors.
How much parking does SHREE GITARJUN have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 11 covered car parking spaces for SHREE GITARJUN.
How big is the land of SHREE GITARJUN?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE GITARJUN stands on 491 sq m of land (about 0.1 acres), with 1,571 sq m of sanctioned built-up area.
Where can I read reviews of SHREE GITARJUN?
Google Maps has reviews of SHREE GITARJUN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHREE GITARJUN?
SHREE GITARJUN by INFINIA BUILDCON is in Makhmalabad, Nashik (pincode 422003), near Panchvati, Maharashtra, and is registered on MahaRERA as P51600051247, per GharKundli's check of MahaRERA records.
How many homes are in SHREE GITARJUN?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE GITARJUN has 23 homes in 1 tower registered on MahaRERA, and 96% of them are sold or booked.
When was SHREE GITARJUN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE GITARJUN was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SHREE GITARJUN?
No court cases are listed for SHREE GITARJUN on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SHREE GITARJUN?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is INFINIA BUILDCON.
Check it yourself on MahaRERA
- How to check the possession date of SHREE GITARJUN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Nashik →
Other projects in pincode 422003
- ALPINE
- Vastu Shilp
- SHIVSUNDAR HEIGHTS
- PADMASHREE PARK
- Saubhagya Pride
- SAMARTH DATTAKRUPA
- Amber Co. Op. Hsg. Soc.
- AKSHAR GARDEN
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.