ASHTAPAD PHASE VI
by ARKK BUILDERS AND DEVELOPERS · Belatgavhan, NashikAlso near Devlali
Possession date of ASHTAPAD PHASE VI: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51600051118, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about ASHTAPAD PHASE VI?
How the possession date of ASHTAPAD PHASE VI has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ASHTAPAD PHASE VI’s extension records on MahaRERA (P51600051118), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ASHTAPAD PHASE VI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- ASHTAPAD PHASE IIP51600025733
- ASHTAPAD PHASE IIIP51600028363
- ASHTAPAD PHASE VP51600045625
- ASHTAPAD PHASE VI BUILDING B C DP51600078513 · possession 30 Apr 2030
- ASHTAPAD PHASE VIIP51600078954 · possession 30 Apr 2030
- MahaRERA registration
- P51600051118
- Status
- Registered and active
- Builder
- ARKK BUILDERS AND DEVELOPERS
- Location
- Belatgavhan, Nashik · 422401
- Project type
- Residential / Group Housing
- Registered on
- 29 May 2023
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 108
- Towers
- 9
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of ASHTAPAD PHASE VI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A | 100% | 25% | 0% | 0% |
| BUILDING E | 0% | 0% | 0% | 0% |
| BUILDING F | 0% | 0% | 0% | 0% |
| BUILDING G | 100% | 80% | 20% | 0% |
| BUILDING H | 100% | 80% | 20% | 0% |
| BUILDING I | 100% | 80% | 20% | 0% |
| BUILDING J | 100% | 80% | 20% | 0% |
| BUILDING K | 100% | 80% | 20% | 0% |
| BUILDING L | 100% | 50% | 20% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ASHTAPAD PHASE VI every month.
ASHTAPAD PHASE VI: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING A (4 floors) · BUILDING E (4 floors) · BUILDING F (4 floors) · BUILDING G (4 floors) · BUILDING H (4 floors) · BUILDING I (4 floors) · BUILDING J (4 floors) · BUILDING K (4 floors) · and 1 more
- Land: 12,500 sq m (about 3.1 acres) · sanctioned built-up 8,250 sq m · recreational space 3,241 sq m
- Boundaries filed include: SHIV ROAD
The builder’s record and reviews
Arkk Builders AND Developers has 10 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of ASHTAPAD PHASE VI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ASHTAPAD PHASE VI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ASHTAPAD PHASE VI
What is the possession date of ASHTAPAD PHASE VI?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ASHTAPAD PHASE VI in Belatgavhan, Nashik is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ASHTAPAD PHASE VI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ASHTAPAD PHASE VI's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of ASHTAPAD PHASE VI?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ASHTAPAD PHASE VI in Belatgavhan, Nashik is P51600051118.
Is ASHTAPAD PHASE VI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ASHTAPAD PHASE VI is registered as P51600051118 and its status is "Registered and active".
What is the construction status of ASHTAPAD PHASE VI?
According to GharKundli's check of MahaRERA records (updated November 2026), ASHTAPAD PHASE VI's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 80% across 9 towers. GharKundli's full report compares construction progress with the deadline.
Does ASHTAPAD PHASE VI have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is ASHTAPAD PHASE VI safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ASHTAPAD PHASE VI is registered on MahaRERA as P51600051118, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does ASHTAPAD PHASE VI have other wings or phases?
Yes. MahaRERA lists 5 other registrations of the same project, each with its own possession date: ASHTAPAD PHASE II (P51600025733); ASHTAPAD PHASE III (P51600028363); ASHTAPAD PHASE V (P51600045625); ASHTAPAD PHASE VI BUILDING B C D (P51600078513, possession 30 Apr 2030); ASHTAPAD PHASE VII (P51600078954, possession 30 Apr 2030). Check that your agreement names the registration of your own wing.
How can I get updates if ASHTAPAD PHASE VI's possession date changes?
The latest dates are on ASHTAPAD PHASE VI's MahaRERA page (P51600051118). GharKundli's Kundli Watch sends a free WhatsApp update on ASHTAPAD PHASE VI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ASHTAPAD PHASE VI have?
According to GharKundli's check of MahaRERA records (updated November 2026), ASHTAPAD PHASE VI has 9 buildings filed: BUILDING A with 4 floors; BUILDING E with 4 floors; BUILDING F with 4 floors; BUILDING G with 4 floors; BUILDING H with 4 floors; BUILDING I with 4 floors; and 3 more.
How big is the land of ASHTAPAD PHASE VI?
According to GharKundli's check of MahaRERA records (updated November 2026), ASHTAPAD PHASE VI stands on 12,500 sq m of land (about 3.1 acres), with 8,250 sq m of sanctioned built-up area and 3,241 sq m of recreational open space.
What is the track record of ASHTAPAD PHASE VI's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Arkk Builders AND Developers has 10 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ASHTAPAD PHASE VI?
Google Maps has reviews of ASHTAPAD PHASE VI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ASHTAPAD PHASE VI?
ASHTAPAD PHASE VI by ARKK BUILDERS AND DEVELOPERS is in Belatgavhan, Nashik (pincode 422401), near Devlali, Maharashtra, and is registered on MahaRERA as P51600051118, per GharKundli's check of MahaRERA records. Its boundaries filed there include SHIV ROAD.
How many homes are in ASHTAPAD PHASE VI?
According to GharKundli's check of MahaRERA records (updated November 2026), ASHTAPAD PHASE VI has 108 homes in 9 towers registered on MahaRERA.
When was ASHTAPAD PHASE VI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ASHTAPAD PHASE VI was registered on MahaRERA on 29 May 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on ASHTAPAD PHASE VI?
No court cases are listed for ASHTAPAD PHASE VI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of ASHTAPAD PHASE VI?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ARKK BUILDERS AND DEVELOPERS, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ASHTAPAD PHASE VI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Nashik →
Other projects in pincode 422401
- Sai Nisarg
- SAI PARK
- TULASI BAUG
- SHRI KRISHNA ROW HOUSES
- KALAPURNAM PARK PHASE 2
- SHRI ANANT AVENUE
- SHRI RAM RESIDENCE PARK
- SHREE VISHVA
Other projects by ARKK BUILDERS AND DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.