Kalpavruksh Garden III
by Mahendra J Vora & Others · Kandivali West, MumbaiAlso near Borivali, Charkop, Bandra
Possession date of Kalpavruksh Garden III: 30 June 2021. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800007112. Status: Lapsed (registration period ended). 17 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (June 2021) has passed.
What do you want to know about Kalpavruksh Garden III?
GharKundli’s full report on Kalpavruksh Garden III
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 17 complaints and 1 court case, and how it ended
- Construction pace against the June 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007112
- Status
- Lapsed (registration period ended)
- Builder
- Mahendra J Vora & Others
- Location
- Kandivali West, Mumbai · 400067
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- June 2021
- Homes
- 177
- Towers
- 3
- Complaints on MahaRERA
- 17
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Kalpavruksh Garden III, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A Wing | 100% | 75% | 75% | 75% |
| B Wing | 100% | 75% | 75% | 75% |
| C Wing | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kalpavruksh Garden III every month.
Kalpavruksh Garden III: buildings, flats and land, as filed on MahaRERA
- Buildings: A Wing (25 floors) · B Wing (25 floors) · C Wing (30 floors)
- Land: 567 sq m (about 0.1 acres) · sanctioned built-up 5,517 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Balaji Construction (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 90 months late); 1 lapsed. 31 complaints on MahaRERA across 2 projects.
Read Google reviews of Kalpavruksh Garden III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kalpavruksh Garden III: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Kalpavruksh Garden III
What is the possession date of Kalpavruksh Garden III?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Kalpavruksh Garden III in Kandivali West, Mumbai is 30 June 2021. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Kalpavruksh Garden III?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kalpavruksh Garden III's builder has filed on MahaRERA, the official one, is 30 June 2021, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Kalpavruksh Garden III?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Kalpavruksh Garden III in Kandivali West, Mumbai is P51800007112.
Is Kalpavruksh Garden III registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Kalpavruksh Garden III is registered as P51800007112 and its status is "Lapsed (registration period ended)".
What is the construction status of Kalpavruksh Garden III?
According to GharKundli's check of MahaRERA records (updated November 2026), Kalpavruksh Garden III's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 75% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Kalpavruksh Garden III have complaints on MahaRERA?
17 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Kalpavruksh Garden III safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Kalpavruksh Garden III is registered on MahaRERA as P51800007112, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and 17 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Kalpavruksh Garden III's possession date changes?
The latest dates are on Kalpavruksh Garden III's MahaRERA page (P51800007112). GharKundli's Kundli Watch sends a free WhatsApp update on Kalpavruksh Garden III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kalpavruksh Garden III have?
According to GharKundli's check of MahaRERA records (updated November 2026), Kalpavruksh Garden III has 3 buildings filed: A Wing with 25 floors; B Wing with 25 floors; C Wing with 30 floors.
How big is the land of Kalpavruksh Garden III?
According to GharKundli's check of MahaRERA records (updated November 2026), Kalpavruksh Garden III stands on 567 sq m of land (about 0.1 acres), with 5,517 sq m of sanctioned built-up area.
What is the track record of Kalpavruksh Garden III's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Construction (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 90 months late); 1 lapsed. 31 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Kalpavruksh Garden III?
Google Maps has reviews of Kalpavruksh Garden III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 17 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Kalpavruksh Garden III?
Kalpavruksh Garden III by Mahendra J Vora & Others is in Kandivali West, Mumbai (pincode 400067), near Borivali, Charkop, Bandra, Maharashtra, and is registered on MahaRERA as P51800007112, per GharKundli's check of MahaRERA records.
How many homes are in Kalpavruksh Garden III?
According to GharKundli's check of MahaRERA records (updated November 2026), Kalpavruksh Garden III has 177 homes in 3 towers registered on MahaRERA.
When was Kalpavruksh Garden III registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Kalpavruksh Garden III was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Kalpavruksh Garden III?
1 court case is listed for Kalpavruksh Garden III on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Kalpavruksh Garden III?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Mahendra J Vora & Others.
Check it yourself on MahaRERA
- How to check the possession date of Kalpavruksh Garden III
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400067
- PRIME SQUARE
- LA SERENA Tower 5, Tower 6 and Tower 7
- CHARKOP SHREE GANESH CHS LTD
- MPR SHRI PARAS DARSHAN
- SAFFRONWOODS CHSL
- SIGMA AMBER
- Avenue Wing B phase 2
- JAYAKAR HOUSE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.