Possession date of Erectors Jaihind (MahaRERA P51800011367): 30 April 2028, moved from 31 December 2023 (48 months later). No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800011367, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800011367, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Erectors Jaihind?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Erectors Jaihind has moved

  1. 31 December 2023

    Completion date given when the project was registered

  2. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800016801)

    Reason the builder gave MahaRERA:
    “Dear Sir, With reference to the captioned subject, we would like to inform your goodself that our project ‘JAIHIND’ is registered on the MahaRERA webportal vide Registration Number: P51800011367. The registration certificate was issued for…” Read the full reason“Dear Sir, With reference to the captioned subject, we would like to inform your goodself that our project ‘JAIHIND’ is registered on the MahaRERA webportal vide Registration Number: P51800011367. The registration certificate was issued for the period ending 30 June 2024 (A copy of the certificate is attached herewith as Annexure 1). With reference to the above, we would like to inform you that there has been delay in obtaining various permissions required to complete the building. The plans will have to be amended as per DCPR 2034. We request you to extend the project completion date by a f…”
  3. 31 December 2027

    Extended at the builder's request (MahaRERA application EXT51800019874)

    Reason the builder gave MahaRERA: “Dear Sir, Please refer to the attached letter.”
  4. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Erectors Jaihind’s extension records on MahaRERA (P51800011367), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Erectors Jaihind

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800011367
Status
Registered and active
Builder
S.P. ERECTORS AND DEVELOPERS PRIVATE LIMITED
Location
Chembur, Mumbai · 400071
Project type
Others
Registered on
31 Aug 2017
Completion date at registration
December 2023
Latest completion date
April 2028
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of Erectors Jaihind, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
JAIHIND70%70%75%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Erectors Jaihind every 1–2 months.

Erectors Jaihind: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Erectors Jaihind →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Erectors Jaihind: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Erectors Jaihind

What is the possession date of Erectors Jaihind?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Erectors Jaihind in Chembur, Mumbai is 30 April 2028 — 48 months later than 31 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 48 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Erectors Jaihind?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Erectors Jaihind's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 31 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Erectors Jaihind extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Erectors Jaihind's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "Dear Sir, With reference to the captioned subject, we would like to inform your goodself that our project ‘JAIHIND’ is registered on the MahaRERA webportal vide Registration Number: P51800011367. The registration certificate was issued for the period ending 30 June 2024 (A copy of the certificate is attached herewith as Annexure 1). With reference to the above, we would like to inform you that there has been delay in obtaining various permissions required to complete the building. The plans will have to be amended as per DCPR 2034. We request you to extend the project completion date by a f…"; to 31 December 2027, giving the reason "Dear Sir, Please refer to the attached letter.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Erectors Jaihind?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Erectors Jaihind in Chembur, Mumbai is P51800011367.

Is Erectors Jaihind registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Erectors Jaihind is registered as P51800011367 and its status is "Registered and active".

What is the current construction status of Erectors Jaihind? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Erectors Jaihind's status on MahaRERA is "Registered and active". As filed by the builder, slab work on JAIHIND is 70% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.

Does Erectors Jaihind have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Erectors Jaihind safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Erectors Jaihind is registered on MahaRERA as P51800011367, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Erectors Jaihind?

Erectors Jaihind is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Erectors Jaihind?

For a flat in Erectors Jaihind (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Erectors Jaihind received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Erectors Jaihind is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Erectors Jaihind uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Erectors Jaihind was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Erectors Jaihind's possession date changes?

The latest dates are on Erectors Jaihind's MahaRERA page (P51800011367). GharKundli's Kundli Watch sends a free WhatsApp update on Erectors Jaihind every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Erectors Jaihind have?

According to GharKundli's check of MahaRERA records (updated October 2026), Erectors Jaihind has one building filed: JAIHIND with 14 floors.

How big is the land of Erectors Jaihind?

According to GharKundli's check of MahaRERA records (updated October 2026), Erectors Jaihind stands on 1,900 sq m of land (about 0.5 acres), with 3,026 sq m of sanctioned built-up area.

What are the reviews of Erectors Jaihind?

Google Maps has reviews of Erectors Jaihind written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Erectors Jaihind?

Erectors Jaihind by S.P. ERECTORS AND DEVELOPERS PRIVATE LIMITED is in Chembur, Mumbai, pincode 400071 (near Kurla, Ghatla, Bandra East), Maharashtra, and is registered on MahaRERA as P51800011367, per GharKundli's check of MahaRERA records. Its boundaries filed there include SCHEME ROAD, EASTERN EXPRESS HIGHWAY. Its land is filed as 553 PT. GharKundli lists all 318 MahaRERA projects in Chembur (400071).

When was Erectors Jaihind registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Erectors Jaihind was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Does Erectors Jaihind have any legal issues or court cases?

1 court case is listed for Erectors Jaihind on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Erectors Jaihind?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is S.P. ERECTORS AND DEVELOPERS PRIVATE LIMITED.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Chembur (400071)

All 318 projects in Chembur (400071) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.