Possession: TRANQUIL BAY is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900003689. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about TRANQUIL BAY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of TRANQUIL BAY has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2019

    Extended at the builder's request (MahaRERA application EXT51900000994)

    Reason the builder gave MahaRERA:
    “We have constructed the building “Tranquil Bay” consists of Stilt, 1st floor podium parking and 2nd to 18th floor and part 19th floor as habitable floors. The building is complete in all aspects and Part Occupancy Certificate bearing No.EB/…” Read the full reason“We have constructed the building “Tranquil Bay” consists of Stilt, 1st floor podium parking and 2nd to 18th floor and part 19th floor as habitable floors. The building is complete in all aspects and Part Occupancy Certificate bearing No.EB/3281/GN/A dated 18th December 2017 from MCGM is obtained upto 11th floor. We are now in the process of obtaining CFO NOC and permissions from other authorities with a view to obtain Full Occupation Certificate. The delay in giving possession of the remaining flats to clients from 10th to 19th floor is due to compliance of IOD conditions of MCGM for issuan…”

Source: TRANQUIL BAY’s extension records on MahaRERA (P51900003689), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TRANQUIL BAY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the December 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900003689
Status
Completed
Builder
SURAJ ESTATE DEVELOPERS LTD
Location
Mari Nagar Mahim, Mumbai · 400028
Project type
Residential / Group Housing
Registered on
6 Aug 2017
Completion date at registration
December 2018
Latest completion date
December 2019
Delay so far
12 months
Homes
23
Towers
1
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
14

Construction progress of TRANQUIL BAY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TRANQUIL BAY100%100%80%80%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TRANQUIL BAY every month.

TRANQUIL BAY: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Suraj Estate Developers (a group of 5 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 6 finished, 0 within the promised date and 6 needed more time (typically 12 months); 11 still being built, 4 past the promised date (typically 15 months late); 1 lapsed. 10 complaints on MahaRERA across 6 projects.

Read Google reviews of TRANQUIL BAY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TRANQUIL BAY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TRANQUIL BAY

What is the possession date of TRANQUIL BAY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for TRANQUIL BAY in Mari Nagar Mahim, Mumbai is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for TRANQUIL BAY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TRANQUIL BAY's builder has filed on MahaRERA, the official one, is 31 December 2019, already 12 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TRANQUIL BAY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), TRANQUIL BAY's builder applied to MahaRERA to extend the completion date once: to 31 December 2019, giving the reason "We have constructed the building “Tranquil Bay” consists of Stilt, 1st floor podium parking and 2nd to 18th floor and part 19th floor as habitable floors. The building is complete in all aspects and Part Occupancy Certificate bearing No.EB/3281/GN/A dated 18th December 2017 from MCGM is obtained upto 11th floor. We are now in the process of obtaining CFO NOC and permissions from other authorities with a view to obtain Full Occupation Certificate. The delay in giving possession of the remaining flats to clients from 10th to 19th floor is due to compliance of IOD conditions of MCGM for issuan…".

What is the RERA number of TRANQUIL BAY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of TRANQUIL BAY in Mari Nagar Mahim, Mumbai is P51900003689.

Is TRANQUIL BAY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), TRANQUIL BAY is registered as P51900003689 and its status is "Completed".

What is the construction status of TRANQUIL BAY?

According to GharKundli's check of MahaRERA records (updated November 2026), TRANQUIL BAY's status on MahaRERA is "Completed". As filed by the builder, slab work on TRANQUIL BAY is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does TRANQUIL BAY have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is TRANQUIL BAY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), TRANQUIL BAY is registered on MahaRERA as P51900003689, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if TRANQUIL BAY's possession date changes?

The latest dates are on TRANQUIL BAY's MahaRERA page (P51900003689). GharKundli's Kundli Watch sends a free WhatsApp update on TRANQUIL BAY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TRANQUIL BAY have?

According to GharKundli's check of MahaRERA records (updated November 2026), TRANQUIL BAY has one building filed: TRANQUIL BAY with 23 floors.

How big is the land of TRANQUIL BAY?

According to GharKundli's check of MahaRERA records (updated November 2026), TRANQUIL BAY stands on 796 sq m of land (about 0.2 acres), with 2,425 sq m of sanctioned built-up area.

What is the track record of TRANQUIL BAY's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Suraj Estate Developers (a group of 5 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 6 finished, 0 within the promised date and 6 needed more time (typically 12 months); 11 still being built, 4 past the promised date (typically 15 months late); 1 lapsed. 10 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of TRANQUIL BAY?

Google Maps has reviews of TRANQUIL BAY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TRANQUIL BAY?

TRANQUIL BAY by SURAJ ESTATE DEVELOPERS LTD is in Mari Nagar Mahim, Mumbai (pincode 400028), near Dadar West, Prabhadevi, Shivaji Park, Maharashtra, and is registered on MahaRERA as P51900003689, per GharKundli's check of MahaRERA records. Its boundaries filed there include KASHINATH DHURU ROAD.

How many homes are in TRANQUIL BAY?

According to GharKundli's check of MahaRERA records (updated November 2026), TRANQUIL BAY has 23 homes in 1 tower registered on MahaRERA.

When was TRANQUIL BAY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), TRANQUIL BAY was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on TRANQUIL BAY?

1 court case is listed for TRANQUIL BAY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of TRANQUIL BAY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SURAJ ESTATE DEVELOPERS LTD, which has 14 other projects registered on MahaRERA.

Other projects in Mari Nagar Mahim

All 148 projects in Dadar West (400028) →

Other projects by SURAJ ESTATE DEVELOPERS LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.