Suraj Ave Maria Apartment
by SURAJ ESTATE DEVELOPERS LTD · Agar Bazar, Mumbai 400028Registered on MahaRERA as “Ave Maria Apartment”
What’s in the report? →Possession date of Suraj Ave Maria Apartment (MahaRERA P51900021954): 31 December 2025, moved from 30 December 2024 (12 months later), and it has already passed. It has 179 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900021954. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51900021954, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Suraj Ave Maria Apartment?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Suraj Ave Maria Apartment has moved
30 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51900025841)
Reason the builder gave MahaRERA:
“26th December, 2024 The Chairman MahaRERA, Bandra (East), Mumbai – 400 051 Dear Sir, Sub.: Redevelopment of property known as “Ave Maria” on property bearing F.P. 822, TPS IV of Mahim Division, situate at S.K.Bole Road, Dadar (West), Mumbai…” Read the full reason
“26th December, 2024 The Chairman MahaRERA, Bandra (East), Mumbai – 400 051 Dear Sir, Sub.: Redevelopment of property known as “Ave Maria” on property bearing F.P. 822, TPS IV of Mahim Division, situate at S.K.Bole Road, Dadar (West), Mumbai – 400 028. We have registered our above project known as “Ave Maria” vide registration No.P51900021954. The completion date as per the Certificate is 31st December, 2024. The construction work of the project is fully complete and we have obtained NOC from MHADA for issuance of OC. Accordingly, we have shifted existing tenants/occupants to their respectiv…”
Source: Suraj Ave Maria Apartment’s extension records on MahaRERA (P51900021954), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Suraj Ave Maria Apartment
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 court cases, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900021954
- Status
- Lapsed (registration period ended)
- Builder
- SURAJ ESTATE DEVELOPERS LTD
- Location
- Agar Bazar, Mumbai · 400028
- Project type
- Residential / Group Housing
- Registered on
- 25 Aug 2019
- Completion date at registration
- December 2024
- Latest completion date
- December 2025
- Delay so far
- 12 months
- Homes
- 179
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 14
Construction progress of Suraj Ave Maria Apartment, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Ave Maria Apartment | 100% | 100% | 100% | 98% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Suraj Ave Maria Apartment every 1–2 months.
Suraj Ave Maria Apartment: buildings, flats and land, as filed on MahaRERA
- Buildings: Ave Maria Apartment (31 floors)
- Land: 1,698 sq m (about 0.4 acres) · sanctioned built-up 6,799 sq m · recreational space 327 sq m
- Land, as filed: F P 822
- Map: Get directions
The builder’s record and reviews
Suraj Estate Developers (a group of 5 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 6 finished, 0 within the promised date and 6 needed more time (typically 12 months); 11 still being built, 4 past the promised date (typically 15 months late); 1 lapsed. 10 complaints on MahaRERA across 6 projects.
Read Google reviews of Suraj Ave Maria Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Suraj Ave Maria Apartment: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Suraj Ave Maria Apartment
What is the possession date of Suraj Ave Maria Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Suraj Ave Maria Apartment in Agar Bazar, Mumbai is 31 December 2025 — 12 months later than 30 December 2024, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Suraj Ave Maria Apartment?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Suraj Ave Maria Apartment's builder has filed on MahaRERA, the official one, is 31 December 2025, already 12 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Suraj Ave Maria Apartment extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Ave Maria Apartment's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "26th December, 2024 The Chairman MahaRERA, Bandra (East), Mumbai – 400 051 Dear Sir, Sub.: Redevelopment of property known as “Ave Maria” on property bearing F.P. 822, TPS IV of Mahim Division, situate at S.K.Bole Road, Dadar (West), Mumbai – 400 028. We have registered our above project known as “Ave Maria” vide registration No.P51900021954. The completion date as per the Certificate is 31st December, 2024. The construction work of the project is fully complete and we have obtained NOC from MHADA for issuance of OC. Accordingly, we have shifted existing tenants/occupants to their respectiv…".
What is the RERA number of Suraj Ave Maria Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Suraj Ave Maria Apartment in Agar Bazar, Mumbai is P51900021954.
Is Suraj Ave Maria Apartment registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Ave Maria Apartment is registered as P51900021954 and its status is "Lapsed (registration period ended)".
What is the current construction status of Suraj Ave Maria Apartment? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Ave Maria Apartment's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Ave Maria Apartment is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Suraj Ave Maria Apartment have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Suraj Ave Maria Apartment safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Ave Maria Apartment is registered on MahaRERA as P51900021954, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Suraj Ave Maria Apartment?
Suraj Ave Maria Apartment isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Suraj Ave Maria Apartment?
For a flat in Suraj Ave Maria Apartment (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Suraj Ave Maria Apartment received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Ave Maria Apartment isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Suraj Ave Maria Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Ave Maria Apartment's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Suraj Ave Maria Apartment uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Suraj Ave Maria Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Suraj Ave Maria Apartment's possession date changes?
The latest dates are on Suraj Ave Maria Apartment's MahaRERA page (P51900021954). GharKundli's Kundli Watch sends a free WhatsApp update on Suraj Ave Maria Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Suraj Ave Maria Apartment have?
According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Ave Maria Apartment has one building filed: Ave Maria Apartment with 31 floors.
How big is the land of Suraj Ave Maria Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Ave Maria Apartment stands on 1,698 sq m of land (about 0.4 acres), with 6,799 sq m of sanctioned built-up area and 327 sq m of recreational open space.
What is the track record of Suraj Ave Maria Apartment's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Estate Developers (a group of 5 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 6 finished, 0 within the promised date and 6 needed more time (typically 12 months); 11 still being built, 4 past the promised date (typically 15 months late); 1 lapsed. 10 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Suraj Ave Maria Apartment?
Google Maps has reviews of Suraj Ave Maria Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Suraj Ave Maria Apartment?
Suraj Ave Maria Apartment by SURAJ ESTATE DEVELOPERS LTD is in Agar Bazar, Mumbai, pincode 400028, Maharashtra, and is registered on MahaRERA as P51900021954, per GharKundli's check of MahaRERA records. Its land is filed as F P 822. GharKundli lists all 148 MahaRERA projects in Dadar West (400028).
How many flats are in Suraj Ave Maria Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Ave Maria Apartment has 179 homes in 1 tower registered on MahaRERA.
When was Suraj Ave Maria Apartment registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Ave Maria Apartment was registered on MahaRERA on 25 August 2019. GharKundli did not find a title report on the land on file there.
Does Suraj Ave Maria Apartment have any legal issues or court cases?
3 court cases are listed for Suraj Ave Maria Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Suraj Ave Maria Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SURAJ ESTATE DEVELOPERS LTD, which has 14 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Suraj Ave Maria Apartment
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ward GNorth
All 148 projects in Dadar West (400028) →Other projects by SURAJ ESTATE DEVELOPERS LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.