by SURAJ ESTATE DEVELOPERS LTD · Mari Nagar Mahim, Mumbai 400028Also near Dadar West, Prabhadevi, Shivaji ParkRegistered on MahaRERA as “LOUISANDRA”

What’s in the report? →

Possession date of Suraj Louisandra (MahaRERA P51900010078): 30 June 2025, moved from 30 June 2022 (36 months later), and it has already passed. It has 72 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900010078. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51900010078, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2025) has passed.

What do you want to know about Suraj Louisandra?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Suraj Louisandra has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51900012062)

    Reason the builder gave MahaRERA:
    “REASONS FOR EXTENTION OF DATE OF POSSESSION At the time of RERA Registration of the above project, the original approved plans of the project consisted of Gr. + 4 upper storey + 5 (part) approved vide IOD No. EB/5940/GN/A dated 03/09/2015 u…” Read the full reason“REASONS FOR EXTENTION OF DATE OF POSSESSION At the time of RERA Registration of the above project, the original approved plans of the project consisted of Gr. + 4 upper storey + 5 (part) approved vide IOD No. EB/5940/GN/A dated 03/09/2015 utilizing the FSI available under Regulation 33(7) of DCR 1991. Thereafter, after the implementation of DCPR 2034, the plan was amended therein utilizing the potential of Regulation 33(7) and Regulation 33(12) of DCPR 2034 and accordingly, amended plans + IOD for Gr. + 22 upper floors were issued by MCGM vide No. EB/5940/GN/A/IOD/1/New dated 07/11/2019. Fu…”
  3. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51900016979)

    Reason the builder gave MahaRERA:
    “Due to delay in obtaining approvals and C.C., we are not in a position to complete the project by 30/06/2023. We request you to grant us the extension for 1 more year i.e. from 30/06/2023 to 30/06/2024. We have uploaded the consent of 51% o…” Read the full reason“Due to delay in obtaining approvals and C.C., we are not in a position to complete the project by 30/06/2023. We request you to grant us the extension for 1 more year i.e. from 30/06/2023 to 30/06/2024. We have uploaded the consent of 51% of the sold flat purchasers.”
  4. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51900025459)

    Reason the builder gave MahaRERA:
    “To, The Chairman, MahaRERA, Bandra, Mumbai. Dear Sir, Sub.: Reason for extension of date of possession We have registered our building “LOUISANDRA” with MahaRERA vide registration No. P51900010078. At the time of RERA registration of the sa…” Read the full reason“To, The Chairman, MahaRERA, Bandra, Mumbai. Dear Sir, Sub.: Reason for extension of date of possession We have registered our building “LOUISANDRA” with MahaRERA vide registration No. P51900010078. At the time of RERA registration of the said building, the original approved plans of the said building consisted of part basement + ground floor + 22 upper floors approved vide IOD No. EB/5940/GN/A/337/1 dated 07/11/2019 utilizing the FSI available under Regulation 33(7) & 33(12) of DCPR 2034. We have also received part Occupation Certificate after due compliance of conditions. However, the comm…”

Source: Suraj Louisandra’s extension records on MahaRERA (P51900010078), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Suraj Louisandra

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900010078
Status
Lapsed (registration period ended)
Builder
SURAJ ESTATE DEVELOPERS LTD
Location
Mari Nagar Mahim, Mumbai · 400028
Project type
Others
Registered on
23 Aug 2017
Completion date at registration
June 2022
Latest completion date
June 2025
Delay so far
36 months
Homes
72
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
14

Construction progress of Suraj Louisandra, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LUISANDRA100%100%100%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Suraj Louisandra every 1–2 months.

Suraj Louisandra: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Suraj Estate Developers (a group of 5 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 6 finished, 0 within the promised date and 6 needed more time (typically 12 months); 11 still being built, 4 past the promised date (typically 15 months late); 1 lapsed. 10 complaints on MahaRERA across 6 projects.

Read Google reviews of Suraj Louisandra →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Suraj Louisandra: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Suraj Louisandra

What is the possession date of Suraj Louisandra?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Suraj Louisandra in Mari Nagar Mahim, Mumbai is 30 June 2025 — 36 months later than 30 June 2022, the date given at registration. That date has already passed.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Suraj Louisandra?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Suraj Louisandra's builder has filed on MahaRERA, the official one, is 30 June 2025, already 36 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Suraj Louisandra extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Louisandra's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2023, giving the reason "REASONS FOR EXTENTION OF DATE OF POSSESSION At the time of RERA Registration of the above project, the original approved plans of the project consisted of Gr. + 4 upper storey + 5 (part) approved vide IOD No. EB/5940/GN/A dated 03/09/2015 utilizing the FSI available under Regulation 33(7) of DCR 1991. Thereafter, after the implementation of DCPR 2034, the plan was amended therein utilizing the potential of Regulation 33(7) and Regulation 33(12) of DCPR 2034 and accordingly, amended plans + IOD for Gr. + 22 upper floors were issued by MCGM vide No. EB/5940/GN/A/IOD/1/New dated 07/11/2019. Fu…"; to 30 June 2024, giving the reason "Due to delay in obtaining approvals and C.C., we are not in a position to complete the project by 30/06/2023. We request you to grant us the extension for 1 more year i.e. from 30/06/2023 to 30/06/2024. We have uploaded the consent of 51% of the sold flat purchasers."; to 30 June 2025, giving the reason "To, The Chairman, MahaRERA, Bandra, Mumbai. Dear Sir, Sub.: Reason for extension of date of possession We have registered our building “LOUISANDRA” with MahaRERA vide registration No. P51900010078. At the time of RERA registration of the said building, the original approved plans of the said building consisted of part basement + ground floor + 22 upper floors approved vide IOD No. EB/5940/GN/A/337/1 dated 07/11/2019 utilizing the FSI available under Regulation 33(7) & 33(12) of DCPR 2034. We have also received part Occupation Certificate after due compliance of conditions. However, the comm…".

What is the RERA number of Suraj Louisandra?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Suraj Louisandra in Mari Nagar Mahim, Mumbai is P51900010078.

Is Suraj Louisandra registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Louisandra is registered as P51900010078 and its status is "Lapsed (registration period ended)".

What is the current construction status of Suraj Louisandra? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Louisandra's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on LUISANDRA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Suraj Louisandra have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Suraj Louisandra safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Louisandra is registered on MahaRERA as P51900010078, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Suraj Louisandra?

Suraj Louisandra isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Suraj Louisandra?

For a flat in Suraj Louisandra (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Suraj Louisandra received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Louisandra isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Suraj Louisandra?

According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Louisandra's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Suraj Louisandra uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Suraj Louisandra was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Suraj Louisandra's possession date changes?

The latest dates are on Suraj Louisandra's MahaRERA page (P51900010078). GharKundli's Kundli Watch sends a free WhatsApp update on Suraj Louisandra every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Suraj Louisandra have?

According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Louisandra has one building filed: LUISANDRA with 23 floors.

How big is the land of Suraj Louisandra?

According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Louisandra stands on 2,783 sq m of land (about 0.7 acres), with 526 sq m of sanctioned built-up area.

What is the track record of Suraj Louisandra's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Estate Developers (a group of 5 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 6 finished, 0 within the promised date and 6 needed more time (typically 12 months); 11 still being built, 4 past the promised date (typically 15 months late); 1 lapsed. 10 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Suraj Louisandra?

Google Maps has reviews of Suraj Louisandra written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Suraj Louisandra?

Suraj Louisandra by SURAJ ESTATE DEVELOPERS LTD is in Mari Nagar Mahim, Mumbai, pincode 400028 (near Dadar West, Prabhadevi, Shivaji Park), Maharashtra, and is registered on MahaRERA as P51900010078, per GharKundli's check of MahaRERA records. Its boundaries filed there include S K BOLE ROAD, BANK OF MAHARASHTRA, GOKHALE ROAD. Its land is filed as FP NO 1/274. GharKundli lists all 148 MahaRERA projects in Dadar West (400028).

How many flats are in Suraj Louisandra?

According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Louisandra has 72 homes in 1 tower registered on MahaRERA.

When was Suraj Louisandra registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Louisandra was registered on MahaRERA on 23 August 2017. GharKundli did not find a title report on the land on file there.

Does Suraj Louisandra have any legal issues or court cases?

No court cases are listed for Suraj Louisandra on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Suraj Louisandra?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SURAJ ESTATE DEVELOPERS LTD, which has 14 other projects registered on MahaRERA.

Other projects in Dadar West (400028)

All 148 projects in Dadar West (400028) →

Other projects by SURAJ ESTATE DEVELOPERS LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.