CCIL Bhavan
by SURAJ ESTATE DEVELOPERS LTD · Agar Bazar, MumbaiAlso near Dadar West, Shivaji Park, Prabhadevi
Possession date of CCIL Bhavan: 31 December 2027, moved from 30 December 2024 (32 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900021953, and currently active. Its completion date has moved from December 2024 to December 2027: 32 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about CCIL Bhavan?
How the possession date of CCIL Bhavan has moved
30 December 2024
Completion date given when the project was registered
4 June 2026
Extended at the builder's request (MahaRERA application EXT51900025840)
Reason the builder gave MahaRERA:
“We have registered our project known as "CCIL Bhavan" under registration No. P51900021953. The completion date as per the certificate is 30th December, 2024. This project envisages the addition of 3 floors over an existing commercial buildi…” Read the full reason
“We have registered our project known as "CCIL Bhavan" under registration No. P51900021953. The completion date as per the certificate is 30th December, 2024. This project envisages the addition of 3 floors over an existing commercial building of Ground + 6 floors. We have earlier obtained the occupation certificate for the existing building up to 6th floor on 13th February, 2012 ( O.C copy attached in other technical tab). We have received the commencement certificate from BMC on 2nd May, 2024 and same is revalidated up to 07.12.2025 (Revalidation letter attached in CC Tab) and the actual c…”31 August 2027
Extended at the builder's request (MahaRERA application EA28072621896)
Reason the builder gave MahaRERA:
“Sub.: Redevelopment of property known as "CCIL Bhavan" on property bearing F.P. 822, TPS IV of Mahim Division, situate at S.K.Bole Road, Dadar (West), Mumbai - 400 028. We have registered our project known as "CCIL Bhavan" under registratio…” Read the full reason
“Sub.: Redevelopment of property known as "CCIL Bhavan" on property bearing F.P. 822, TPS IV of Mahim Division, situate at S.K.Bole Road, Dadar (West), Mumbai - 400 028. We have registered our project known as "CCIL Bhavan" under registration No.P51900021953. The completion date as per the certificate is 4th June,2026. This project envisages the addition of 3 floors over an existing commercial building of Ground + 6 floors. We have received the Commencement Certificate from BMC on 2nd May, 2024 and the construction work could only commence after the cessation of the monsoon season i.e. in th…”31 December 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: CCIL Bhavan’s extension records on MahaRERA (P51900021953), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on CCIL Bhavan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 court cases, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900021953
- Status
- Registered and active
- Builder
- SURAJ ESTATE DEVELOPERS LTD
- Location
- Agar Bazar, Mumbai · 400028
- Project type
- Commercial
- Registered on
- 25 Aug 2019
- Completion date at registration
- December 2024
- Latest completion date
- December 2027
- Delay so far
- 32 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 5
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 14
Construction progress of CCIL Bhavan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CCIL BHAVAN | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- CCIL BHAVAN: covers CC Issued upto 8th floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on CCIL Bhavan every month.
CCIL Bhavan: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 4,368 – 7,412 | 3 |
- Buildings: CCIL BHAVAN (3 floors, 3 units)
- Land: 2,325 sq m (about 0.6 acres) · sanctioned built-up 1,285 sq m · recreational space 327 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Suraj Estate Developers (a group of 5 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 6 finished, 0 within the promised date and 6 needed more time (typically 12 months); 11 still being built, 4 past the promised date (typically 15 months late); 1 lapsed. 10 complaints on MahaRERA across 6 projects.
Read Google reviews of CCIL Bhavan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
CCIL Bhavan: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about CCIL Bhavan
What is the possession date of CCIL Bhavan?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for CCIL Bhavan in Agar Bazar, Mumbai is 31 December 2027 — 32 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for CCIL Bhavan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date CCIL Bhavan's builder has filed on MahaRERA, the official one, is 31 December 2027, already 32 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of CCIL Bhavan extended?
According to GharKundli's check of MahaRERA records (updated October 2026), CCIL Bhavan's builder applied to MahaRERA to extend the completion date 2 times: to 4 June 2026, giving the reason "We have registered our project known as "CCIL Bhavan" under registration No. P51900021953. The completion date as per the certificate is 30th December, 2024. This project envisages the addition of 3 floors over an existing commercial building of Ground + 6 floors. We have earlier obtained the occupation certificate for the existing building up to 6th floor on 13th February, 2012 ( O.C copy attached in other technical tab). We have received the commencement certificate from BMC on 2nd May, 2024 and same is revalidated up to 07.12.2025 (Revalidation letter attached in CC Tab) and the actual c…"; to 31 August 2027, giving the reason "Sub.: Redevelopment of property known as "CCIL Bhavan" on property bearing F.P. 822, TPS IV of Mahim Division, situate at S.K.Bole Road, Dadar (West), Mumbai - 400 028. We have registered our project known as "CCIL Bhavan" under registration No.P51900021953. The completion date as per the certificate is 4th June,2026. This project envisages the addition of 3 floors over an existing commercial building of Ground + 6 floors. We have received the Commencement Certificate from BMC on 2nd May, 2024 and the construction work could only commence after the cessation of the monsoon season i.e. in th…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of CCIL Bhavan?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of CCIL Bhavan in Agar Bazar, Mumbai is P51900021953.
Is CCIL Bhavan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), CCIL Bhavan is registered as P51900021953 and its status is "Registered and active".
What is the construction status of CCIL Bhavan?
According to GharKundli's check of MahaRERA records (updated October 2026), CCIL Bhavan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on CCIL BHAVAN is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does CCIL Bhavan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is CCIL Bhavan safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), CCIL Bhavan is registered on MahaRERA as P51900021953, its completion date has moved 32 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if CCIL Bhavan's possession date changes?
The latest dates are on CCIL Bhavan's MahaRERA page (P51900021953). GharKundli's Kundli Watch sends a free WhatsApp update on CCIL Bhavan every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does CCIL Bhavan have?
According to GharKundli's check of MahaRERA records (updated October 2026), CCIL Bhavan has one building filed: CCIL BHAVAN with 3 floors and 3 units.
How big is the land of CCIL Bhavan?
According to GharKundli's check of MahaRERA records (updated October 2026), CCIL Bhavan stands on 2,325 sq m of land (about 0.6 acres), with 1,285 sq m of sanctioned built-up area and 327 sq m of recreational open space.
What is the track record of CCIL Bhavan's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Suraj Estate Developers (a group of 5 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 6 finished, 0 within the promised date and 6 needed more time (typically 12 months); 11 still being built, 4 past the promised date (typically 15 months late); 1 lapsed. 10 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of CCIL Bhavan?
Google Maps has reviews of CCIL Bhavan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is CCIL Bhavan?
CCIL Bhavan by SURAJ ESTATE DEVELOPERS LTD is in Agar Bazar, Mumbai (pincode 400028), near Dadar West, Shivaji Park, Prabhadevi, Maharashtra, and is registered on MahaRERA as P51900021953, per GharKundli's check of MahaRERA records.
How many homes are in CCIL Bhavan?
According to GharKundli's check of MahaRERA records (updated October 2026), CCIL Bhavan has 0 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was CCIL Bhavan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), CCIL Bhavan was registered on MahaRERA on 25 August 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on CCIL Bhavan?
5 court cases are listed for CCIL Bhavan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of CCIL Bhavan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SURAJ ESTATE DEVELOPERS LTD, which has 14 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of CCIL Bhavan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Ward GNorth
- Ave Maria Apartment
- Ratan Address
- Sanghvi Morya
- ARYAVRAT PROJECT
- YASH TRINITY
- MANIKYA
- Sugee Vrundavan
- ANJ ANANDA
Other projects by SURAJ ESTATE DEVELOPERS LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.