SURAJ PARK VIEW 2
by SURAJ ESTATE DEVELOPERS LTD · Dadar West, MumbaiAlso near Shivaji Park, Prabhadevi, Mahim
Possession date of SURAJ PARK VIEW 2: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900047891, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SURAJ PARK VIEW 2?
How the possession date of SURAJ PARK VIEW 2 has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SURAJ PARK VIEW 2’s extension records on MahaRERA (P51900047891), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SURAJ PARK VIEW 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 4 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- SURAJ PARK VIEW 1PR1170002500887 · possession 30 Apr 2032
- MahaRERA registration
- P51900047891
- Status
- Registered and active
- Builder
- SURAJ ESTATE DEVELOPERS LTD
- Location
- Dadar West, Mumbai · 400028
- Project type
- Residential / Group Housing
- Registered on
- 1 Dec 2022
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 72
- Sold or booked
- 91%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 4
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 14
Construction progress of SURAJ PARK VIEW 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 2 | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 2: covers Full CC
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SURAJ PARK VIEW 2 every month.
SURAJ PARK VIEW 2: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 2 (24 floors, 72 units)
- Land: 2,271 sq m (about 0.6 acres) · sanctioned built-up 3,419 sq m · recreational space 227 sq m
- Boundaries filed include: ANANT PATIL MARG
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Suraj Estate Developers (a group of 5 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 6 finished, 0 within the promised date and 6 needed more time (typically 12 months); 11 still being built, 4 past the promised date (typically 15 months late); 1 lapsed. 10 complaints on MahaRERA across 6 projects.
Read Google reviews of SURAJ PARK VIEW 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SURAJ PARK VIEW 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SURAJ PARK VIEW 2
What is the possession date of SURAJ PARK VIEW 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SURAJ PARK VIEW 2 in Dadar West, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SURAJ PARK VIEW 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SURAJ PARK VIEW 2's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SURAJ PARK VIEW 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SURAJ PARK VIEW 2 in Dadar West, Mumbai is P51900047891.
Is SURAJ PARK VIEW 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SURAJ PARK VIEW 2 is registered as P51900047891 and its status is "Registered and active".
What is the construction status of SURAJ PARK VIEW 2?
According to GharKundli's check of MahaRERA records (updated November 2026), SURAJ PARK VIEW 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING NO 2 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SURAJ PARK VIEW 2 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SURAJ PARK VIEW 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SURAJ PARK VIEW 2 is registered on MahaRERA as P51900047891, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does SURAJ PARK VIEW 2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SURAJ PARK VIEW 1 (PR1170002500887, possession 30 Apr 2032). Check that your agreement names the registration of your own wing.
How can I get updates if SURAJ PARK VIEW 2's possession date changes?
The latest dates are on SURAJ PARK VIEW 2's MahaRERA page (P51900047891). GharKundli's Kundli Watch sends a free WhatsApp update on SURAJ PARK VIEW 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SURAJ PARK VIEW 2 have?
According to GharKundli's check of MahaRERA records (updated November 2026), SURAJ PARK VIEW 2 has one building filed: BUILDING NO 2 with 24 floors and 72 units.
How big is the land of SURAJ PARK VIEW 2?
According to GharKundli's check of MahaRERA records (updated November 2026), SURAJ PARK VIEW 2 stands on 2,271 sq m of land (about 0.6 acres), with 3,419 sq m of sanctioned built-up area and 227 sq m of recreational open space.
What is the track record of SURAJ PARK VIEW 2's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Suraj Estate Developers (a group of 5 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 6 finished, 0 within the promised date and 6 needed more time (typically 12 months); 11 still being built, 4 past the promised date (typically 15 months late); 1 lapsed. 10 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SURAJ PARK VIEW 2?
Google Maps has reviews of SURAJ PARK VIEW 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SURAJ PARK VIEW 2?
SURAJ PARK VIEW 2 by SURAJ ESTATE DEVELOPERS LTD is in Dadar West, Mumbai (pincode 400028), near Shivaji Park, Prabhadevi, Mahim, Maharashtra, and is registered on MahaRERA as P51900047891, per GharKundli's check of MahaRERA records. Its boundaries filed there include ANANT PATIL MARG.
How many homes are in SURAJ PARK VIEW 2?
According to GharKundli's check of MahaRERA records (updated November 2026), SURAJ PARK VIEW 2 has 72 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.
When was SURAJ PARK VIEW 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SURAJ PARK VIEW 2 was registered on MahaRERA on 1 December 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SURAJ PARK VIEW 2?
4 court cases are listed for SURAJ PARK VIEW 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SURAJ PARK VIEW 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SURAJ ESTATE DEVELOPERS LTD, which has 14 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SURAJ PARK VIEW 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Dadar West
- ARYAVRAT PROJECT
- YASH TRINITY
- Sigma Garnet
- AHILYA
- SAI ARADHYA
- VASANT PRABHA
- BUILDARCH SAKURA
- SAMARTHA HEIGHTS
Other projects by SURAJ ESTATE DEVELOPERS LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.