Hari Smruti CHS
by RAMNIYATI ADITYA DEVELOPERS LLP · Dahisar East, Mumbai 400092Also near Borivali West, Lower Parel, Babhai Naka
What’s in the report? →Possession date of Hari Smruti CHS (MahaRERA P51800010736): 30 December 2025, moved from 18 August 2022 (40 months later), and it has already passed. It has 66 homes (1 BHK, 2 BHK and 3 BHK, 440–1585 sq ft carpet), 75% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800010736. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800010736, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Hari Smruti CHS?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Hari Smruti CHS has moved
18 August 2022
Completion date given when the project was registered
31 December 2024
Extended at the builder's request (MahaRERA application EXT51800011555)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2024”
30 December 2025
Extended at the builder's request (MahaRERA application EXT51800024907)
Reason the builder gave MahaRERA: “Due to shortage of material and labor not able to complete please grant us extension till 30/12/2025”
Source: Hari Smruti CHS’s extension records on MahaRERA (P51800010736), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Hari Smruti CHS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800010736
- Status
- Lapsed (registration period ended)
- Builder
- RAMNIYATI ADITYA DEVELOPERS LLP
- Location
- Dahisar East, Mumbai · 400092
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- August 2022
- Latest completion date
- December 2025
- Delay so far
- 40 months
- Homes
- 66
- Sold or booked
- 75%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Hari Smruti CHS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Hari Smurti CHS-Redevelopment project | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Hari Smurti CHS-Redevelopment project: covers GROUND + 20 UPPER FLOORS
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hari Smruti CHS every 1–2 months.
Hari Smruti CHS: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 482 – 1,585 | 33 |
| Shops | 144 – 537 | 21 |
| Office Space | 214 – 707 | 17 |
| 3 BHK | 738 – 1,585 | 17 |
| 1 BHK | 440 – 1,030 | 16 |
- Buildings: Hari Smurti CHS-Redevelopment project (20 floors, 104 units)
- Land: 1,200 sq m (about 0.3 acres) · sanctioned built-up 1,175 sq m
- Land, as filed: 554B
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Sahakar Developers (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 24 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Hari Smruti CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Hari Smruti CHS: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Hari Smruti CHS
What is the possession date of Hari Smruti CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Hari Smruti CHS in Dahisar East, Mumbai is 30 December 2025 — 40 months later than 18 August 2022, the date given at registration. That date has already passed.
The date has already moved 40 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Hari Smruti CHS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Hari Smruti CHS's builder has filed on MahaRERA, the official one, is 30 December 2025, already 40 months later than the 18 August 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Hari Smruti CHS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Hari Smruti CHS's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2024, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2024"; to 30 December 2025, giving the reason "Due to shortage of material and labor not able to complete please grant us extension till 30/12/2025".
What is the RERA number of Hari Smruti CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Hari Smruti CHS in Dahisar East, Mumbai is P51800010736.
Is Hari Smruti CHS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hari Smruti CHS is registered as P51800010736 and its status is "Lapsed (registration period ended)".
What is the current construction status of Hari Smruti CHS? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Hari Smruti CHS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Hari Smurti CHS-Redevelopment project is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Hari Smruti CHS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Hari Smruti CHS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Hari Smruti CHS is registered on MahaRERA as P51800010736, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 40 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Hari Smruti CHS?
Hari Smruti CHS isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Hari Smruti CHS are 440 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Hari Smruti CHS?
For a flat in Hari Smruti CHS (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Hari Smruti CHS received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Hari Smruti CHS isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Hari Smruti CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), Hari Smruti CHS's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Hari Smruti CHS a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Hari Smruti CHS is a redevelopment: 40 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Hari Smruti CHS uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Hari Smruti CHS was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Hari Smruti CHS's possession date changes?
The latest dates are on Hari Smruti CHS's MahaRERA page (P51800010736). GharKundli's Kundli Watch sends a free WhatsApp update on Hari Smruti CHS every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Hari Smruti CHS have?
According to GharKundli's check of MahaRERA records (updated October 2026), Hari Smruti CHS has one building filed: Hari Smurti CHS-Redevelopment project with 20 floors and 104 units.
What are the flat sizes (carpet area) in Hari Smruti CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Hari Smruti CHS: 2 BHK: 482 to 1585 sq ft carpet (33 homes); 3 BHK: 738 to 1585 sq ft carpet (17 homes); 1 BHK: 440 to 1030 sq ft carpet (16 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Hari Smruti CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), Hari Smruti CHS stands on 1,200 sq m of land (about 0.3 acres), with 1,175 sq m of sanctioned built-up area.
What is the track record of Hari Smruti CHS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sahakar Developers (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 24 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Hari Smruti CHS?
Google Maps has reviews of Hari Smruti CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Hari Smruti CHS?
Hari Smruti CHS by RAMNIYATI ADITYA DEVELOPERS LLP is in Dahisar East, Mumbai, pincode 400092 (near Borivali West, Lower Parel, Babhai Naka), Maharashtra, and is registered on MahaRERA as P51800010736, per GharKundli's check of MahaRERA records. Its land is filed as 554B. GharKundli lists all 362 MahaRERA projects in Borivali West (400092).
How many flats are in Hari Smruti CHS, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Hari Smruti CHS has 66 homes in 1 tower registered on MahaRERA, and 75% of them are sold or booked.
When was Hari Smruti CHS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Hari Smruti CHS was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Does Hari Smruti CHS have any legal issues or court cases?
No court cases are listed for Hari Smruti CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Hari Smruti CHS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAMNIYATI ADITYA DEVELOPERS LLP.
Check it yourself on MahaRERA
- How to check the possession date of Hari Smruti CHS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data